IR 05000331/2019004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000331/2019004
ML20028D691
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 01/28/2020
From: Billy Dickson
NRC/RGN-III/DRP/B2
To: Dean Curtland
NextEra Energy Duane Arnold
References
IR 2019004
Download: ML20028D691 (26)


Text

January 28, 2020

SUBJECT:

DUANE ARNOLD ENERGY CENTER - INTEGRATED INSPECTION REPORT 05000331/2019004

Dear Mr. Curtland:

On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Duane Arnold Energy Center. On January 9, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Billy C. Dickson, Jr, Chief Branch 2 Division of Reactor Projects

Docket No. 05000331 License No. DPR-49

Enclosure:

As stated

Inspection Report

Docket Number:

05000331

License Number:

DPR-49

Report Number:

05000331/2019004

Enterprise Identifier: I-2019-004-0065

Licensee:

NextEra Energy Duane Arnold, LLC

Facility:

Duane Arnold Energy Center

Location:

Palo, Iowa

Inspection Dates:

October 01, 2019 to December 31, 2019

Inspectors:

G. Hansen, Senior Emergency Preparedness Inspector

V. Myers, Senior Health Physicist

C. Norton, Senior Resident Inspector

T. Ospino, Reactor Engineer

G. Roach, Senior Operations Engineer

J. Seymour, Operations Engineer

Approved By:

Billy C. Dickson, Jr, Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Duane Arnold Energy Center, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The unit began the inspection period at rated thermal power. On November 2, 2019, the unit was down powered to 60 percent power for a control rod sequence exchange. The unit was returned to full power on November 3, 2019 and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems on November 4, 2019:
  • Control building heating ventilation and air conditioning (HVAC)
  • Reactor building HVAC

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated system configurations during a partial walkdowns of the following areas:

(1)

'A' emergency service water system on October 2, 2019

(2) High pressure coolant injection system on October 8, 2019
(3) Standby liquid control system on October 9, 2019
(4) Control rod drive system on October 15, 2019 (5)

'A' residual heat removal system on November 5, 2019 (6)

'A' core spray system on November 7, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Torus basement on October 7, 2019

Inspection Activities - Underground Cables (IP Section 02.02c.) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Cable vaults MH106 and MH107 on October 9, 2019

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from November 4 through December 12, 2019

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations

The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on November 21, 2019

Annual Requalification Operating Tests

The inspectors evaluated the adequacy of the facility licensees annual requalification operating test

Administration of an Annual Requalification Operating Test

The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives

Requalification Examination Security

The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised

Remedial Training and Re-examinations

The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions

The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses

Control Room Simulator

The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46

Problem Identification and Resolution

The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated a reactor plant power evolution and rod sequence exchange on November 3, 2019

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator requalification training and activities on October 1, 2019

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Electric fire pump minimum flow valve on October 25, 2019
(2) Control room annunciator horn on November 5, 2019

Quality Control (IP Section 02.02) (1 Sample)

The inspectors evaluated maintenance and quality control activities associated with the following equipment performance activities:

(1) Quality control sample for an emergency service water exchange of a differential pressure indicator switch on November 7, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) A small spurious increase in reactor power on October 24, 2019
(2) The unplanned unavailability of the 'A' control building chiller on December 20, 2019
(3) Reactor core isolation coolant unavailability for operability test and system walkdown on December 3, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (1 Sample)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Condition Report (CR) 02329060, emergency service water and well water abnormal indication on October 16, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Following 'A' and 'B' rod block monitor repairs after receiving spurious alarms when selecting control rods on October 3, 2019
(2) Following calibrations of the LOW LOW pressure set point channels on October 15, 2019
(3) Following repack of CV1956A, essential service water to 'A' control building chiller on October 29, 2019
(4) Following 'A' containment spray logic calibration on October 30, 2019
(5) Following repair of 'C' residual heat removal pump torus suction isolation valve on November 7, 2019
(6) Following repairs to 'A' diesel generator air start check CV 32-0043 on November 19, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated forced outage readiness on November 5, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) High pressure coolant injection system operability test on October 23, 2019
(2) In field activities associated with reactor core isolation coolant system operability test on December 3, 2019
(3) In field activities associated with standby liquid control operability test on December 5, 2019

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspector completed the evaluation of submitted Emergency Action Level and Emergency Plan changes on November 21, 2019. This evaluation does not constitute NRC approval.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 02.01) (1 Sample)

The inspectors evaluated radiological hazards assessments and controls.

