|
---|
Category:Inspection Report
MONTHYEARIR 05000331/20240022024-10-25025 October 2024 NRC Inspection Report No. 07200032/2024001 and 05000331/2024002 IR 07200032/20224012023-03-0909 March 2023 Public DAEC ISFSI - Independent Spent Fuel Storage Installation Security Inspection Report 07200032/2022401 IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 IR 05000331/20220012022-03-0404 March 2022 Subject: NRC Inspection Report Nos. 05000331/2022001(DNMS) and 07200032/2022001(DNMS) IR 05000331/20210012022-01-25025 January 2022 NRC Inspection Report Nos. 05000331/2021001(DNMS); 07200032/2021001(DNMS); and 07200032/2021002(DNMS) - Duane Arnold Energy Center IR 05000331/20214022021-12-30030 December 2021 DAEC Decommissioning Reactor - Decommissioning Security Inspection Report 05000331/2021402 IR 05000331/20214012021-08-25025 August 2021 DAEC Decommissioning Reactor (Permanently Shut Down) and Independent Spent Fuel Storage Installation - Security Inspection Reports 05000331/2021401; and 07200032/2021401 IR 05000331/20200042021-02-12012 February 2021 Integrated Inspection Report 05000331/2020004 and 05000331/2020501 IR 05000331/20200102021-01-0707 January 2021 NRC Inspection Report No. 05000331/2020010(DNMS) - Duane Arnold Energy Center IR 05000331/20200032020-11-0606 November 2020 Integrated Inspection Report 05000331/2020003 and 07200032/2020001 IR 05000331/20200052020-09-0101 September 2020 Updated Inspection Plan for Duane Arnold Energy Center (Report 05000331/2020005) IR 05000331/20200022020-08-0404 August 2020 Integrated Inspection Report 05000331/2020002 IR 05000331/20204022020-07-14014 July 2020 Security Baseline Inspection Report 05000331/2020402 IR 05000331/20200012020-06-22022 June 2020 Reissue - Duane Arnold Energy Center - Integrated Inspection Report 05000331/2020001 IR 05000331/20204012020-06-10010 June 2020 Security Baseline Inspection Report 05000331/2020401 ML20132A2662020-05-11011 May 2020 Integrated Inspection Report 05000331/2020001 IR 05000331/20190062020-03-0303 March 2020 Annual Assessment Letter Duane Arnold Energy Center (Report 05000331/2019006) IR 05000331/20190042020-01-28028 January 2020 Integrated Inspection Report 05000331/2019004 IR 05000331/20190132019-12-11011 December 2019 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000331/2019013 IR 05000331/20190032019-11-12012 November 2019 Integrated Inspection Report 05000331/2019003 IR 05000331/20194112019-10-21021 October 2019 Dune Arnold Energy Center - NRC Baseline Inspection Report 05000331/2019411 IR 05000331/20190112019-10-0101 October 2019 NRC Inspection Report 05000331/2019011 IR 05000331/20190052019-08-28028 August 2019 Updated Inspection Plan for Duane Arnold Energy Center (Report 05000331/2019005) IR 05000331/20190022019-08-0101 August 2019 Integrated Inspection Report 05000331/2019002 IR 05000331/20193012019-06-18018 June 2019 NRC Initial License Examination Report 05000331/2019301 IR 05000331/20190012019-05-0303 May 2019 NRC Integrated Inspection Report 05000331/2019001 IR 07200032/20194012019-05-0202 May 2019 Independent Spent Fuel Storage Installation NRC Security Inspection Report 07200032/2019401 (DRS-G.Bonano) IR 05000331/20190102019-04-18018 April 2019 NRC Biennial Problem Identification and Resolution Inspection Report 05000331/2019010 IR 05000331/20194102019-04-16016 April 2019 NRC Security Baseline Inspection Report 05000331/2019410 (DRS-G.Bonano) IR 05000331/20180062019-03-0404 March 2019 Annual Assessment Letter for Duane Arnold Energy Center (Report 05000331/2018006) IR 05000331/20180042019-02-0707 February 2019 Errata - Duane Arnold Energy Center - NRC Integrated Inspection Report 05000331/2018004 ML19029A4432019-01-29029 January 2019 NRC Integrated Inspection Report 05000331/2018004 IR 05000331/20182012019-01-0808 January 2019 NRC Security Baseline Inspection Report 05000331/2018201 IR 05000331/20184142018-11-29029 November 2018 NRC Cyber Security Inspection Report 05000331/2018414 - Cover Letter (DRS-G.Hausman) IR 05000331/20180032018-10-24024 October 2018 NRC Integrated Inspection Report 05000331/2018003 IR 05000331/20184132018-10-11011 October 2018 NRC Security Baseline Inspection Report 05000331/2018413 (DRS-J.Kutlesa) IR 05000331/20180052018-08-28028 August 2018 Updated Inspection Plan for Duane Arnold Energy Center (Report 05000331/2018005) IR 05000331/20180022018-08-0303 August 2018 NRC Integrated Inspection Report 05000331/2018002 IR 05000331/20184122018-07-17017 July 2018 NRC Security Baseline Inspection Report 05000331/2018412 (DRS-G.Bonano) IR 05000331/20185032018-05-29029 May 2018 NRC Emergency Preparedness Inspection Report 05000331/2018503 (Gph) IR 05000331/20180012018-05-0404 May 2018 NRC Integrated Inspection Report 05000331/2018001 IR 05000331/20184112018-03-23023 March 