IR 05000331/2020001

From kanterella
Jump to navigation Jump to search
Reissue - Duane Arnold Energy Center - Integrated Inspection Report 05000331/2020001
ML20175A122
Person / Time
Site: Duane Arnold 
Issue date: 06/22/2020
From: Billy Dickson
Division Reactor Projects III
To: Dean Curtland
NextEra Energy Duane Arnold
Shared Package
ML2017A147 List:
References
IR 2020001
Download: ML20175A122 (14)


Text

June 22, 2020

SUBJECT:

REISSUE - DUANE ARNOLD ENERGY CENTER - INTEGRATED INSPECTION REPORT 05000331/2020001

Dear Mr. Curtland:

The NRC identified that the inspection report sent to you dated May 11, 2020, (ML20132A266)

inadvertently failed to document the completion of an annual inspection sample of the 71152 inspection procedure. As a result, the NRC is reissuing the report in its entirety with the updated subject. None of these changes affected the technical content of the report.

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Duane Arnold Energy Center. On April 16, 2020, the NRC inspectors discussed the results of this inspection with Mr. M. Davis, Licensing Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA by April Nguyen for/

Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects

Docket No. 05000331 License No. DPR-49

Enclosure:

As stated

Inspection Report

Docket Number:

05000331

License Number:

DPR-49

Report Number:

05000331/2020001

Enterprise Identifier: I-2020-001-0046

Licensee:

NextEra Energy Duane Arnold, LLC

Facility:

Duane Arnold Energy Center

Location:

Palo, Iowa

Inspection Dates:

January 01, 2020 to March 31, 2020

Inspectors:

R. Edwards, Senior Health Physicist

V. Myers, Senior Health Physicist

C. Norton, Senior Resident Inspector

T. Ospino, Reactor Engineer

J. Rutkowski, Project Engineer

Approved By:

Billy C. Dickson, Jr., Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Duane Arnold Energy Center, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The Unit began the inspection period at rated thermal power. On February 15, 2020, the unit was down powered to 60 percent power for a control rod sequence exchange. The unit was returned to full power on February 16, 2020, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Standby liquid control system on March 10, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Low Level Radioactive Waste Processing and Storage Facility Elevation 757 South Fire Zones 21-G and 21-N on March 6, 2020
(2) Reactor Building Elevation 786 Fire Zones 3-A and 3-B on March 10, 2020
(3) Radwaste Building Fire Zones 13-A, 13-B, and 13-C on March 11, 2020
(4) Turbine Building Elevation 757 Fire Zones 8-A, 8-B, 8-D, 8-F and 8-H on March 16, 2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated a reactor plant power evolution and rod sequence exchange on February 15, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training and activities on March 10, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Emergent work on torus spray and cooling supply header isolation valve on January 7, 2020
(2) Planned work on the 'A' control rod drive pump speed increaser on February 4, 2020
(3) Planned work on the Reactor Core Isolation Cooling (RCIC) system on February 24, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Condition Report (CR) 02343529, Kaman equipment not operable on February 5, 2020
(2) CR 02343787, Part 21 drywell accident range radiation monitor on February 7, 2020
(3) CR 02347414, High Pressure Coolant Injection (HPCI) system room exhaust fan outboard belt beginning to fail on March 6, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)