(1) The inspectors reviewed the following:

Radiological Surveys

  • Refuel floor
  • Reactor water clean up pump room
  • Heater bay
  • Torus rooms

Risk Significant Radiological Work Activities

  • Tri-nuke filter removal from spent fuel pool
  • Reactor water clean up pump removal

Air Sample Survey Records

  • Sample 19-145, refuel floor
  • Sample 19-19, reactor water clean up pump room

Instructions to Workers (IP Section 02.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1) The inspectors reviewed the following:

Radiation Work Packages

  • 19-0112, Refuel Floor Pool Work
  • 19-0051, Routine Work and Inspections
  • 19-0600, High Steam Areas at Power

Electronic Alarming Dosimeter Alarms

  • Dose rate alarm on dosimeter serial number 029216 on 11/12/2018
  • Dose rate alarm on dosimeter serial number 048617 on 06/03/2019
  • Dose rate alarm on dosimeter serial number 897998 on 08/15/2019

Labeling of Containers

  • Rebuild equipment on the turbine operating deck
  • Refuel floor spare rigging container
  • 55 gallon drums in the radioactive waste building
  • Dry active waste storage area containers

Contamination and Radioactive Material Control (IP Section 02.03) (1 Sample)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors verified the following sealed sources are accounted for and are intact:
  • Source 3826
  • Source 734

Radiological Hazards Control and Work Coverage (IP Section 02.04) (1 Sample)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors also reviewed the following radiological work package for areas with airborne radioactivity:
  • None were available for review during this inspection.

High Radiation Area and Very High Radiation Area Controls (IP Section 02.05) (1 Sample)

(1) The inspectors evaluated risk-significant high radiation area and very high radiation area controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 02.06) (1 Sample)

(1) The inspectors evaluated radiation worker performance and radiation protection technician proficiency.

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors walked down the following gaseous and liquid radioactive effluent monitoring and filtered ventilation systems to assess the material condition and verify proper alignment according to plant design:

(1)

  • Low level radioactive waste building ventilation system
  • Ground water mitigation systems

Calibration and Testing Program (Process & Effluent Monitors) (IP Section 02.02) (1 Sample)

The inspectors reviewed the following gaseous and liquid effluent monitor instrument calibrations and tests:

(1)

  • Reactor building Kaman 6

Sampling and Analysis (IP Section 02.03) (1 Sample)

The inspectors reviewed the following:

(1) Radioactive Effluent Sampling and Analysis Activities
  • Permanent ground water mitigation system sampling
  • Temporary ground water mitigation system sampling
  • Reactor building gaseous effluent system sampling

Instrumentation and Equipment (IP Section 02.04) (1 Sample)

The inspectors reviewed the following radioactive effluent discharge system surveillance test results:

(1) Standby gas treatment system

Dose Calculations (IP Section 02.05) (1 Sample)

The inspectors reviewed the following to asses public dose:

(1) Liquid and Gaseous Discharge Permits
  • Liquid discharges made 10/23/2019 through 10/28/2019 for the temporary ground water mitigation system
  • Liquid discharges made 10/23/2019 through 10/30/2019 for the permanent ground water mitigation system

Annual Radiological Effluent Release Reports

  • 2017 Annual Radioactive Material Release Report
  • 2018 Annual Radioactive Material Release Report

Abnormal Gaseous or Liquid Tank Discharges

  • None were available for review during this inspection.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (October 1, 2018 to September 30, 2019)

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) Unit 1 (October 1, 2018 to September 30, 2019)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 1 (October 1, 2018 to September 30, 2019)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 1 (October 1, 2018 to September 30, 2019)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) October 1, 2018 to September 30, 2019

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in integrated process radiation monitor issues that might be indicative of a more significant safety issue on December 27, 2019

