September 1, 2020

SUBJECT:

UPDATED INSPECTION PLAN FOR DUANE ARNOLD ENERGY CENTER (REPORT 05000331/2020005)

Dear Mr. Curtland:

The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for the Duane Arnold Energy Center. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9587 with any questions you have regarding this letter.

Sincerely,

/RA/

April Nguyen, Acting Chief Branch 2 Division of Reactor Projects Docket Nos. 50-331;72-032 License No. DPR-49 Enclosure(s):

Inspection Plan cc: Distribution via LISTSERV Letter to Dean Curtland from April Nguyen dated September 1, 2020.

SUBJECT: UPDATED INSPECTION PLAN FOR DUANE ARNOLD ENERGY CENTER (REPORT 05000331/2020005)

DISTRIBUTION:

Jessie Quichocho Elise Burket RidsNrrDorlLpl3 RidsNrrPMDuaneArnold Resource RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML20244A330 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME RRuiz:wc via email ANguyen: via email DATE 8/28/2020 8/28/2020 OFFICIAL RECORD COPY

IP 22 Inspection Activity Plan Report 07200032 - Duane Arnold (ISFSI)

07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count ISFSI Pad Inspection 3 1 01/18/2021 01/22/2021 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations 1 02/01/2021 02/05/2021 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations ISFSI Pad Construction Inspection 3 1 02/15/2021 02/17/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI 1 03/15/2021 03/17/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI 1 04/12/2021 04/14/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI ISFSI Security Inspection 1 1 04/12/2021 04/14/2021 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations ISFSI Cask Loading Inspection 2 1 11/08/2021 11/12/2021 IP 60855 001001 Operation Of An ISFSI ISFSI Cask Loading Inspection 2 1 03/14/2022 03/18/2022 IP 60855 001001 Operation Of An ISFSI 1 06/06/2022 06/10/2022 IP 60855 001001 Operation Of An ISFSI This report does not include INPO and OUTAGE activities. Page 1 of 2 This report shows only on-site and announced inspection procedures.

8/31/2020 1:21:51 PM

IP 22 Inspection Activity Plan Report Duane Arnold 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count ISFSI Cask Loading Inspection 3Q2020 2 1 08/31/2020 09/04/2020 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Security Baseline Inspection 1 1 10/26/2020 10/30/2020 IP 71130.02 000734 Access Control Emergency Preparedness Baseline Inspection / Performance Indicator Verification 1 1 04/12/2021 04/16/2021 IP 71114.02 000717 Alert and Notification System Testing 1 04/12/2021 04/16/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 04/12/2021 04/16/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1 04/12/2021 04/16/2021 IP 71151 001397 Performance Indicator Verification Force-On-Force Planning and Exercise Weeks - DA 6 1 11/15/2021 11/19/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 12/13/2021 12/17/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing This report does not include INPO and OUTAGE activities. Page 2 of 2 This report shows only on-site and announced inspection procedures.

8/31/2020 1:21:51 PM