05000293/LER-2013-003, Regarding Loss of Off-Site Power Events Due to Winter Storm Nemo
| ML13114A293 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 04/08/2013 |
| From: | Dodds R Entergy Nuclear Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 2.13.032 LER 13-003-00 | |
| Download: ML13114A293 (8) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(ix)(A) 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
| 2932013003R00 - NRC Website | |
text
SEn tergy Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Ralph A. Dodds, III Director, Nuclear Safety Assurance April 8, 2013 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555
SUBJECT:
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 Licensee Event Report 2013-003-00, Loss of Off-Site Power Events Due to Winter Storm Nemo LETTER NUMBER: 2.13.032
Dear Sir or Madam:
The enclosed Licensee Event Report (LER) 2013-003-00, "Loss of Off-Site Power Events Due to Winter Storm Nemo" is submitted in accordance with 10 CFR 50.73.
This letter contains no commitments.
Please do not hesitate to contact Mr. Joseph R. Lynch, (508) 830-8403, if there are any questions regarding this submittal.
Sincerely, Ralph A. Dodds, III : Licensee Event Report 2013-003-00, Loss of Off-Site Power Events Due to Winter Storm Nemo (5 pages)
PNPS Letter 2.13.032 Page 2 of 2 cc:
Mr. William M. Dean Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-1415 INPO Records 700 Galleria Parkway Atlanta, GA 30399-5957 Mr. Richard V. Guzman, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8-C2 11555 Rockville Pike Rockville, MD. 20852 USNRC Senior Resident Inspector Pilgrim Nuclear Power Station
Attachment I Letter Number 2.13.032 Licensee Event Report 2013-003-00 Loss of Off-Site Power Events Due to Winter Storm Nemo (5 Pages)
NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 10/31/2013 (10-2010)
Estimated burden per response to comply with this mandatory collection request: 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />.
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA/Privacy Service Branch (T-5 F53), U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to LICENSEE EVENT REPORT (LER) infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503.
If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
- 3. PAGE Pilgrim Nuclear Power Station 05000293 1 OF 5
- 4. TITLE Loss of Off-Site Power Events Due to Winter Storm Nemo
- 5. EVENT DATE
- 6. LER NUMBER
- 7. REPORT DATE
- 8. OTHER FACILITIES INVOLVED RE FACILITY NAME DOCKET NUMBER MONTH DAY YEAR YEAR SEQUENTIAL V
MONTH DAY YEAR N/A NUMBER N
FACILITY NAME DOCKET NUMBER 02 08 2013 2013 003 00 4
08 2013 NFA NAEDCETNME
- 9. OPERATING MODE
- 11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply) 20.2201(b) 20.2203(a)(3)(i) 50.73(a)(2)(i)(C) 50.73(a)(2)(vii)
N 20.2201(d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A) 20.2203(a)(1) 20.2203(a)(4) 50.73(a)(2)(ii)(B) 50.73(a)(2)(viii)(B) 20.2203(a)(2)(i) 50.36(c)(1)(i)(A) 50.73(a)(2)(iii) 50.73(a)(2)(ix)(A) 20.2203(a)(2)(ii) 50.36(c)(1 )(ii)(A) x 50.73(a)(2)(iv)(A) 50.73(a)(2)(x)
- 10. POWER LEVEL 20.2203(a)(2)(iii) 50.36(c)(2) 50.73(a)(2)(v)(A) 73.71 (a)(4) 20.2203(a)(2)(iv) 50.46(a)(3)(ii)
B 73.71 (a)(5) 20.2203(a)(2)(v) 50.73(a)(2)(i)(A) x 50.73(a)(2)(v)(B)
=OTHER 85%
20.2203(a)(2)(vi) 50.73(a)(2)(i)(B) 50.73(a)(2)(v)(C)
Specify in Abstract below or in H-50.73(a)(2)(v)(D)
BACKGROUND:
Pilgrim Station is connected to the transmission lines through a 345KV ring bus located within the station's 345KV switchyard. The 345KV ring bus connects the output of the main transformer, the startup transformer (SUT), Line 355, and Line 342. There are four gas circuit breakers which comprise Pilgrim's 345KV ring bus:
ACB-1 02, ACB-1 03, ACB-104 and ACB-105.
