Finding | |
---|---|
Title | Blocked Drains in the 480 Volt Switchgear Room |
Description | The inspectors identified a Green finding (FIN) because Entergy allowed the Unit 3 480 volt switchgear room floor drains to become blocked such that they could not mitigate an internal flood postulated in Action and Condition Tracking Form 95-14218. Specifically, if both service water (SW) relief valves in the 480 volt switchgear room lifted, their flow rate would be greater than the as-found drain flow rate. This finding does not involve enforcement action because no violation of regulatory requirement was identified. This finding was more than minor because it was associated with the protection against external factors attribute of the Mitigating Systems cornerstone, and adversely affected the cornerstone objective to ensure the capability of systems to respond to initiating events to prevent undesirable consequences. Specifically, the Unit 3 480 volt switchgear room floor drains were not capable of mitigating an internal flood hazard to prevent damage to the 480 volt switchgear, potentially resulting in core damage. In accordance with IMC 0609.04, Initial Characterization of Findings, and Exhibit 4, External Events Screening Questions, of IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, issued June 19, 2012, the inspectors determined this finding required a detailed risk assessment. A detailed risk assessment was conducted using the Unit 3 SDP External Event Notebook, which determined that there was a change in core damage frequency of low E-8 per reactor year (an increase in 1 in 100 million reactor years). Therefore, this performance deficiency was of very low safety significance (Green). The inspectors determined the finding does not have a cross-cutting aspect. Although Entergy did not thoroughly evaluate the Unit 2 blocked floor drain issue in 2011 to ensure the resolution addressed extent of condition, Entergy has improved their extent of condition evaluation guidance since 2012. |
Site: | Indian Point |
---|---|
Report | IR 05000286/2015003 Section 1R06 |
Date counted | Sep 30, 2015 (2015Q3) |
Type: | Finding: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.06 |
Inspectors (proximate) | A Bolger A Burritt B Pinson G Newman H Gray J Furia J Stewart O Masnyk-Bailey S Barr S Rich |
INPO aspect | |
' | |