2018 NRC Security Baseline Inspection Report 05000331/2018411 - (Cover Letter Only) IR 05000331/20180102018-03-16016 March 2018 NRC Triennial Fire Protection Inspection Report 05000331/2018010 (DRS-A.Dahbur) IR 05000331/20170062018-03-0202 March 2018 Annual Assessment Letter for Duane Arnold Energy Center (Report 05000331/2017006) IR 05000331/20184102018-02-26026 February 2018 NRC Material Control and Accounting Program Inspection Report 05000331/2018410 IR 05000331/20170042018-01-22022 January 2018 NRC Integrated Inspection Report 05000331/2017004; 07200032/2017001; and Emergency Preparedness Annual Inspection Report 05000331/2017501 ML18012A5482018-01-10010 January 2018 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000331/2018001 (DRS-A.Dunlop) IR 05000331/20174072017-12-14014 December 2017 NRC Security Baseline Inspection Report 05000331/2017407 - Cover Letter Only (DRS-M.Ziolkowski) 2024-10-25
[Table view] Category:Letter
MONTHYEARIR 05000331/20240022024-10-25025 October 2024 NRC Inspection Report No. 07200032/2024001 and 05000331/2024002 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities NG-24-0004, 2023 Annual Radiological Environmental Operating Report2024-05-0808 May 2024 2023 Annual Radiological Environmental Operating Report NG-24-0003, Submittal of 2023 Annual Radioactive Material Release Report2024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Material Release Report ML24072A0292024-03-29029 March 2024 Nextera Energy Duane Arnold, Llc. Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-24-0002, 2023 Annual Exposure Report - Form 5s2024-03-0606 March 2024 2023 Annual Exposure Report - Form 5s L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update ML23137A1672023-05-11011 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report L-2023-029, And Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 And Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22339A0012022-12-22022 December 2022 – Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) ML22285A0072022-10-13013 October 2022 NRC Analysis of NextEra Energy Duane Arnolds Decommissioning Funding Status Report, Docket No. 50-331 IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan ML22089A0492022-05-12012 May 2022 Sfmp Review Letter NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval L-2022-068, NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 22022-04-25025 April 2022 NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 2 NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s ML22080A1822022-03-22022 March 2022 Letter to B. Coffey from M. Doell - Duane Arnold ISFSI QAPD RAI Letter L-2022-012, Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3)2022-03-16016 March 2022 Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22059A7462022-03-10010 March 2022 ISFSI-Only Physical Security Plan License Amendment Approval NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks 2024-09-04
[Table view] |
See also: IR 05000331/2018001
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, ILLINOIS 60532-4352
January 10, 2018
Mr. Dean Curtland
Director of Site Operations
NextEra Energy Duane Arnold, LLC
3277 DAEC Road
Palo, IA 52324-9785
SUBJECT: DUANE ARNOLD ENERGY CENTERNOTIFICATION OF AN NRC TRIENNIAL
HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR
INFORMATION; INSPECTION REPORT 05000331/2018001
Dear Mr. Curtland:
On March 12, 2018, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite
portion of the Triennial Heat Sink Performance Inspection at your Duane Arnold Energy
Center. This inspection will be performed in accordance with NRC Baseline Inspection
Procedure 71111.07.
In order to minimize the impact that the inspection has on the site and to ensure a productive
inspection, we have enclosed a request for documents needed for the inspection. The
documents have been divided into three groups.
The first group lists information necessary for our initial inspection scoping activities.
This information should be available to the lead inspector no later than
January 29, 2018. By February 5, 2018, the inspector will communicate the initial
selected set of approximately 2-3 risk significant heat exchangers.
The second group is needed to support our in-office preparation activities. This set of
documents, including the calculations associated with the selected heat exchangers,
should be available at the Regional Office no later than February 28, 2018. This
information should be separated for each selected component, especially if provided
electronically (e.g., folder with component name that includes calculations, condition
reports, maintenance history, etc.). During the in-office preparation activities, the
inspector may identify additional information needed to support the inspection.