'A' and 'B' fuel pool demineralizers flow recording controllers replaced with low indicating recorders on February 19, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Following inboard and outboard torus vent valve seal pressure indicators reconfiguration on January 30, 2020
(2) Following 'A' control rod drive pump speed changer maintenance on February 4, 2020
(3) Following replacement of reactor building door 280 on February 26, 2020
(4) Following oil change on the 'B' fuel pool pump on January 22, 2020
(5) Following modification to replace 'B' fuel pool demineralizer flow indicating recorder with a flow indicating controller on January 22, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) In field activities associated with the pressure suppression chamber to reactor building vacuum breaker operability test on January 7, 2020
(2) In field activities associated with the HPCI system operability test on January 14, 2020
(3) In field activities associated with the Low Pressure Coolant Injection (LPCI) system operability test on January 27, 2020
(4) In field activities associated with the fuel pool liner monitoring test on January 27, 2020
(5) In field activities associated with repositioning torus to reactor building vacuum breaker T-seal pressure indicators on January 29, 2020
(6) Functional test of turbine stop valve closure input to the reactor protection system and recirculation pump trip logic on February 15, 2020
(7) In field activities associated with the Standby Liquid Control (SBLC) pump operability test on March 10, 2020
(8) In field activities associated with the 'B' standby diesel generator operability test (fast start) on March 11, 2020

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the emergency response organization training drill on March 4,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Portable Survey Instruments
  • Ludlum 177, serial number 342940
  • Mirion Telepole II, serial number 228316-027
  • Ludlum 26, serial number HP3508
  • Ludlum 12-4, serial number 326388
  • Ludlum 9-3, serial number 343228

Source Check Demonstration

  • Ludlum 177, serial number 342940
  • Mirion Telepole II, serial number 228316-027
  • Ludlum 26, serial number HP3508

Area Radiation Monitors and Continuous Air Monitors

  • RE-9167, reactor building railroad access area
  • RE-9177, clean up phase separator area
  • RE-9156, reactor water clean up pump rooms
  • AMS-4, low level radioactive waste storage and processing facility
  • AMS-4, refuel floor

Personnel Contamination Monitors, Portal Monitors and Small Article Monitors

  • Argos-5AB, serial number 308
  • Cronos-1, serial number 215
  • Gem 5, serial number 366

Calibration and Testing Program (IP Section 02.02) (1 Partial)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1)

(Partial)

  • Whole body counter calibration on May 8, 2019
  • AMP 100, serial number 5012-014, calibration on September 13, 2019
  • Argos-5AB, serial number 308, calibration on July 9, 2019
  • RE-9156, reactor water clean up pump rooms area monitor, calibration on June 12,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1, 2019 to December 31, 2019)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)

(1) Unit 1 (January 1, 2019 to December 31, 2019)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) Unit 1 (January 1, 2019 to December 31, 2019)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors reviewed the licensees corrective actions associated with inaccurate documentation on February 3, 2020

71153 - Follow-up of Events and Notices of Enforcement Discretion Reporting (IP Section 03.05)

(1) The inspectors reviewed the circumstances surrounding Event Notification 54528, transport of a potentially contaminated person to a medical facility on February 18,

INSPECTION RESULTS

Observation: Licensee Documentation Observation 71152 During the 2019 fourth quarter, while performing reviews associated with baseline inspection activities, the inspectors identified several documentation issues. These issues included operational logging errors, missing signatures in surveillance test procedures and work orders, and inaccurate date and time notations. Although individual performance deficiencies associated with these documentation issues were minor, they were numerous, demonstrated a lack of attention-to-detail, and made it difficult to track the work performed. During the 2019 fourth quarter exit, the inspectors informed the licensee that the inspectors would conduct a Problem Identification and Resolution (PIR), inspection during the first quarter of 2020 and assess Duane Arnold's corrective actions to improve the quality of documentation.

During the week of January 19, 2020, the inspectors conducted a PIR inspection of the documentation associated with the maintenance window on the B control building chiller.

This work activity was chosen because it was complex and included coordination among multiple work groups. The inspectors noted a profound improvement in documentation quality over the 2019 fourth quarter that included:

1. reduced logging errors,

2. appropriate work and review signatures, and

3. improved time and date notations when work was repeated or handed off between

workers.