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors reviewed the licensee's corrective action program for potential adverse trends in addressing risk and risk communication on December 27,

INSPECTION RESULTS

Observation: Addressing Risk and Risk Communication 71152 In August of 2019, the inspectors identified a negative trend in addressing risk and risk communication. Examples include:

  • During the 2018 refueling outage, the risk associated with work on the condensate demineralizer instrument air filter housing was not communicated to the workers. This resulted in the workers improvising a repair to the severely damaged and degraded condensate demineralizer air filter housing. The improvised repair failed while the plant was at full power. Demineralizer flow was lost. Subsequently, operators manually scrammed the reactor due to rapidly lowering reactor water level. The inspectors documented this event in Inspection Report 05000331/2019002 and the licensee reported this as detailed in License Event Report 05000331/2019-001-00.
  • In July 2019, the licensee did not adequately communicate identified risks associated with fuel mixture adjustments on the diesel fire pump engine during a maintenance inspection. The licensee did not provide adequate oversight over an inexperienced vendor technician during the fuel mixture adjustment portion of the inspection. The technician made inappropriate adjustments and created an over rich fuel mixture that deposited combustibles in the exhaust line. This resulted in an exhaust line fire that spread to the non-safety related side of the pump house roof. The inspector evaluated this minor event during the 3rd Quarter of 2019.
  • Other minor examples included an inadequate brief for work on the well water flow recorder and an inadequate brief associated with taking an oil sample on an instrument air compressor. In the first example, a technician inadvertently allowed a loose wire to make contact which blew a fuse in the recorder circuit. This resulted in well water isolating from loads and unplanned entries into abnormal and emergency operating procedures. In the second example, an operator unfamiliar with the sample location breached the instrument air system causing a control room alarm for low instrument air pressure.

The inspectors monitored licensee actions to address risk and risk communication. The inspectors observed increased emphasis on risk communications during plan-of-day meetings and shop briefings. Duane Arnold Nuclear Assurance observed communications and wrote action requests to address substandard communications. This resulted in discussions that increased sensitivity to the importance of addressing risk and risk communication. The inspectors concluded that the licensee's increased emphasis on risk and risk communication resulted in improvements in station performance and a reduction in near miss occurrences.

Observation: Integrated Process Radiation Monitor Maintenance Issues and Post Accident Sampling 71152 Early in 2019, the inspectors observed an increasing trend in process radiation monitor issues. The inspectors noted several minor equipment and human performance related issues.

Equipment related issues, the result of component aging and spare part availability, included:

  • reoccurring off-gas detector failure alarms
  • multiple momentary radiation detector alarms with nothing recorded
  • control building intake radiation monitor trouble alarms and spurious standby filter unit actuations
  • recurring fuel pool exhaust radiation monitor downscale alarms
  • incorrect background on effluent ventilation radiation monitor

Human performance issues, the result of inadequate work focus in the field or procedure unfamiliarity, included:

  • incorrect background programmed into radiation monitors
  • using incorrect background values while calibrating a reactor building vent shaft radiation monitor
  • mispositioning components when calibrating effluent radiation monitors
  • lack of familiarity with emergency alternate sampling procedures for when accident range process radiation monitors are unavailable

The inspectors determined that the equipment related issues identified in this inspection sample, although many, were minor and adequately addressed. The inspectors determined that the human performance issues identified in this sample were adequately addressed.

The inspectors evaluated the licensee's readiness to do post-accident manual sampling, analysis and assessment of offsite releases with a concurrent loss of accident range effluent radiation monitors. The inspectors reviewed procedures, training records, walked down sample locations with technicians, and conducted interviews with supervisors and technicians. The inspectors concluded for the scenarios discussed, licensee staff have the training and supervisory skills to collect, analyze and assess post-accident releases with post-accident effluent radiation monitors unavailable.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On January 9, 2020, the inspectors presented the integrated inspection results to
  • Mr. D. Curtland, Director of Site Operations and other members of the licensee staff.
  • On October 24, 2019, the inspectors presented the radiation protection program inspection results to Mr. D. Curtland, Director of Site Operations and other members of the licensee staff.
  • On November 21, 2019, the inspectors presented the Emergency Action Level and Emergency Plan Changes Inspection inspection results to Mr. M. Davis, Licensing Manager and other members of the licensee staff.
  • On November 21, 2019, the inspectors presented the radiation protection program inspection results to Mr. D. Curtland, Director of Site Operations and other members of the licensee staff.
  • On November 22, 2019, the inspectors presented the Biennial inspection of the licensed operator requalification program inspection results to Mr. R. Spading, Operations Director and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Miscellaneous