The last group includes the additional information above as well as plant specific
reference material. This information should be available onsite to the inspector on
March 12, 2018. It is also requested that corrective action documents and/or questions
developed during the inspection be provided to the inspector as the documents are
generated.
All requested documents are to be for the time period from the onsite inspection period back to
the documents that were provided in response to the previous Heat Sink Performance
Inspection. If no activities were accomplished in that time period, then the request applies to the
last applicable document in the previous time period. It is important that these documents be as
complete as possible, in order to minimize the number of documents requested during the
preparation week or during the onsite inspection.
D. Curtland -2-
The lead inspector for this inspection is Andrew Dunlop. We understand that our licensing
contact for this inspection is Laura Swenzinski of your organization. If there are any questions
about the inspection or the material requested in the enclosure, please contact the lead
inspector at 630-829-9726 or via e-mail at Andrew.Dunlop@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Andrew Dunlop, Senior Reactor Engineer
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-331
License No. DPR-49
Enclosure:
Document Request for Triennial Heat Sink
Performance Inspection
cc: Distribution via LISTSERV
D. Curtland -3-
Letter to Dean Curtland from Andrew Dunlop dated January 10, 2018
SUBJECT: DUANE ARNOLD ENERGY CENTERNOTIFICATION OF AN NRC TRIENNIAL
HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR
INFORMATION; INSPECTION REPORT 05000331/2018001
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3
RidsNrrPMDuaneArnold Resource
RidsNrrDirsIrib Resource
Steven West
Kenneth OBrien
Richard Skokowski
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
ADAMS Accession Number ML18012A548
OFFICE RIII RIII RIII RIII
NAME ADunlop:cl
DATE 01/10/18
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
Inspection Report: 05000331/2018001
Inspection Dates: March 12-16, 2018;
Inspection Procedure: IP 71111.07, Heat Sink Performance
Lead Inspector: Andrew Dunlop
630-829-9726
Andrew.Dunlop@nrc.gov
I. Information Requested By January 29, 2018
1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting
Safety-Related Equipment, heat exchangers in order of risk significance.
2. Copy of heat exchanger performance trending data tracked for each GL 89-13
heat exchanger.
3. List of Corrective Action Program documents (with a short description)
associated with GL 89-13 heat exchangers, heat sinks, silting, corrosion,
fouling, or heat exchanger testing, for the previous 3 years.
4. Copy of any self-assessment done on any of GL 89-13 heat exchangers.
5. Last two System Health Report(s) and maintenance rule system notebooks for all
the GL 89-13 heat exchangers.
6. List of engineering-related operator workarounds (with a short description)
associated with GL 89-13 heat exchangers for the previous 3 years.
7. List of permanent and temporary modifications (with a short description)
associated with GL 89-13 heat exchangers for the previous 3 years.
II. Information Requested By February 28, 2018
1. Copies of the GL 89-13 responses.
2. Copy of the Updated Final Safety Analysis Report (UFSAR) section applicable to
the GL 89-13 Heat Exchanger Program.
3. Copies of procedures developed to implement the recommendations of GL 89-13
(e.g., the GL 89-13 Heat Exchanger Program description).
4. Copies of the selected Corrective Action Program documents.
Enclosure
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
5. For the specific heat exchangers selected:
a. Copies of the UFSAR sections applicable for each heat exchanger.
b. Copy of system description and design basis document for the heat
exchangers (as applicable).
c. Provide a list of calculations (with a short description) which currently apply to
each heat exchanger.
i. establish the limiting design basis heat load required to be removed
by each of these heat exchangers;
ii. demonstrate the heat exchangers capacity to remove the limiting heat
load;
iii. correlate surveillance testing and/or inspection results from these heat
exchangers with design basis heat removal capability (e.g., basis for
surveillance test and/or inspection acceptance criteria);
iv. evaluate the potential for water hammer in each heat exchanger or
associated piping; and
v. evaluate excessive tube vibration in each heat exchanger.
d. Copy of any operability determinations or other documentation of degradation
associated with the heat exchangers or the systems that support the
operation for the selected heat exchangers.
e. Copy of the construction code, Design Specification, heat exchanger data
sheets, and vendor documents including component drawings applicable for
the heat exchangers.
f. Copies of normal, abnormal, and emergency operating procedures
associated with the selected heat exchangers.