The inspectors concluded the licensee changed behaviors to sustain document quality improvements that includes:

1. call outs at plan-of-the-day meetings,

2. emphasis on documentation quality during shop briefings, and

3. nuclear assurance review of documentation quality.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On April 16, 2020, the inspectors presented the integrated inspection results to Mr. M. Davis, Licensing Manager, and other members of the licensee staff.
  • On March 19, 2020, the inspectors presented the radiation protection program inspection results to Mr. D. Curtland, Director of Site Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Fire Plans

PFP-LL-757

Pre-Fire Plan LLRPSF

PFP-RB-786

Pre-Fire Plan Reactor Building Elevation 786

PFP-RW-757

Pre-Fire Plan Radwaste Building

PFP-TB-757

Pre-Fire Plan Turbine Building Elevation 757

71111.11Q Miscellaneous

Reactivity Management Plan Down Power for February 2020

Control Rod Sequence Exchange

01/22/2020

SEG 2020B-01E

Evaluated Scenario

Procedures

Operating

Instruction 264

Reactor Recirculation System

143

Operating

Instruction 856.1

Reactor Manual Control System

71111.13

Corrective Action

Documents

Condition Report

(CR) 02340151

Handswitch has Intermittent Contact for MO2005

01/06/2020

Miscellaneous

Operations Logs

2/24/2020

Operations Logs

01/06/2020

Duane Arnold Station Daily Status Report

2/24/2020

VALOP-L200-08

Limitorque Valve Operator Inspection and Lubrication

Procedures

MA-AA-100-1011-

FO1

Troubleshooting, MO2005 did not Open as Expected HS

was Taken to Open

01/06/2020

Work Orders

40659928-01

IP209 A-G, Inspect and Oil Change

WO 40662001

MO, 2405-0, Elect Lube and Inspect

71111.15

Corrective Action

Documents

CR 02343529

Kaman Equipment not Operable

CR 02343787

Part 21 Drywell Accident Range Radiation Monitor

CR 02347414

HPCI System Room Exhaust Fan Outboard Belt Beginning

to Fail

71111.18

Engineering

Changes

EC-287976,

Replace FRC-

3511A(B)

Replace FRC-3511A(B), Fuel Pool F/D IT-206A(B) Effluent

Flow Controllers

Miscellaneous

2nd Assistant Logs

71111.18

Miscellaneous

APED-G41-2929-

047, Fuel Pool

Demineralizers

Control Panel

Fuel Pool Demineralizers Control Panel

APED-G41-2929-

049 Sheet 1

Fuel Pool Demineralizers Electric Schematic, Filter 'A'

APED-G41-2929-

049 Sheet 2

Fuel Pool Demineralizers Electric Schematic, Filter 'B'

APED-G41-2929-

056

Fuel Pool Demineralizers Control Panel Wiring

APED-G41-2929-

058

Fuel Pool F/D System, Withdraw Drawing

Bech-M135

P&ID Fuel Pool Demineralizer System

Procedures

Operating

Instruction 435

Fuel Pool Cooling System

Work Orders

WO 40580523

Replace FRC 3511 by EC 287976

71111.19

Miscellaneous

GMP-Test-54

des Mid/High Range Leak Rate Monitor (LRM) Sec C

Procedures

STP 3.6.1.3-

2CAC

CAC, PCIS, and ASME Valve Functional Test

STP NS700002A

Secondary Containment Test Using SBGT 'A'

