ML14266A423

From kanterella
Jump to navigation Jump to search
IR 050003312014010, on 04/21/2014 - 09/03/2014; Duane Arnold Energy Center (Daec); Problem Identification and Resolution
ML14266A423
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 09/19/2014
From: O'Brien K
Division of Reactor Safety III
To: Vehec T
NextEra Energy Duane Arnold
David J. Oliver
References
IR-2014-010
Download: ML14266A423 (17)


See also: IR 05000331/2014010

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

September 19, 2014

Mr. Thomas Vehec

Vice President

NextEra Energy Duane Arnold, LLC

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT: DUANE ARNOLD ENERGY CENTER - NRC FOLLOW-UP INSPECTION

REPORT 05000331/2014010 AND NOTICE OF VIOLATION.

Dear Mr. Vehec:

On September 3, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a follow-up

inspection conducted during the week of April 21, 2014, at your Duane Arnold Energy Center

(DAEC). The purpose of the inspection was to evaluate corrective actions for recent Non-Cited

Violations (NCVs) associated with the discovery of submerged safety-related cables in

embedded conduits. The enclosed report presents the results of this inspection, which were

discussed on September 3, 2014, with Mr. G. Pry, and other members of your staff.

This inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions in your license.

Within these areas, the inspection consisted of a selected examination of procedures and

representative records, observations of activities, and interviews with personnel.

Based on the results of this inspection, the NRC has identified an issue that was evaluated

under the risk significance determination process as having very low safety significance

(Green). The NRC has also determined that a violation is associated with this issue. This

violation was evaluated in accordance with the NRC Enforcement Policy. The current

Enforcement Policy is included on the NRCs web site at

(http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html).

The violation is cited in the enclosed Notice of Violation (Notice) and the circumstances

surrounding it are described in detail in the subject inspection report. The violation is being

cited in the Notice because DAEC had failed to restore compliance, or demonstrate objective

evidence of plans to restore compliance in a reasonable period following documentation of four

associated NCVs issued from January 30, 2013, to December 5, 2013.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response to the Notice. The NRCs

review of your response to the Notice will also determine whether further enforcement action is

necessary to ensure your compliance with regulatory requirements.

T. Vehec -2-

In addition, if you disagree with the cross-cutting aspect assigned to the finding in this report,

you should provide a response within 30 days of the date of this inspection report, with the basis

for your disagreement, to the Regional Administrator, Region III, and the NRC Resident

Inspector at Duane Arnold Energy Center.

In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's Rules of Practice, a copy of

this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the NRC's Agencywide Documents

Access and Management System (ADAMS). ADAMS is accessible from the NRC web site at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not

include any personal privacy or proprietary information so that it can be made available to the

Public without redaction.

Sincerely,

/RA/

Kenneth G. OBrien, Director

Division of Reactor Safety

Docket No. 50-331

License No. NPF-49

Enclosure:

Inspection Report 05000331/2014010;

w/Attachment: Supplemental Information

cc w/encl: Distribution via LISTSERV

NOTICE OF VIOLATION

NextEra Energy Duane Arnold Docket No. 50-331

Duane Arnold Energy Center License No. NPF-49

During an NRC inspection conducted from April 21 2014, to April 25, 2014, with continued in-

office review through September 3, 2014, a violation of NRC requirements was identified. In

accordance with the NRC Enforcement Policy, the violation is listed below:

Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix B, Criterion XVI,

Corrective Action, states, in part, that measures shall be established to assure that

conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations,

defective material and equipment, and non-conformances are promptly identified and

corrected.

Contrary to the above, from October 16, 2012, to July 10, 2014, the licensee did not

assure that conditions adverse to quality were corrected. Specifically, the licensee failed

to remove water from nine conduits containing safety-related cables and the cables were

not qualified for continuous exposure to water. Safety-related components served by

these cables were essential safety busses, residual heat removal pumps, both

emergency diesel generator control and output power, and high pressure coolant

injection.

This violation is associated with a (Green) Significant Determination Process (SDP) finding.

