2CAN039602, Informs That ANO-2 Completed GL 89-10 Initial Implementation Commitments for Items a Through H & Suppls 1-7.Detailed Supporting Documentation Extensive & Available at ANO for NRC Review

From kanterella
(Redirected from ML20101E550)
Jump to navigation Jump to search
Informs That ANO-2 Completed GL 89-10 Initial Implementation Commitments for Items a Through H & Suppls 1-7.Detailed Supporting Documentation Extensive & Available at ANO for NRC Review
ML20101E550
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 03/19/1996
From: Mims D
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
2CAN039602, 2CAN39602, GL-89-10, NUDOCS 9603250107
Download: ML20101E550 (2)


Text

.

O

= ENTERGY cemu og ma m Revu AR 723m

.o.. ioc.

Td 501 M2 5007 l

l March 19,1996 l

2CAN039602 U. S. Nuclear Regulatory Commission Document Control Desk Mail Station PI-137 Washington, DC 20555

Subject:

Arkansas Nuclear One - Unit 2 1 Docket No. 50-368  !

License No. NPF-6 Completion of Generic Letter 89-10 Commitments for ANO-2 i

Gentlemen:  ;

l Generic Letter (GL) 89-10, " Safety-Related Motor-Operated Valve Testing and Surveillance," dated June 28,1989, and Supplements 1 through 7, provide the scope of the NRC requirements regarding motor-operated valve (MOV) testing and analysis. The generic letter requested licensees to complete certain actions. This letter is submitted for Arkansas Nuclear One, Unit 2 (ANO-2) in accordance with reporting requirement "m" of GL 89-10 to inform you that ANO-2 has completed its GL 89-10 initial implementation commitments for  !

items "a" through "h" and supplements 1-7, as applicable to ANO-2. The detailed supporting documentation is extensive and is available at ANO for review by the NRC.

The generic letter required each licensee to notify the NRC in writing within 30 days after completing the actions described in the first paragraph of item "i." which states that completion of design basis reviews, analyses, verifications, tests, and inspections must be completed within five years or three refueling outages of the date of the generic letter, whichever is later. The completion date for ANO was extended based on justification provided to the NRC in a letter dated March 19,1993 (0CAN039308). The new completion date for ANO-2 was determined to be 120 days following completion of refueling outage 2R11. Refueling outage 2R11 concluded on November 25,1995.

The initial implementation commitments for ANO-1 have already been completed.

l Notification was provided to the NRC via a letter dated August 4,1995 (ICAN089502).

l l Should you have questions or comments, please contact me.

l t 250014 9603250107 960319

.' M 3 9

PDR ADOCK 05000368 e p PDR l

. U. S. NRC

  • March 19,1996 1

2C4N039602 Page 2 Very truly yours,

/b, 9, AtMS l l

Dwight C. Mims ,

Director, Nuclear Safety DCM/dwb 1

cc: Mr. Leonard J. Callan i Regional Administrator j U. S. Nuclear Regulatory Commission l Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One l P.O. Box 310 l London, AR 72847 l Mr. George Kalman i NRR Project Manager Region IV/ANO-1 & 2

U. S. Nuclear Regulatory Commission NRR Mail Stop 13-H-3 One White Flint North 11555 Rockville Pike Rockville, MD 20852 l