6. For the ultimate heat sink (UHS) and the safety-related service water system (or
equivalent):
a. Copies of the applicable UFSAR sections.
b. Copy of system description and design basis document (as applicable).
c. Copy of any operability determinations or other documentation of degradation
associated with the UHS and the safety-related service water system.
d. Copy of the document (e.g., UFSAR or Technical Requirements Manual) that
states the maximum cooling water system inlet temperature limit that still
allows full licensed power operation of the nuclear reactor.
e. Copy of system description and design basis document (as applicable).
f. Copy of the construction code and Design Specification.
2
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
g. Copies of normal, abnormal, and emergency operating procedures
associated with the UHS and safety-related service water systems including
procedures for loss of these systems.
h. Copies of corrective action documents associated with waterhammer or
hydraulic transients in the service water system for the previous 3 years.
i. If available, provide an electronic copy of piping and instrumentation
diagrams for the service water system, including the intake structure.
j. Provide a list of calculations (with a short description), which currently apply
to UHS and safety-related service water system.
k. Provide a list of instruments (with a short description) associated with
automatic or alarm functions for the safety-related service water system
and/or UHS.
l. Provide a list of any design change (with a short description) performed on
the UHS or safety-related service water system for the previous 3 years.
7. A schedule of all inspections, cleanings, maintenance, or testing of any
safety-related plant heat exchanger to be performed during the onsite portion
of the inspection.
III. Information Requested to be Available on First Day of Inspection, March 12, 2018
1. For the specific heat exchangers selected.
a. Copy of the calculation which correlates surveillance testing results from
these heat exchangers with design basis heat removal capability (e.g., basis
for surveillance test acceptance criteria).
b. Copies of the two most recent completed tests and evaluation data
confirming thermal performance for those heat exchangers which are
performance tested.
c. Documentation and procedures that identify the types, accuracy, and location
of any special instrumentation used for the two most recently completed
thermal performance tests for the heat exchangers (e.g., high accuracy
ultrasonic flow instruments or temperature instruments). Include calibration
records for the instruments used during these tests.
d. Information regarding any alarms which monitor on-line performance.
e. Copy of the document describing the inspection results of each heat
exchanger.
f. The cleaning and inspection maintenance schedule for each heat exchanger
for the next 5 years.
g. Copy of the design specification and heat exchanger data sheets for each
heat exchanger.
3
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
h. Copy of the vendor manuals including component drawings for each heat
exchanger.
i. Copy of the calculation which establishes the limiting (maximum) design
basis heat load which is required to be removed by each of these heat
exchangers.
j. Copy of the operating procedure that ensures that the maximum cooling
water system inlet temperature limit is not exceeded.
k. Copy of the calculations or documents which evaluate the potential for water
hammer in each heat exchanger or associated piping.
l. Copy of the calculations that evaluate excessive tube vibration in each heat
exchanger and the documents that describe the controls that prevent heat
exchanger degradation due to excessive flow induced vibration during
operation.
m. Copy of the periodic flow testing at or near maximum design flow.
n. Copy of the document which identifies the current number of tubes in service
for each heat exchanger and the supporting calculation which establishes the
maximum number of tubes which can be plugged in each heat exchanger.
o. Copy of the document establishing the repair criteria (plugging limit) for
degraded tubes which are identified in each heat exchanger.
p. Copies of the documents that verify the structural integrity of the heat
exchanger (e.g., eddy current summary sheets, ultrasonic testing results, and
visual inspection results).
q. Copies of those documents that describe the methods taken to control water
chemistry in the heat exchangers.
2. For the UHS
a. Copies of the inspection procedures for the verification of the structural
integrity of underwater UHS and the associated results for the two most
recently completed inspections.
b. Copies of the maintenance and/or inspection procedures for underwater UHS
sediment intrusion and the associated results including underwater diving
inspections and/or sediment removal activities for the two most recently
completed inspections.
c. Copies of calculations and surveillances that determine the UHS reservoir
capacity and heat transfer capability.
d. Copies of surveillance procedures and the two most recently completed tests
performed on the instrumentation relied upon to determine UHS reservoir
capability.
4
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
3. For the review of the operation of the safety-related service water system (or
equivalent) and the UHS:
a. Copies of any design change performed on the UHS within the last 6 years.
b. Copies of any design change performed on the safety-related service water
system within the last 6 years.
c. Copies of procedures for a loss of UHS.
d. Copies of procedures for a loss of service water system.
e. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,
dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or
kelp).
f. Copies of chemistry procedures that monitor for pH, calcium hardness, etc.
Also, provide copies of the associated results for the last 3 years.
g. Copies of documents associated with the monitoring of pump performance for
potential strong-pump vs. weak-pump interaction.
If the information requested above will not be available, please contact Andrew Dunlop as soon
as possible at 630-829-9726 or email Andrew.Dunlop@nrc.gov.
5