Pursuant to the provisions of 10 CFR 2.201, NextEra Energy Duane Arnold is hereby required

to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional

Administrator, Region III, and a copy to the NRC Resident Inspector at the Duane Arnold

Energy Center, within 30 days of the date of the letter transmitting this Notice of Violation

(Notice). This reply should be clearly marked as a Reply to a Notice of Violation;

VIO 05000331/2014010-01 and should include for each violation: (1) the reason for the

violation, or, if contested, the basis for disputing the violation or severity level, (2) the corrective

steps that have been taken and the results achieved, (3) the corrective steps that will be taken,

and (4) the date when full compliance will be achieved. Your response may reference or

include previous docketed correspondence, if the correspondence adequately addresses the

required response. If an adequate reply is not received within the time specified in this Notice,

an order or a Demand for Information may be issued as to why the license should not be

modified, suspended, or revoked, or why such other action as may be proper should not be

taken. Where good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs Agencywide Documents Access and Management

System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or

safeguards information so that it can be made available to the public without redaction. If

NOTICE OF VIOLATION -2-

personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request withholding of such material, you must specifically identify the portions of your response

that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,

explain why the disclosure of information will create an unwarranted invasion of personal

privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

In accordance with 10 CFR 19.11, you may be required to post this Notice within two working

days of receipt.

Dated this 23 day of September, 2014

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No: 50-331

License No: NPF-49

Report No: 05000331/2014010

Licensee: NextEra Energy Duane Arnold, LLC

Facility: Duane Arnold Energy Center

Location: Palo, IA

Dates: April 21 through September 3, 2014

Inspectors: D. Oliver, Senior Resident Inspector (Point Beach)

S. Shah, Reactor Engineer

Approved by: Kenneth G. O'Brien, Director

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000331/2014010, 04/21/2014 - 09/03/2014; Duane Arnold Energy Center (DAEC);

Problem Identification and Resolution

This report covers a 1-week period of announced onsite baseline inspection by Region III based

engineering inspectors. With continued in-office review through September 3, 2014, one finding

was identified by the inspectors. The finding was considered a cited violation of NRC

regulations. The significance of most findings is indicated by their color (i.e., greater than

Green, or Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609,

Significance Determination Process (SDP). Cross-cutting aspects were determined using

IMC 0310, Components Within the Cross Cutting Areas. Findings for which the SDP does not

apply may be Green or be assigned a severity level after NRC management review. All

violations of NRC requirements are disposition in accordance with the NRCs Enforcement

Policy dated July 9, 2013. The NRCs program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 5,

dated February 2014.

A. NRC-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

Green: The inspectors identified a finding of very low safety significance and an

associated cited violation of Title 10, Code of Federal Regulations (CFR), Part 50,

Appendix B, Criterion XVI, Corrective Action, where the licensee failed to correct a

condition adverse to quality following the discovery of water in several safety-related

electrical conduits. Specifically, the licensee identified water in 23 embedded conduits

containing cables for safety-related equipment. However, the licensee failed to take

corrective action to remove water from nine of the conduits. This violation is being cited

because the licensee had failed to restore compliance, or demonstrate objective

evidence of plans to restore compliance in a reasonable period following documentation

of four associated Non-Cited Violations (NCVs) issued from January 30, 2013 to

December 5, 2013.

The performance deficiency was determined to be more than minor, because the finding

was associated with the Mitigating Systems cornerstones attribute of design control for

ensuring the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Specifically, by not removing water from

the conduits, cables were continuously exposed to water which is an adverse

environment for which they were not qualified, designed or evaluated for, and will lead to

cable degradation and could potentially cause cable failure. Cable failure would prevent

the systems from carrying out their intended safety-related functions. The finding had a

cross-cutting aspect in the area of Human Performance because the licensee did not

operate and maintain equipment within design margins. Margins were not carefully

guarded or changed only through a systematic and rigorous process. Special attention

was not placed on maintaining defense-in-depth, and safety-related equipment.

Specifically, the corrective actions developed by the licensee were insufficient to restore

safety-related cables to their design environment to ensure that cables did not remain

submerged. [H.6] (Section 4OA2)

B. Licensee-Identified Violations

None

2

REPORT DETAILS

4. OTHER ACTIVITIES (OA)

4OA2 Identification and Resolution of Problems (71152)

Cornerstones: Mitigating Systems

.1 Selected Issue Follow-Up Inspection: Corrective Actions Following Discovery That

Standby Diesel Generator (SBDG) Cables Were Submerged

a. Inspection Scope

The inspectors reviewed 18 corrective action process documents that were related to the

follow-up actions to recent non-cited violations associated with the discovery of

submerged safety-related cables in embedded conduits. The inspectors reviewed these

documents to evaluate the effectiveness and timeliness of corrective actions taken and

proposed related to the quality assurance and design control of safety-related cabling.