Work Orders

40658036-01

STP 3.6.1.3-02CAC, PCIS, and ASME Valve Functional

Test

40659928-01

IP209 A-G, Inspect and Oil Change

40695659-01

PI4300: Reconfigure Orientation

71111.20

Procedures

PCP 2.41

Fuel Pool Liner Monitoring

71111.22

Corrective Action

Documents

Condition Report

(CR) 02342593

Torus Water Temperature Difference Between Recorders at

Maximum Difference

01/27/2020

CR 02344750

Z19011 Indication During STP 3.3.1.1-19

CR 02348061

PSV3252B Leaking from Valve Cap

03/11/2020

Miscellaneous

Pictures of PI-4300

Procedures

NS490003A

'A' RHR System Leakage Inspection Walkdown

STP 3.3.1.1-19

Functional Test of TSV Closure Input to RPS and RPT

STP 3.5.1-02A

A LPCI System Operability Test

STP 3.5.1-05

HPCI System Operability Test

STP 3.6.1.3-

2CAC

CAC PCIS and ASME Valve Functional Test

STP 3.6.1.6-01

Pressure Suppression Chamber to Reactor Building Vacuum

Breaker Operability Test

STP NS520001

HPCI System Leakage Inspection Walkdown

WM-AA-1000-F01 Work Activity Risk Evaluation Form

Work Orders

40654043

Pressure Suppression Chamber Reactor Building Vacuum

Breaker Operability Test

40655944-01

STP 3.5.1-05 HPCI System Operability Test

40658036-01

STP 3.6.1.3-02CAC PCIS and ASME Valve Functional Test

40658042-01

STP 3.5.1-02 LCPI System Operability Test

40661313

Standby Liquid Control Pump Operability Test

03/10/2020

40664416-01

STP 3.8.1-06B 'B' SBDG Operability Test (Fast Start)

03/11/2020

40695659-01

P14300: Reconfigure Orientation

71114.06

Corrective Action

Documents

2347183

20 Drill Observations Not Covered by Drill Critique

03/04/2020

2347187

20 Drill Note 5 Information Communication

03/04/2020

2347205

20 Drill Question on Issuing Potassium Iodide

03/04/2020

Miscellaneous

NOTE-5

Duane Arnold Energy Center Emergency Notification

Procedures

EPIP 3.3

Dose Assessment and Protective Actions

EPIP 4.5

Administration of Potassium Iodide

71124.05

Calibration

Records

Ortec Whole Body Counter

05/08/2019

AMP-100 Serial Number 5012-014

09/13/2019

Argos-5AB Serial Number 308

07/09/2019

Procedures

HPP 3109.87

Operation of the Argos 5AB Personnel Contamination

Monitor

Work Orders

40381701

RE9156: Reactor Water Clean Up Pump Rooms A and B

06/12/2016

71151

Miscellaneous

NG-001L

NRC PI Data Calculation, Review and Approval

07/08/2019

NG-001L

NRC PI Data Calculation, Review and Approval

04/16/2019

NG-001L

NRC PI Data Calculation, Review and Approval

10/14/2019

NDE Reports

NG-001L

NRC PI Data Calculation, Review and Approval

01/17/2020

71152

Miscellaneous

January 12-17, 2020 DAEC Operational Logs

Procedures

Clearance - 3002,

I/16924B

AC to DC converter

Clearance 3000 -

1VAC308B-02

Control Building Air Conditioning Unit, CB Heating,

Ventilation, and Air Conditioning (HVAC) Room

Clearance 3000 -

1VCP030B

Control Building HVAC Chilled Water Pump, North Open

Area

Clearance 3000 -

1VRF030B

Control Building HVAC Return Air Fan, CB HVAC Room

Work Orders

40603853-01

1VCP030B: Rebuild Pump

40603853-02

1VCP030B: OPS PMT

40634094-01

I/16924B: Calibrate

40655395-01

1VAC030B: Inspect and Lube Unit

40656453-01

1VRF030B: MA, Inspect Unit and Lube BRG

406566918-01

PS6933B: Inspect and Calibrate

40656919-01

PS6930B: Inspect and Calibrate, High Pressure Safety

Switch

40671140-01

STP 3.7.5-01-B, 'B' Control Building Chiller Operability

40671140-02

B2: Swap to 'B' Chiller

40688611-01

1VCH001B: Inspection with ESW Secured

71153

Corrective Action

Documents

CR 02344843

Medical Emergency

2/17/2020

CR 02344897

Security Medical Response SEL 20-11

2/17/2020

Miscellaneous

Event Notification

(EN) 54528

Transport of Potentially Contaminated Person to a Medical

Facility

0