Seasonal

Readiness

Winter 2019 Memo Curtland to Moul

09/24/2019

71111.04Q Corrective Action

Documents

Condition Report

(CR) 02220863

1P230B Standby Liquid Control (SBLC) Pump Leakage

Update

08/17/2017

CR 02253601

'B' SBLC Pump Seal Leak

03/10/2018

CR 02258728

Sodium Penta Borate Crystal Under 1P230B

04/10/2018

CR 02261588

(Previously Identified) 1P230B SBLC Leak Rate

Update-2dpm

04/26/2018

Drawings

BECH-M117

Control Rod Drive Hydraulic System

Miscellaneous

'A' Emergency Diesel Generator Outage Work Plan Spread

Sheet

Procedures

OI 149

Residual Heat Removal (RHR) System

170

OI 149A2

'A' RHR System Valve Lineup

OI 151

Core Spray System

OI 151A2

'A' Core Spray System Valve Lineup

OI 151A6

Core Spray System Control Panel Lineup

OI 152

High Pressure Coolant Injection (HPCI) System

20

OI 152A2

HPCI System Valve Lineup

OI 153

SBLC

OI 153A1

SBLC System Electrical Lineup

OI 153A2

SBLC System Valve Lineup

OI 255

Control Rod Drive Hydraulic System

OI 255A3

Control Rod Drive System HCU Valve Lineup

OI 416

RHR Service Water System

OI 416A6

Residual Heat Removal Service Water System Control Panel

Lineup

OI 454

Emergency Service Water System

STP 3.5.1-05

HPCI System Operability Test

STP NS540002-A 'A' Emergency Service Water Operability Test

STP NS550003

Surveillance Test Procedure (STP) ASME CDR Accumulator

Check Valve test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

40637955-01

GWPP Mitigation System / 'A' Emergency Service Water

Operability test

09/26/2019

71111.06

Drawings

GMP-ELEC-39

Electrical Man-Hole Inspection

71111.11B

Corrective Action

Documents

CR 2263827

PDA Interim Report - Operations

05/11/2018

CR 2281632

Tech Spec 3.0.4 Question

09/22/2018

CR 2287125

IRM Upscale Activated and Reset

10/21/2018

CR 2303207

Invoked T.S. 5.2.2.C

2/23/2019

CR 2305415

Near Miss - Exam Validation Session on Simulator Printer

03/12/2019

Engineering

Changes

278899

Replace River Water Make-up System Controllers

284591

Replacing Transverse Incore Probe Drawers and Removing

XY Plotters from Panel 1C13

288619

Replacing and Removing Switchyard Breaker Handswitches

and Indicating Lights from Panel 1C08

Miscellaneous

Simulator Review Committee Meeting Minutes

06/05/2019

Simulator Review Committee Meeting Minutes

10/11/2018

2018 DAEC NRC

Annual Operating

Exam Report

Examination Summary

08/08/2018

2018 Operability

and Steady State

Test Data

21.4% Power Test

10/01/2018

2018 Operability

and Steady State

Test Data

53.7% Power Test

10/01/2018

2018 Operability

and Steady State

Test Data

78.9% Power Test

10/02/2018

2018 Operability

and Steady State

Test Data

99.1% Power Test

10/02/2018

2018 Operability

and Steady State

Test Data

Stability Test @ 100% Power

10/02/2018

2019 Written

Written Examination Sample Plan

2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Sample Plan

DAEC 2017

LOCT Biennial

Exam

Examination Summary

2/15/2017

DAEC BRE

Written Exam Development Methodology Matrix

2017

DAEC LOCT Two

Year Plan

Training Plan

2018-2019

ESG and JPM

Sample Plan

Operating Test Sample Plan

2019

JPM 2.4.35-01

Job Performance Measure

JPM 2.4.41-23

Job Performance Measure