In addition, corrective action documents written on issues identified during the inspection

were reviewed to verify adequate problem identification and incorporation of the

problems into the corrective action system. The list of specific corrective action

documents that were sampled and reviewed by the inspectors is provided in the

Attachment to this report.

This review constituted one in-depth problem identification and resolution sample as

defined in Inspection Procedure 71152-05.

b. Findings

(1) Failure to Remove Water From Conduits Containing Safety-Related Cables

Introduction: The inspectors identified a finding of very low safety significance

(Green) and an associated cited violation of 10 CFR Part 50, Appendix B, Criterion XVI,

Corrective Action, for the licensees failure to correct a condition adverse to quality

following the discovery of water in several safety-related electrical conduits. Specifically,

the licensee identified water in 23 embedded conduits containing cables for

safety-related equipment. However, the licensee failed to take corrective action to

remove water from nine of the conduits. This violation is being cited because the

licensee had failed to restore compliance, or demonstrate objective evidence of plans to

restore compliance in a reasonable period following documentation of four associated

non-cited violations issued from January 30, 2013 to December 5, 2013.

Description: Thirty-four conduits containing cables for safety-related equipment and

equipment important to safety were included in the licensees Aging Management

Program for Inaccessible and Embedded Cables (AMP). The scope of this AMP had

been recently expanded to include conduits that contained low voltage cables as a

result of the discovery of water in October 2012 in conduit 1K111, which contained

cables that support the A SBDG. These cables were replaced because of a failed

cable in that conduit. As described in NRC Inspection Report 05000331/2013008, the

licensee performed Apparent Cause Evaluation (ACE) 01812795-00, Water Damaged

SR [Safety-Related] Cables in the TB [Turbine Building] Floor at Elevation 734, dated

October 16, 2012. The ACE included an extent of condition evaluation to determine how

3

many conduits contained similar conditions of wetted and submerged cables. The

licensees extent of condition evaluation determined that all conduits associated with both

SBDGs that were embedded in the Turbine Buildings concrete base mat contained water

in sufficient quantity to submerge the cables contained within the conduits. This discovery

prompted the licensee to include all conduits that were embedded in the turbine and

reactor building concrete base mats into the AMP.

As a result of the licensees inspections of embedded conduits with the expanded scope of

the AMP, the licensee discovered water in a total 23 of the 25 conduits inspected, with 9

conduits remaining to be inspected. Of the 23 conduits containing water, 11 conduits were

subsequently closed following their inspection with water remaining in the conduits.

Boroscope video taken by the licensee during inspections revealed that some conduits

had retained enough water to completely submerge the cables contained within. Among

the 11 conduits containing water, 9 contained safety-related cabling for:

  • 4kV feeds to essential busses from both Standby Transformers;
  • A SBDG low voltage control and 480 VAC cables;
  • B SBDG 4kV power cables; and

In addition to the cables listed above, the licensee had determined that water had been

removed from 12 of the conduits. However, during the week of April 21, 2014, the

inspectors noted that while the licensee was performing inspections from the turbine

building end of conduits that terminated in the reactor building, visible signs of water

seepage was present at the conduit seals in the reactor building, indicating that water

could be present in conduits that were determined by the licensee to be dry, or

dewatered because they had only been inspected from one end.

Since October 2012 when the licensee initially discovered water in the conduits

associated with the A SBDG, the licensee has not restored the cables to compliance

by removing the water and drying the cables out; nor has the licensee provided any

objective plans to do so in the future. Rather the licensee has made several attempts

to qualify cables that were not initially designed, procured, tested, or installed for

submerged environmental conditions.

The issue of submerged cabling in the industry has been the subject of numerous NRC

regulatory guidance documents, public meetings and NRC findings and violations

stemming from a range of issues from failure to meet design control to actual events

that resulted from these conditions.