Line 355 is a two terminal line which connects Pilgrim to National Grid's Bridgewater Station and is connected to ACB-102 and ACB-1 05. Line 342 is a three terminal line, which connects Pilgrim to the Canal Power Plant's Switchyard in Sandwich, MA and to Auburn Street Station Switchyard in Whitman, MA. The Canal Switchyard is owned and operated by NSTAR and Auburn Street Station Switchyard is owned and operated by National Grid.
Pilgrim's ACB-103 and ACB-104 connect Line 342 to the plant's switchyard. The 345KV system is the Pilgrim Station output power connection and is the preferred off-site power source via the SUT.
The 345KV ring bus design locates the power transmission lines such that a failure of any one line will not result in the loss of the other line. Specifically, with both transmission lines in service, a failure of either 345KV line will not result in a main generator trip, a SUT trip, or a failure of the other 345KV line. Either of the two 345KV lines is capable of carrying full station output and supplying station loads via the SUT.
The 345KV protective relay system is designed and coordinated to isolate system disturbances and minimize the impact to the overall transmission system. The protective systems are comprised of a primary and secondary protection scheme and are divided into four zones of protection.
" The main transformer (bounded by ACB-104 and ACB-105)
" The SUT (bounded by ACB-102 and ACB-103)
" Line 355 (bounded by ACB-102 and ACB-105 and Bridgewater Station)
" Line 342 (bounded by ACB-103 and ACB-104 and Auburn Street Station Street and Canal Stations)
When ACB-104 and ACB-105 open, the main transformer is isolated from the 345KV transmission system thus resulting in a generator full load reject event.
In addition to the preferred 345KV off-site power lines, Pilgrim has a secondary off-site power source, a 23KV line from NSTAR's Manomet Substation that provides power to a shutdown transformer (SDT).
During normal station start-ups and shutdowns, the station's 4160V demands are supplied by the SUT. Once the station main generator is synchronized to the 345KV transmission system, the station unit auxiliary transformer (UAT) supplies all station 4160V demands, with the SUT maintained in standby, ready to provide 4160V power if necessary.
In anticipation of a major snow storm impacting Pilgrim Station (PNPS) on February 8, 2013, Operations entered Procedure 2.1.37 (Coastal Storm Preparations). Procedure 2.1.42 (Operation During Severe Weather) and EN-EP-302 (Severe Weather Response, currently, EN-FAP-EP-010) at 0800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> on February 7, 2013. At 1021 hours0.0118 days <br />0.284 hours <br />0.00169 weeks <br />3.884905e-4 months <br /> on February 8th, Station Risk was elevated to YELLOW due to the winter storm warning (severe weather).
During the storm on February 8, meteorological instruments at PNPS recorded sustained wind speeds between 42 and 49 mph through 2338 hours0.0271 days <br />0.649 hours <br />0.00387 weeks <br />8.89609e-4 months <br /> at which time the plant information (PI) system stopped recording weather data until 1840 hours0.0213 days <br />0.511 hours <br />0.00304 weeks <br />7.0012e-4 months <br /> the following day. The wind direction was predominantly from the ocean toward the switchvard durinq the storm.U.S. NUCLEAR REGULATORY COMMISSION (10-2010)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE SEQUENTIAL REV Pilgrim Nuclear Power Station 05000293 NUMBER NO.
3 OF 5 2013-003 00
EVENT DESCRIPTION
On Friday, February 8, 2013, at 2018 hours0.0234 days <br />0.561 hours <br />0.00334 weeks <br />7.67849e-4 months <br />, the shutdown transformer (SDT) was declared inoperable due to repeated off-site 23KV Trouble/Trip Bypass alarms and reports from NSTAR regarding the power loss and restoration events on the Line via the Manomet Substation.
On February 8th, two line faults occurred on both 345KV transmission lines connected to the PNPS ring bus. At 2102 hours0.0243 days <br />0.584 hours <br />0.00348 weeks <br />7.99811e-4 months <br /> a major fault occurred on off-site Line 342 which remained de-energized for the remainder of the storm. At 2117 hours0.0245 days <br />0.588 hours <br />0.0035 weeks <br />8.055185e-4 months <br /> a fault on Line 355 occurred resulting in a full load reject of the PNPS generator, a subsequent reactor scram, and loss of the SUT. Emergency diesel generators (EDGs) automatically started and provided power to safety buses A5 and A6. Groups 1, 11, and VI isolations went to completion. Reactor Core Isolation Cooling (RCIC) system was placed in service to maintain reactor vessel water level. High Pressure Coolant Injection (HPCI) system was placed in service to control reactor pressure. All systems performed as designed to bring the reactor to Mode 3, including initiation of reactor water cleanup isolation, reactor building isolation system, and standby gas treatment system.