JPM 201003-03

Job Performance Measure

JPM 215001-01

Job Performance Measure

JPM 217000-01

Job Performance Measure

JPM 259001-12

Job Performance Measure

JPM 264000-10

Job Performance Measure

JPM 295004-02

Job Performance Measure

JPM 304.2-07.02-

Job Performance Measure

JPM 304.2-07.02-

Job Performance Measure

Normal Evolution

3.4.3.3

Reactor Core Reload and Core Performance Testing

11/12/2018

Normal Evolution

STP 3.5.1-01

Core Spray System Operability Test

04/12/2018

ODI-009

Individual Status Change Letter (Active)

08/13/2018

ODI-009

Individual Status Change Letter (Active)

08/28/2018

OP-302

Quarterly Personnel Watchstanding Verifications, Various

2017-2019

PDA OPS 50008

2019 LOCT Biennial Comprehensive Written Exam (RO)

Week 1

PDA OPS 50008

2019 LOCT Biennial Comprehensive Written Exam (RO)

Week 3

PDA OPS 50008

2019 LOCT Biennial Comprehensive Written Exam (SRO)

Week 3

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PDA OPS ESG

350

Simulator Exercise Guide

PDA OPS ESG

351

Simulator Exercise Guide

PDA OPS ESG

354

Simulator Exercise Guide

PDA OPS ESG

356

Simulator Exercise Guide

Post Event

Simulator Testing

'B' FRV Closure and Scram

01/18/2019

Post Event

Simulator Testing

Feedwater Pumps Suction Pressure Trip and Manual Scram

06/18/2019

Scenario Based

Testing

OPS 19-1 NRC Scenario 1

04/19/2019

Scenario Based

Testing

OPS 19-1 NRC Scenario 2

04/19/2019

Scenario Based

Testing

OPS 19-1 NRC Scenario 3

04/19/2019

Simulator Testing

2018 Real Time and Repeatability Test

09/24/2018

Simulator

Transient Test

Loss of All Feedwater

10/17/2018

Simulator

Transient Test

Trip of One Recirculation Pump

10/17/2018

Simulator

Transient Test

Unisolable Main Steam Line Break

10/17/2018

TR-AA-220-1004-

F01

LOCT Annual/Biennial Exam Results Summaries, Various

11/20/2019

TR-AA-230-1000-

F10

Remediation

11/16/2017

TR-AA-230-1007-

F01

Crew Simulator Evaluation Form

11/19/2019

TR-AA-230-1007-

F02

Individual Simulator Evaluation Forms, Various

11/19/2019

TR-AA-230-1007-

STA Simulator Evaluation Forms, Various

11/19/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

F03

TR-AA-230-1007-

F13

Crew Grading Attachments, Various

11/19/2019

TR-AA-230-J405

Training Review Board

11/13/2017

Training

Attendance

Records

Curricula Item Status Matrices, 2017-2019

11/18/2019

Procedures

1801.4

Simulator Configuration Management

OI 152

High Pressure Coolant Injection System

20

OP-AA-100-1001

License Maintenance and Activation

SA-AA-101-1000

NRC Operator License Application and Renewal

Requirements

TR-AA-201-1000-

F01

Licensed Operator Continuing Training 2018-2019 Training

Plan

06/29/2018

TR-AA-201-1000-

F02

DAEC Licensed Operator Continuing Training Program

Description

10/13/2019

TR-AA-201-1000-

F02

Training Program Description

TR-AA-220-1002

NRC Licensed Operator Exam Security

TR-AA-220-1004

Licensed Operator Continuing Training Annual Operating

and Biennial Written Exams

TR-AA-221-1000

Simulator Change Control

TR-AA-230-1007

Conduct of Simulator Training and Evaluation

TR-AA-230-1009

Training Examination Security

Self-Assessments

2019 DAEC Simulator Annual Report

11/13/2019

AR - L2A #:

NAMS 2287755 /

276322

Pre-NRC Licensed Operator Requalification Program

Assessment

08/30/2019

NG-18-0141

2018 DAEC Simulator Annual Report

11/27/2018

Work Orders

SWR 2010

PEST Issue: Total Core Flow, Core Plate DP, Jet Pump DP

01/17/2019

SWR 2011

PEST Issue: B024 RWCU System Cooldown Issue

01/17/2019

SWR 2012

PEST Issue: Main Steamline Flowrates Issue

01/17/2019

SWR 2013

PEST Issue: Containment Pressure/Temperature Response

01/17/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

to Scram/ Recirc Trips

SWR 2014

PEST Issue: Torus Water Level Response to HPCI, RCIC

Running Issues

01/17/2019

SWR 2066

Meteorological Recorder YR-9400 Multiple Issues

SWR 2067

Turbine Vibes too Elevated at Critical Turbine RPMs After

Trip

SWR 2248343

HPCI Auxiliary Oil Pump Handswitch Wobbly

SWR 2257397

Hardened Containment Vent System Radiation Monitor

Display Inoperable

SWR 2306441

Primary Containment Isolation System Valve Closing Time

not within Specification

71111.11Q Corrective Action

Documents

CR 02334071

RPS Relays did not Cycle as Expected for 'B' Inboard Main

Steam Isolation Valve

11/03/2019

Miscellaneous

Evaluated

Scenario

Scenario ESG 2019D-01E

Procedures

NS930002

Main Turbine Stop and Combined Intermediate Valves Test

STP 3.3.1.1-13

Turbine Control Valve Recirculation Pump Trip Logic and

Reactor Protection System Instruments Functional Test

STP 3.3.1.1-17

Main Steam Line Isolation Valve Functional Test

STP 3.3.1.1-19

Functional Test of Turbine Stop Valve Closure Input to

Reactor Protection System Recirculation Pump Trip

71111.12

Corrective Action

Documents

CR 02331615

PSV3302 Internal Parts Degradation

10/15/2019

Miscellaneous

Roy Hanson Email: Electric Fire Pump Unavailability

10/17/2019

Operations Shift Log

10/22/2019

NG-006M

Electrical Termination Sheet

NG-006M

Electrical Termination Sheet

NG-015K

Shift Manager, CRS, WCCS, and STA Turnover Form dated

October 22, 2019

Work Orders

40478652-01

Replace and Calibrate Stilling Basin Differential Pressure

Indicator LIS4935A

11/07/2019

4068329-01

PSV3301; Rebuild and Repack

10/15/2019

71111.13

Corrective Action

Documents

Shift Operations Log

2/03/2019

CR 02327515

Observed Step Rise in Reactor Power

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Shift Operations Logs

2/03/2019

Risk Analysis

White Paper on 'A' Control Building Chiller Risk

Work Plan

40644666

Calibrate I/I 6924A, as part of 'A' CB Chiller AC to DC

Converter Issue

2/05/2019

Work Orders

40194425

Calibrate I/16924B

08/29/2013

236612

Calibrate I/I6924A 'A' CB Chiller AC to DC Converter Card

03/23/2014

Work Plan

40644666

'A' CB Chiller AC to DC Converter Card

2/05/2019

71111.15

Corrective Action

Documents

CR 02329060

Emergency Service Water Abnormal Indication

09/24/2019

71111.19

Corrective Action

Documents

CR 02329584

Rod Block Monitor (RBM) Issues when Selecting a Rod

09/28/2019

CR 02329585

RBM Alarms when Selecting Control Rod

09/28/2019

CR 02333339

CV1956A Packing Leak has Risen to 30 dpm

10/28/2019

CR 02333812

MO 2015 Tripped on Thermal Overload When Timing Open

Per STP

10/31/2019

Drawings

BECH-M132<1>

Diesel Generator Systems

Miscellaneous

Work Plan

40682200-01

Air Receiver 1T-115A Outlet Check Valve

09/17/2019

Work Plan

40682200-01

Air Receiver 1T-115A Outlet Check Valve

09/18/2019

Work Plan

40682200-01

Air Receiver 1T-115A Outlet Check Valve

11/08/2019

Work Plan

40682200-05

Air Receiver 1T-115A Outlet Check Valve

11/19/2019

Work Plan

40682200-05

Air Receiver 1T-115A Outlet Check Valve

11/20/2019

Procedures

CAL-M01-071