Information Notice 2010-26, "Submerged Electrical Cables, dated December 2, 2010,

stated the following:

  • The NRC expects licensees to identify conditions that are adverse to quality for

cables, such as long-term submergence in water. Upon discovery of a

submerged condition, the licensee should take prompt corrective actions to

restore the environment to within the cables design specifications, immediately

determine the operability of the cable(s) to perform its intended design function,

4

and determine the impact of the adverse environment on the design life of the

cable.

  • Cables not designed or qualified for, but exposed to, wet or submerged

environments have the potential to degrade. Cable degradation increases the

probability that more than one cable will fail on demand because of a cable fault,

lightning surge, or a switching transient. Although a single failure is within the

plant design basis, multiple failures of this kind would be challenging for plant

operators. Also, an increased potential exists for a common-mode failure of

accident mitigating system cables if they are subjected to the same environment

and degradation mechanism for which they are not designed or qualified for.

There are numerous NRC publications, such as Information Notice 2010-26,

Submerged Electrical Cables mentioned above, written on this issue and referenced by

the licensee, which acknowledge the potential for safety-related cables to become

submerged. These standards reflect expectations for licensees to detect this condition

and to take prompt and effective corrective action in accordance with the licensees

Corrective Action Program to prevent further degradation from being exposed to wetting

or submergence lasting more than a few days. In the case of DAEC, the licensee had

concluded that cables in wetted or submerged environments constitutes a

nonconforming condition, but did not evaluate the continued degradation that occurs as

the cables remain exposed to the adverse environment.

The inspectors concluded that by not removing the safety-related cables from the

adverse environment, restoring the design conditions and evaluating degradation, the

licensee had allowed a condition adverse to quality to persist. Additionally, the

inspectors determined, by a review of the intended future actions and interviews with the

licensees staff, that the licensee had no objective plans to remove the water from the

conduits or dry the cables out to prevent further degradation.

Analysis: The inspectors determined that failure to correct a condition adverse to quality

following the discovery of water in conduits containing safety-related cables was contrary

to 10 CFR Part 50, Appendix B, Criterion XVI and was within the licensees ability to

foresee and correct. Therefore, this was a performance deficiency. Specifically, the

licensee identified water in nine conduits containing safety-related cables which were not

qualified for continuous exposure to water and failed to take corrective action to remove

the water from the conduits. The performance deficiency was determined to be more

than minor because the finding was associated with the Mitigating Systems

cornerstones attribute of design control for ensuring the availability, reliability, and

capability of systems that respond to Initiating Events to prevent undesirable

consequences. Specifically, by not removing water from the conduits, cables were

continuously exposed to water, which is an adverse environment for which they were not

qualified, designed or evaluated for, and will lead to cable degradation and could

potentially cause cable failure. Cable failure would prevent the systems from carrying

out their intended safety-related functions.

In accordance with IMC 0609, Significance Determination Process, Attachment

0609.04, Initial Characterization of Findings, Table 2, the inspectors determined that

the finding affected the Mitigating Systems cornerstone. As a result, the inspectors

determined that the finding could be evaluated using Appendix A, The Significance

Determination Process (SDP) for Findings At-Power, Exhibit 2 for the Mitigating

Systems cornerstone and determined that the finding is a deficiency affecting the design

or qualification of a mitigating structures, systems and components (SSC), and that the

5

SSCs currently maintain their operability or functionality as applicable; and therefore, the

issue is screened as having very low safety significance (Green).

The finding had a cross-cutting aspect in the area of Human Performance because the

licensee did not operate and maintain equipment within design margins. Margins were

not carefully guarded or changed only through a systematic and rigorous process.

Special attention was not placed on maintaining defense-in-depth, and safety-related

equipment. Specifically, the corrective actions developed by the licensee were

insufficient to restore safety-related cables to their design environment to ensure that

cables did not remain submerged. [H.6]

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,

states, in part, that measures shall be established to assure that conditions adverse to

quality, such as failures, malfunctions, deficiencies, deviations, defective material and

equipment, and non-conformances are promptly identified and corrected. Contrary to

the above, from October 16, 2012, to at least July 10, 2014, the licensee did not assure

that conditions adverse to quality were corrected. Specifically, the licensee failed to

remove water from nine conduits containing safety-related cables and the cables were

not qualified for continuous exposure to water.

