Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
PNO-I-99-043, on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power16 September 1999PNO-I-99-043:on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power
IR 05000219/19980124 March 1999Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items
IR 05000219/199800925 November 1998Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant SupportShutdown Margin
High Radiation Area
Non-Destructive Examination
Offsite Dose Calculation Manual
Hydrostatic
Temporary Modification
Foreign Material Exclusion
Operability Determination
Battery sizing
Maintenance Rule Program
ML20196C60725 November 1998Notice of Violation from Insp on 980914-1025.Violation Noted:On 981014,security Force Vehicle Escort Left Non licensee-designated Vehicle Unattended in Protected Area & Failed to Ensure That Vehicle Ignition Locked & Key Removed
IR 05000219/199800820 October 1998Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant SupportSafe Shutdown
Shutdown Margin
Temporary Modification
Emergency Lighting
Systematic Assessment of Licensee Performance
Operability Determination
Earthquake
Fire Protection Program
Coast down
IR 05000219/199800526 August 1998Insp Rept 50-219/98-05 on 980614-0726.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant SupportHigh Radiation Area
Temporary Modification
Condition Adverse to Quality
IR 05000219/199809917 July 1998SALP Rept 50-219/98-99 for 961201-980613Fire Barrier
Temporary Modification
Missed surveillance
Systematic Assessment of Licensee Performance
Fire Protection Program
IR 05000219/19980072 July 1998Insp Rept 50-219/98-07 on 980615-19.No Violations Noted. Major Areas Inspected:Status of Plant motor-operated Valve Program to Determine Acceptability for Closure of NRC Review Under GL 89-10Stroke time
Anchor Darling
Operability Determination
Weak link
ML20249B36615 June 1998Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Prior to 980304, Licensee Failed to Establish Adequate Design Control Measures to Verify Adequacy of Design Voltage
ML20237E44910 June 1998EN-98-047:on 980615,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on Severity Level III Problem Involving Inoperability of Three of Five Automatic Depressurization Valves
ML20217F66422 April 1998Insp Rept 50-219/98-80 on 980223-0313 & 0330-0402.Violations Noted.Major Areas Inspected:EngineeringSafe Shutdown
Stroke time
Temporary Modification
Power Operated Valves
ML20217F64922 April 1998Notice of Violation from Insp on 980223-0313 & 0330-0402. Violations Noted:On 980226,seismic Deficiency W/Containment Spray Heat Exchanger,That Had Been Identified in Late 1996 by Licensee,Had Not Been Adequately Corrected
ML20216H19115 April 1998Insp Rept 50-219/98-04 on 980226-0318.Violations Noted.Major Areas Inspected:Operations,Maint & Plant SupportOffsite Dose Calculation Manual
ML20216H17015 April 1998Notice of Violation from Insp on 980226-0318.Violations Noted:Since Initial Plant Operation,Operators Implemented Procedure 307,isolation Condenser Sys,Permitting Fill & Make Up to Isolation Condensers During Normal Plant Operations
ML20216J01814 April 1998Notice of Violation from Insp on 971229-980208.Violation Noted:Written SE Was Not Performed to Provide Bases for Determination That Change in Facility as Described in SAR Did Not Involve USQTemporary Modification
IR 05000219/19970084 December 1997Insp Rept 50-219/97-08 on 971020-24.No Violations Noted. Major Areas Inspected:Onsite Emergency PlanLocked High Radiation Area
Earthquake
ML20199G78817 November 1997Notice of Violation from Insp on 970707-970824.Violation Noted:In Oct 1993,vendor Specification for Emergency Svc Water Pump Bowl Assemblies Was Changed from Cast Iron to Stainless SteelCondition Adverse to Quality
PNO-I-97-045, on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR4 August 1997PNO-I-97-045:on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR
IR 05000219/199700429 July 1997Insp Rept 50-219/97-04 on 970526-0706.Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant SupportHigh Radiation Area
Grab sample
NJPDES
Temporary Modification
Job Performance Measure
Process Control Program
Siren
IR 05000219/199700517 July 1997Insp Rept 50-219/97-05 on 970407-11.No Violations Noted. Major Areas Inspected:EngineeringAnchor Darling
Squib
ML20141G9433 July 1997Insp Rept 50-219/97-03 on 970414-0525.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support
ML20141G9403 July 1997Notice of Violation from Insp on 970414-0525.Violation Noted:On 970423,CROs Placed a & B Loops of Shutdown Cooling Sys in Svc W/O Placing Suction Pressure Interlocks in Svc for a & B Pumps by Opening Ps Isolation Valves
IR 05000219/199700219 May 1997Insp Rept 50-219/97-02 on 970224-0413.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant SupportHigh Radiation Area
Grab sample
Offsite Dose Calculation Manual
Temporary Modification
ML20141J52219 May 1997Notice of Violation from Insp on 970224-0413.Violation Noted:Permanent Change,Dec 95,made to Facility,As Described in SAR Involving Removal of Isolation Condenser Radiation Monitors W/O Considering All Relevant Portions of SAR
PNO-I-97-024, on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem23 April 1997PNO-I-97-024:on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem
PNO-I-97-022, on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention10 April 1997PNO-I-97-022:on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention
ML20137E94121 March 1997Notice of Violation from Insp on 970113-0223.Violation Noted:Procedure 108.7, Lockout/Tagout Procedure, Rev 4, Did Not Include Appropriate Quantitative or Qualitative Acceptance Criteria
ML20137E94921 March 1997Insp Rept 50-219/97-01 on 970113-0223.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant SupportTemporary Modification
Double blade guide
Systematic Assessment of Licensee Performance
Flow Induced Vibration
Operability Assessment
IR 05000219/19960999 January 1997SALP Rept 50-219/96-99 for Oyster Creek Nuclear Generating Station for 950625-961130High winds
Temporary Modification
Scram Discharge Volume
Systematic Assessment of Licensee Performance
Biofouling
Fire Protection Program
ML20133D6782 January 1997Notice of Violation from Insp on 961021-1201.Violation Noted:Written Safety Evaluation Was Not Performed to Provide Bases for Determination That Change to Station Procedure 336.3 Did Not Involve Unreviewed Safety Question
PNO-I-96-078, on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event29 October 1996PNO-I-96-078:on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event
IR 05000219/199601027 September 1996Insp Rept 50-219/96-10 on 960923-27.No Violations Noted. Major Areas Inspected:Radiological Source Term Assessment, Results of Exposure Reduction Initiatives & Evidence of Station ALARA ProgramHigh Radiation Area
Design basis earthquake
Earthquake
Scaffolding
IR 05000219/19960112 January 1996Insp Rept 50-219/96-11 on 961021-1201.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant SupportHydrostatic
Temporary Modification
Operability Determination
IR 05000219/199209926 January 1994SALP Rept 50-219/92-99 for Period 920719-931211High Radiation Area
Temporary Modification
Systematic Assessment of Licensee Performance
Operability Determination
Fire Protection Program
ML20059B63323 December 1993Notice of Violation from Insp on 930927-1015.Violation Noted:All NRC Violations & Ten Licensee Event Repts Issued in 1992 & 1993 Did Not Receive Required Independent Safety Reviews
IR 05000219/199308122 December 1993Insp Rept 50-219/93-81 on 930927-1015.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance & Mgt & Corrective ActionsHot Short
Unanalyzed Condition
Commercial Grade Dedication
Hydrostatic
Temporary Modification
Emergency Lighting
Operability Determination
Earthquake
Scaffolding
IR 05000219/199302618 November 1993Insp Rept 50-219/93-26 on 931101-05.No Violations Noted. Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Access Control of Personnel & Packages & Vehicles
IR 05000219/199302418 November 1993Insp Rept 50-219/93-24 on 930921-1101.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support,Including Security & Emergency Preparedness & Safety Assessment/Quality Verification
ML20058A37912 November 1993Insp Rept 50-219/93-23 on 931018-20.Onsite Response to Exercise Scenario Was Good.Major Areas inspected:full- Participation Ingestion Pathway Emergency Preparedness Exercise
ML20059M3219 November 1993EN-93-081A:on 930812,notice of Proposed Imposition of Civil Penalty in Amount of $75,000 Issued to Licensee.Action Based on Five Radiological Controls Violations
IR 05000219/19930259 November 1993Insp Rept 50-219/93-25 on 931018-22.No Violations Noted. Major Areas Inspected:Design Mods & Engineering Support
ML20059F62528 October 1993Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation EventCondition Adverse to Quality
Job Performance Measure
IR 05000219/199301828 October 1993Insp Rept 50-219/93-18 on 930823-1020.No Violations Noted. Major Areas Inspected:Alara,Rirs,Qa Audits,Air & Swipe Sample Counting Facilities & Radiological Controls Organization Professional StaffingScaffolding
IR 05000219/199302019 October 1993Insp Rept 50-219/93-20 on 930816-930917.No Violations Noted. Major Areas Inspected:Radioactive Liquid & Gaseous Effluent Control Programs Including Mgt Controls & QA AuditsGrab sample
Offsite Dose Calculation Manual
IR 05000219/199302115 October 1993Insp Rept 50-219/93-21 on 930810-0920.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality VerificationTemporary Modification
Fire Watch
Hourly Fire Watch
Operability Assessment
ML20059A22015 October 1993Notice of Violation from Insp on 920719-0825.Violation Noted:Licensee Determined That Records Required to Be Maintained by Commission Regulations or License Conditions Not Complete & Accurate in All Matl Respects
IR 05000219/199301714 September 1993Exam Rept 50-219/93-17OL on 930810-12.Exam Results:All 16 Licensed Operators Passed All Portions of Exam That Was Administered & All Three Crews Performed Satisfactorily in SimulatorJob Performance Measure
ML20149D50213 September 1993Notice of Violation from Insp on 930629-0809.Violation Noted:On 930709,NRC Identified Condition Adverse to Quality That Had Existed Since 920709Condition Adverse to Quality
IR 05000219/199301110 September 1993Insp Rept 50-219/93-11 on 930629-0809.No Violations Noted. Major Areas Inspected:Day Shift & Back Shift Hours of Station ActivitiesHigh winds
Stroke time
NJPDES
GOTHIC
ML20149D70510 September 1993Notice of Violation from Insp on 930816-20.Violation Noted: as of 930820,appropriate Measures Were Not Established to Assure Adequate Quality Was Suitably Included in Documents for Procurement of Svcs