Valve Number CV1956A

ER-AA-122-1001

Printed Circuit Board Life Cycle Management Plan

ER-AA-122-1001

Printed Circuit Board Life Cycle Management Plan

GMP-Test-58

Air Operated Valve Diagnostic Testing

OI 878.5

Rod Block Monitoring System

STP 3.1.3-01

Control Rod Exercises

STP 3.3.2.1-01

Rod Block Monitor Functional Check

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

STP 3.3.2.1-01

Rod Block Monitor Functional Check

STP 3.3.2.1-02

Rod Block Monitor Calibration

STP 3.3.2.1-02

Rod Block Monitor Calibration

STP 3.3.5.1-29A

'A' Containment Spray Logic System Functional Test and

RHR Timer Calibration

STP 3.3.6.3-03

Low-Low Set Pressure Set Point Channels Functional Test

STP 3.8.1-11A

Standby Diesel Generator Air Compressor and Air Start

Check Valve Test

STP NS540002A

'A' Emergency Service Water

Work Orders

40609798-01

CV-1959A-0 Perform AOV Diagnostic Testing

10/28/2019

40619490-01

'A' Containment Spray Logic System Functional Test and

RHR Timer Calibration

10/29/2019

40642865-01

Low-Low Set Pressure Setpoint Chan Functional test

10/14/2019

40649752-02

'B' RBM Clean Cards and Cabinet in RBMS

10/03/2019

40690161-05

C-RHR Pump Torus Suction Isolation Valve Post

Maintenance Test

11/07/2019

WR 94198480

Work Request for V-32-043, 'A' Emergency Diesel Starting

Air Check Valve, Failed Surveillance Test

09/03/2019

71111.20

Miscellaneous

Forced Outage Scope List

05/08/2019

71111.22

Procedures

NS500001

Reactor Core Isolation Cooling System Leakage Inspection

Walkdown

NS530001

Standby Liquid Control System Leakage Inspection

Walkdown

STP 3.1.7-01

Standby Liquid Control Pump Operability Test

STP 3.5.1-05

HPCI System Operability Test

STP 3.5.3-02

Reactor Core Isolation Cooling Operability Test

71114.04

Miscellaneous

CFR 50.54(q) Screening and Evaluation Personnel

Training and Qualification Records

07/03/2019

PCR 2269673

CFR 50.54(q) Screening and Evaluation Forms, Joint

Information Center (JIC) Relocation and Staff

Reorganization Screen and Evaluation

07/17/2018

PCR 2277166

CFR 50.54(q) Screening Form, Emergency Plan,

Appendix 6 - Correct Typo"

04/22/2019

PCR 2290125

CFR 50.54(q) Screening Form, Emergency Procedures

2/19/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Update due to NRC Approval of LAR 308 - EAL Scheme

Revision - Editorial Changes

PCR 2299716

CFR 50.54(q) Screening and Evaluation Forms,

Emergency Plan, Section G Revision - Public Information

Requirements and Education Screen and Evaluation

2/05/2019

PCR 2302439

CFR 50.54(q) Screening and Evaluation Forms,

Emergency Plan, Section B Revision to Reflect

Reorganization of EOF and JIC Screen and Evaluation

04/02/2019

PCR 2310522

CFR 50.54(q) Screening and Evaluation Forms,

Emergency Plan, Section B Revision - TSC Staff

Reorganization Screen and Evaluation

05/14/2019

PCR 2313357

CFR 50.54(q) Screening and Evaluation Forms, EAL

Matrix and EAL Technical Bases Document Revisions

Screen and Evaluation

05/14/2019

Procedures

DAEC Emergency Plan, Section B - Emergency Response

Organization

DAEC Emergency Plan, Section B - Emergency Response

Organization

DAEC Emergency Plan, Appendix 6 - Definitions

DAEC Emergency Plan, Appendix 6 - Definitions

DAEC Emergency Plan, Section G - Public Education and

Information

DAEC Emergency Plan, Section G - Public Education and

Information

2310525

CFR 50.54(q) Screening and Evaluation Forms,

Emergency Plan, Section B Revision - TSC Staff

Reorganization Screen and Evaluation

05/14/2019

EP-AA-100-1007

Evaluation of Changes to the Emergency Plan, Supporting

Documents and Equipment [10 CFR 50.54(Q)]