At 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />, an Unusual Event was declared (EAL SU 1.1) for loss of off-site power to Emergency Busses.
At 2211 hours0.0256 days <br />0.614 hours <br />0.00366 weeks <br />8.412855e-4 months <br />, off-site line 355 was restored and ACB-102 was closed manually to reenergize the SUT.
At 2340 hours0.0271 days <br />0.65 hours <br />0.00387 weeks <br />8.9037e-4 months <br />, a 'B' phase fault on the SUT bus work tripped the SUT bus lockout relay. Walkdowns of the switchyard were conducted by Maintenance and Engineering to assess the condition of the SUT bus. The relays that initiated the bus trip indicated the fault was within the SUT protection scheme, but external to the SUT. Breaker ACB-1 02 was closed at 1809 hours0.0209 days <br />0.503 hours <br />0.00299 weeks <br />6.883245e-4 months <br /> on February 9th.
At 0813 hours0.00941 days <br />0.226 hours <br />0.00134 weeks <br />3.093465e-4 months <br /> on February 9th, NSTAR reenergized Line 355 and the SUT was energized and non safety related buses Al, A2, A3, A4 were energized from the SUT commencing at 1815.
At 0400 on February 10, off-site power was restored to safety-related 4160V bus A5 through the SUT via a single 345KV line. At 0830 hours0.00961 days <br />0.231 hours <br />0.00137 weeks <br />3.15815e-4 months <br />, off-site power was restored to safety-related 4160V bus via A6 through SUT.
The EDGs were secured and were on standby. Residual heat removal was in shutdown cooling mode maintaining the reactor in cold shutdown. Fuel pool cooling was in service with fuel pool temperatures trending down.
Effective at 1055 hours0.0122 days <br />0.293 hours <br />0.00174 weeks <br />4.014275e-4 months <br /> on February 10, 2013, Pilgrim terminated the Unusual Event and transitioned to recovery.
At 1401 hours0.0162 days <br />0.389 hours <br />0.00232 weeks <br />5.330805e-4 months <br /> on February 10th, with all control rods fully inserted and the reactor in cold shutdown conditions, the plant experienced a second loss of off-site power with a flashover fault on the B phase bus work of the SUT due to salt contaminated ice bridging on the phase insulator. This resulted in the tripping of the breaker ACB-102 and loss of power to 4160V busses. Both EDGs auto-started as designed and provided power to the emergency buses. This loss of off-site power resulted in de-energization of both reactor protection system (RPS) channels resulting in a reactor scram signal and loss of Shutdown Cooling. At 1426 hours0.0165 days <br />0.396 hours <br />0.00236 weeks <br />5.42593e-4 months <br />, Shutdown Cooling was returned to service. All other plant systems responded as designed. Station personnel established back-up power to A5 and A6 buses in accordance with plant procedures. On February 12, at 0405 hours0.00469 days <br />0.113 hours <br />6.696429e-4 weeks <br />1.541025e-4 months <br /> off-site power was restored to the non safety buses via the Main/ Unit Aux Transformers. At 0601 hours0.00696 days <br />0.167 hours <br />9.937169e-4 weeks <br />2.286805e-4 months <br /> on February 12th, off-site power was restored to safety bus A6 through the Main/Unit Aux Transformers. Off-site power was restored to all 4160V buses through the SUT as of 2147 hours0.0248 days <br />0.596 hours <br />0.00355 weeks <br />8.169335e-4 months <br /> on February 12. The plant returned to power operation on February 15, 2013.U.S. NUCLEAR REGULATORY COMMISSION (10-2010)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE YEAR SEQUENTIAL REV Pilgrim Nuclear Power Station 05000293 NUMBER NO.
4 OF 5 2013-003 00
CAUSE
The coincident loss of transmission Lines 342 and 355 from faults external to the Pilgrim Nuclear Power Station switchyard due to the winter storm resulted in the loss of offsite power, full load rejection, and reactor scram.