This violation is being cited as described in the Notice of Violation, which is enclosed

with this inspection report. This is consistent with the NRC Enforcement Policy,

Section 2.3.2.a.2, which states, in part, that the licensee must restore compliance within

a reasonable period of time (i.e., in a timeframe commensurate with the significance of

the violation) after a violation is identified. The performance deficiency was previously

identified by the NRC on December 5, 2013, and documented as a Non-Cited Violation

(NCV) along with another NCV for creating a procedure that allowed cables to remain

submerged indefinitely. Associated NCVs relating to this performance deficiency were

also issued from January 30, 2013, to December 5, 2013. (Inspection Reports

05000331/2012005, 05000331/2013002, and 05000331/2013008). The inspectors

determined that the licensee had failed to restore compliance within a reasonable time

following issuance of these NCVs, and failed to have objective plans to restore

compliance in the future. (VIO 05000331/2014010-01, Failure to Remove Water

From Conduits Containing Safety-Related Cables)

4OA6 Management Meetings

.1 Exit Meeting Summary

On September 3, 2014, the inspectors presented the inspection results to Mr. G. Pry and

other members of the licensee staff. The licensee acknowledged the issues presented.

The inspectors confirmed that none of the potential report input discussed was

considered proprietary.

ATTACHMENT: SUPPLEMENTAL INFORMATION

6

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

G. Pry, Plant General Manager

M. Davis, Licensing/Emergency Preparedness (EP) Manager

M. Fairchild, Program Engineer Motors and Cables

K. Kleinheinz, Engineering Director

L. Swenzinski, Senior Licensing Engineer

D. Church, Manager Program Engineering

L. Nicholson, Nextera Fleet Licensing

NRC

R. Daley, Chief, Engineering Branch 3

C. Lipa, Chief, Reactor Project Branch 1

D. Oliver, Senior Resident Inspector, Point Beach Nuclear Plant

L. Haeg, Senior Resident Inspector, DAEC

J. Steffes, Resident Inspector, DAEC

C. Phillips, Project Engineer, Reactor Project Branch 1

R. Ng, Project Engineer, Reactor Project Branch 1

J. Gilliam, Reactor Engineer, Engineering Branch 3

M. Jeffers, Reactor Engineer, Engineering Branch 3

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened

05000331/2014010-01 VIO Failure to Remove Water From Conduits Containing Safety-

Related Cables (Section 4OA2)

Closed

None

Discussed

None

1 Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED DURING INSPECTION

Number Description or Title Date or Revision

1812795 Apparent Cause Evaluation for Failed 3

Cables in 1K111

1960738 NECR Conduit Seals Appear to be Damp April 23, 2014

1961073 Evaluate Potential Cable Effect from Damp April 24, 2014

Conduit Seals

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number Description or Title Date or Revision

1960358 Megger Readings for 1P044A-M and Cable April 22, 2014

are Inconsistent

1960587 Conduit 1K109 Inspection Results April 22, 2014

1960223 Debris Found in Conduit 1K112 During April 22, 2014

Inspection

1960222 A SBDG 1K110, 1K111, & 1K112 Conduit April 21, 2014

Inspection Results:

1916178 Untimely Corrective Actions in the Work October 29, 2013

Management Process

1917237 Cable 1A0311-D is in a Wetted November 1, 2013

Environment

1915185 Review Corrective Actions on Conduits September 19, 2013

1939810 Water Found in 2A204 B RHR Feeder February 10, 2014

Conduit

1968613 Replacement of SBDG Cables May 29, 2014

1965405 A Cable in Conduit 1K112 Appears to Have May 13, 2014

a Split Jacket

1950040 Evaluate Installing Level Alarms in March 20, 2014

Manholes

1950235 WO40301105 (MH107) Sump Was on a March 20, 2014

Block Not Fully Pumping

1950277 Cables for Standby XFMR Breakers Not March 20, 2014

Included in POD 1913616

1967520 Evaluate Opening the NECR SBDG May 22, 2014

Conduits for Inspection

1 Attachment

1967523 Evaluate Opening the Reactor Building May 22, 2014

Embedded Conduits

DRAWINGS

Number Description or Title Date or Revision

BECH-E301 Turbine Generator Building Embedded 5

Conduit Below EL-7340

BECH-E302 Reactor Building Embedded Conduit 5

Below EL.716-9

PROCEDURES

Number Description or Title Date or Revision

ACP 1210.7 Electrical and I&C Aging Management 5

Programs

ACP 1210.8 Electrical Cables and Connections 1

Inspection Procedure

REFERENCES

Number Description or Title Date or Revision

N/A Duane Arnold Inaccessible Cable Program April 21, 2014

- Actions Being Taken to Address

OBD/OBN Conditions

ECPM SECT 1.0 Electrical Cable Program Description 3

ECPM SECT 2.0 Electrical Cable Scoping and Population 3

ECPM SECT 3.0 Cable Program Inspection/Test Population 2

Selection

ECPM SECT 3.1 Cable Program Inspection/Test List 1

ECPM SECT 4.1 Cable Aging Management Review 1

ECPM SECT 4.2 Cable Aging due to Ohmic Heating 0

ECPM SECT 4.3 Adverse Localized Equipment 1

Environments

ECPM SECT 4.4 Electrical Manhole Inspection Frequency 1

ECPM SECT 4.5 Electrical Cable Operability 4

ECPM SECT 4.6 Test and Inspection Data Review and 1

Trending

ECPM SECT 4.7 Test and Inspection Methodology 0

ECPM SECT 4.8 Action for Failed or Degraded Cables 2

ECPM SECT 4.9 Susceptibility of Water Collection in 0

Control Building Embedded Conduits

ER-AA-106 Cable Condition Monitoring Program 3

N/A Inaccessible 4160 V and 480 V Power March 31, 2014

Cable Test Results

N/A Embedded Conduit Inspection Results March 31, 2014

2

VENDOR DOCUMENTS

Number Description or Title Date or Revision

12-021 Condition Assessment of 5KV and 600 V February 29, 2012

Cables Removed from the Duane Arnold

Nuclear Plant

12-111 Evaluation of 600 V Cables with Damaged August 2, 2012

Insulation Removed from the Duane

Arnold Nuclear Power Plant

WORK ORDERS

Number Description or Title Date or Revision

40235151 SUS24.01 Inspect TURB BLDG Side of April 22, 2014

Conduits for Water

3

LIST OF ACRONYMS USED

ACE Apparent Cause Evaluation

ADAMS Agencywide Documents Access And Management System

AMP Aging Management Program for Inaccessible and Embedded Cables

CFR Code of Federal Regulations

DAEC Duane Arnold Nuclear Center

IMC Inspection Manual Chapter

NRC Nuclear Regulatory Commission

PARS Public Available Records System

SBDG Standby Diesel Generator

SDP Significance Determination Process

SSC Structure, System, and Component

4

T. Vehec -2-

In addition, if you disagree with the cross-cutting aspect assigned to the finding in this report,

you should provide a response within 30 days of the date of this inspection report, with the basis

for your disagreement, to the Regional Administrator, Region III, and the NRC Resident

Inspector at Duane Arnold Energy Center.

In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's Rules of Practice, a copy of

this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the NRC's Agencywide Documents

Access and Management System (ADAMS). ADAMS is accessible from the NRC web site at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not

include any personal privacy or proprietary information so that it can be made available to the

Public without redaction.

Sincerely,

/RA/

Kenneth G. OBrien, Director

Division of Reactor Safety

Docket No. 50-331

License No. NPF-49

Enclosure:

Inspection Report 05000331/2014010;

w/Attachment: Supplemental Information

cc w/encl: Distribution via LISTSERV

DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\-DAEC 2014 010 Notive of Violation DJO.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII Via email RIII

NAME DJOliver:ls SOrth CLipa RCDaley KGOBrien

DATE 09/15/14 09/18/14 09/19/14 09/22/14 09/23/14

OFFICIAL RECORD COPY

Letter to Thomas Vehec from Kenneth G. O'Brien dated September 23, 2014.

SUBJECT: DUANE ARNOLD ENERGY CENTER - NRC FOLLOW-UP INSPECTION

REPORT 05000331/2014010 AND NOTICE OF VIOLATION

DISTRIBUTION:

John Jandovitz

RidsNrrDorlLpl3-1 Resource

RidsNrrPMDuaneArnold Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Steven Orth

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Carmen Olteanu

ROPreports.Resource@nrc.gov0