PCR 2299718

CFR 50.54(q) Screening and Evaluation Forms,

Emergency Plan, Section G Revision - Public Information

Requirements and Education Screen and Evaluation

71124.01

Miscellaneous

Radiation Protection Work Plan For HPCI/RCIC Runs

01/10/2019

Procedures

HPP 3104.03

Radiological Air Sample Collection and Analysis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radiation

Surveys

Form HP-48

Air Sample Record For Tri-Nuke Filter Removal

10/15/2019

Form HP-48

Air Sample Record For Reactor Water Clean Up Pump Work

2/18/2019

Form HP-48

Air Sample Record For High Pressure Coolant Injection

Surveillance

10/23/2019

PDA-M-

20170112-2

Surveys For High Pressure Coolant Injection and Torus

Rooms

01/12/2017

PDA-M-

20190218-2

Reactor Water Clean Up Pump Removal Surveys

2/18/2019

PDA-M-

20190219-1

Reactor Water Clean Up Pump Removal Surveys

2/19/2019

PDA-M-

20190530-2

Heater Bay Surveys For Camera Installation

05/30/2019

PDA-M-

20190603-7

Heater Bay Surveys For Steam Leak Isolation

06/03/2019

PDA-M-

20191015-1

Refuel Floor Tri-Nuke Filter Removal Surveys

10/15/2019

PDA-M-

20191016-2

Refuel Floor Tri-Nuke Filter Removal Surveys

10/16/2019

PDA-M-

20191023-2

Surveys For Torus Rooms

10/23/2019

PDA-M-

20191023-3

Surveys For High Pressure Coolant Injection Rooms

10/23/2019

Radiation Work

Permits (RWPs)

19-0051

Routine Work and Inspections

19-0112

Refuel Floor Pool Work

19-0600

High Steam Areas At Power

Work Orders

40624340

Sealed Source Leakage Test

07/17/2019

71124.06

Corrective Action

Documents

298709

Kaman 5 Mid-Range Conversion Factor Incorrectly

Calculated

01/21/2019

Procedures

NS790601

Effluent Particulate and Iodine Sampling and Analysis

NS790708

Offsite Effluent Dose Calculations

NS790709

Ground Water Protection Program Mitigation System

PCP 10.1

MIDAS - Offsite Radiation Dose Assessment

Work Orders

40562421

Kaman 5 Calibration

01/03/2019

40608222

Standby Gas Treatment System Filter Efficiency

2/04/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

40617861

RE 1997: Replacement Detector

08/31/2018

40626760

Kaman 6 Calibration

10/17/2019

71151

Miscellaneous

Reactor

Oversight

Process

Radiological Effluent Technical Specifications/Offsite Dose

Calculation Manual NRC PI Data Calculation, Review and

Approval, 3rd Quarter 2019

Reactor

Oversight

Process

Residual Heat Removal NRC PI Data Calculation, Review

and Approval, 2nd Quarter 2019

Reactor

Oversight

Process

Cooling Water Support Systems NRC PI Data Calculation,

Review and Approval, 1st Quarter 2019

Reactor

Oversight

Process

Reactor Coolant Systems Specific Activity Samples NRC PI

Data Calculation, Review and Approval, 4th Quarter 2018

71152

Corrective Action

Documents

CR 02308485

Received Multiple Momentary Reactor Building Kaman

Alarms

04/02/2019

CR 02310749

RIM6101B Control Building Radiation Monitor Trouble and

'B' Standby Filter Unit Auto-Start

04/16/2019

Procedures

PSAP 6.1

Emergency Procedures for Effluent Sample Retrieval

6