The subsequent flashovers in the switchyard were due to snow and ice buildup on insulators and electrical distribution components.
CONTRIBUTING CAUSES
PNPS procedure 2.1.42, Operation During Severe Weather, provides limited guidance for Operations to determine which severe snow storms are most likely to challenge Pilgrim switchyard reliability.
Corrective actions to preclude recurrence taken in response to prior LER 2008-006-00 and LER 2008-007-00, Loss of SUT on line 355 flashover and ACB-1 05 flashover, and plant trip did not prevent recurrence.
Previously identified internal Operating Experience (OE) was not successfully utilized to direct the removal of snow and ice from insulators on the SUT prior to reenergizing.
CORRECTIVE ACTIONS
The following corrective actions were completed to address the LOOP and flashover events prior the restart of Pilgrim Station:
The component of the capacitor coupled voltage transformer (CCVT) that was damaged due to the flashover fault was repaired.
Pilgrim reviewed LOOP events with NSTAR to improve reliability of service to the SUT.
Additional corrective actions included in the corrective action program are as follows:
Procedural guidance containing a systematic process for removal and restoration of bus sections during and following blizzard conditions will be developed and implemented. This includes all 345KV and 23KV power lines.
Procedural guidance for de-icing insulating material susceptible to a flashover event in the switchyard following blizzard conditions will be developed and implemented.
SAFETY CONSEQUENCES
The Loss of Off-Site Power (LOOP) event is analyzed in the Updated Final Safety Analysis Report (UFSAR) and assumes loss of both 345 KV and 23 KV (preferred and secondary) sources coincident with a design basis accident (DBA). The design imposes a 10 second delay in re-energizing the 4160V Emergency Buses required to mitigate the DBA. In cases where coincident loss of an EDG presents a bounding condition, the affected safety bus is not assumed to be picked up by the shutdown transformer (SDT). The bounding condition in which all off-site power and onsite AC (EDGs) sources would be lost is a Station Blackout (SBO) transient event (10 CFR 50.63). Pilgrim is designed to recover from the SBO event by having a separate SBO diesel generator capable of providing power to the required safety buses to shutdown the plant and maintain it in a safe condition. Thus, the LOOP events experienced by Pilgrim are within the analyzed conditions and plant systems responded as desiqned.U.S. NUCLEAR REGULATORY COMMISSION (10-2010)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE SEQUENTIAL REV Pilgrim Nuclear Power Station 05000293 NUMBER NO.
5 OF 5 2013-003 00 During and following the storm, operators were able to maintain safe shutdown conditions (reactivity control, reactor water inventory, decay heat removal, etc.). While loss of power to non-safety related spent fuel cooling was a key consideration, time-to-boil never became an overriding concern with respect to reenergizing buses and there was no freshly discharged spent fuel in the pool. The most recent freshly discharged fuel was almost 23 months old, and the time to boil was approximately seven days upon loss of fuel pool cooling. The spent fuel pool temperature was less than 105 degrees F.
The EDGs started and loaded as expected following each loss of SUT event. The amount of fuel onsite initially was sufficient to operate the EDGs for 7 days (under LOCA conditions) and the SBO DG was always available.
Based on the challenge to safety systems during and following the event, Conditional Core Damage Frequency (CCDF) of the event was estimated to be 1.8E-5.
Throughout these events there was no adverse impact on the public health and safety.
PREVIOUS EVENTS:
The most recent LOOP events at Pilgrim Station reported as LER are as follows:
LER 2008-006-00, Automatic Scram Resulting from Switchyard Breaker Fault During Winter Storm, dated February 12, 2009.
LER 2008-007-00, Momentary Loss of all 345KV Off-Site Power to the Startup Transformer from Switchyard Breaker Fault, dated February 12, 2009.
ENERGY INDUSTRY IDENTIFICATION SYSTEM (EIIS) CODES:
COMPONENTS CODES Transformer (Startup AC) Bus XFMR SYSTEMS Switchyard System (Startup Transformer)
FK ESF Actuation (RPS, PCIS, RBIS)
JE Main Generator Output Power System EL Medium Voltage Power System-Class 1 E (4KV)
EB
REFERENCES:
Condition Report CR-PNP-2013-0798, Loss of Off-Site Power