Category:Legal-Affidavit
MONTHYEARML24022A3232024-01-22022 January 2024 Geha/Northstar Response to NRC Request for Additional Information Regarding Direct Transfer of Vnc Licenses ML23338A1312023-12-0404 December 2023 GE-Hitachi Nuclear Energy Americas, LLC, Additional Information to Geha and GNF-A Application for Order Consenting to Indirect Transfer of Control (Reference 1) ML23292A3362023-10-19019 October 2023 Northstar Vallecitos, LLC, Supplemental Information - Financial Qualifications ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23123A0752023-04-12012 April 2023 Response to NRC Request for Inspection Documents ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML22084A5782022-03-23023 March 2022 GNF-A/GEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML22080A1322022-03-21021 March 2022 GE-Hitachi Nuclear Energy Americas, LLC, NRC Request for Inspection Documents ML22061A0652022-03-0202 March 2022 GE-Hitachi Nuclear Energy Americas, LLC, NRC Request for Documents - Vallecitos Nuclear Center (Vnc) M200102, GEH - Response to NRC Request for Additional Information (Rai), March 16, 20202020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 ML20197A0122020-07-15015 July 2020 GEH - Response to NRC Request for Additional Information (Rai), March 16, 2020 M190202, GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-11-15015 November 2019 GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules ML19319B8452019-11-15015 November 2019 GEH - Third Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules M190065, GE-Hitachi Nuclear Energy Americas, LLC - Second Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules2019-03-28028 March 2019 GE-Hitachi Nuclear Energy Americas, LLC - Second Reply to NRC Request for Information Needed for GE-Hitachi Exemption Request for Alternate Decommissioning Schedules ML19080A0602019-03-19019 March 2019 Transmittal 19-008 M190061 GEH-GNF-A NRC Financial Assurance Update - 03192019 M180200, GE-Hitachi Nuclear Energy Americas, LLC - Response to NRC Request for Additional Information (RAI) Interim Status Report2018-10-23023 October 2018 GE-Hitachi Nuclear Energy Americas, LLC - Response to NRC Request for Additional Information (RAI) Interim Status Report ML18151A8612018-05-31031 May 2018 GEH Response to NRC Request for Additional Information (RAI) M180115, GEH Response to NRC Request for Additional Information (RAI)2018-05-31031 May 2018 GEH Response to NRC Request for Additional Information (RAI) ML18096A0392018-04-0505 April 2018 GEH/GNF-A Financial Assurance of Decommissioning Funds - Standby Trust Agreement Amendments ML18087A1762018-03-27027 March 2018 Letter 18-022 M180065 GEH-GNF-A NRC Decommissioning Surety Bonds 3-27-18 ML18078A1912018-03-19019 March 2018 GEH/GNF-A Financial Assurance of Decommissioning Funds - Supplemental Information M180053, GEH/GNF-A Financial Assurance of Decommissioning Funds - Supplemental Information2018-03-19019 March 2018 GEH/GNF-A Financial Assurance of Decommissioning Funds - Supplemental Information ML0702505252007-01-19019 January 2007 Request for NRC Consent to the Transfer of Control of GE Licenses to GE-Hitachi Nuclear Energy America, LLC, and for Approval of Conforming Amendments 2024-01-22
[Table view] Category:Letter
MONTHYEARML24331A2292024-12-20020 December 2024 CA SHPO Consultation Letter ML24330A0472024-12-0404 December 2024 NRC to Fws Designation of Northstar LLC as the Non Federal Representative for the Vbwr Ad Getr ML24326A1902024-11-21021 November 2024 GEH Notification of GE Vernova and GE (Aerospace) Company Stock Beneficial Ownership Filing ML24299A1302024-11-0707 November 2024 Historic and Cultural Resources Amendment Request for Supplemental Information IR 05000018/20240022024-10-29029 October 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2024-002, 05000070/2024002, 05000183/2024002, and 050-00073/2024002 ML24299A0682024-10-25025 October 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24284A1182024-10-10010 October 2024 GEH - Notification of GE Company Stock Beneficial Ownership Filing ML24271A1572024-09-27027 September 2024 Notification of Planned Closing, Trust Fund Balance at Transfer and Proof of Insurance ML24270A2242024-09-26026 September 2024 License Amendment Request - Historic and Cultural Resources Review Vallecitos Boiling Water Reactor and General Electric Test Reactor ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24165A2812024-06-13013 June 2024 Northstar Vallecitos, LLC, Documentary Evidence of Insurance Vallecitos Nuclear Center ML24157A0882024-06-0505 June 2024 GE-Hitachi Nuclear Energy Americas, LLC, Vallecitos Nuclear Center (Vnc) Organization Change ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000018/20240012024-05-29029 May 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2024-001, 050 00070/2024-001, 050-00183/2024-001, and 050-00073/2024-001 ML24039A0192024-04-25025 April 2024 Order Approving Transfer of the Vallecitos Nuclear Center Licenses and Conforming License Amendments ML24088A2392024-03-28028 March 2024 GE-Hitachi Nuclear Energy Americas, LLC, NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed - Step Two ML24051A1802024-02-22022 February 2024 Boiling Water Reactor License Termination Plan Request for Additional Information - Letter ML24032A1082024-02-0101 February 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24022A3232024-01-22022 January 2024 Geha/Northstar Response to NRC Request for Additional Information Regarding Direct Transfer of Vnc Licenses IR 05000018/20230022024-01-0909 January 2024 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2023002, 05000070/2023002, and 05000183/2023002 ML23345A1222023-12-21021 December 2023 Request for Additional Information Regarding the Direct Transfer of Control of Vallecitos Nuclear Center Licenses and Conforming License Amendments ML23345A0812023-12-11011 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A1312023-12-0404 December 2023 GE-Hitachi Nuclear Energy Americas, LLC, Additional Information to Geha and GNF-A Application for Order Consenting to Indirect Transfer of Control (Reference 1) ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed ML23279A1322023-11-13013 November 2023 GE Hitachi Nuclear Energy - Vallecitos Nuclear Center, Getr Decommissioning Plan – (License Number TR-1, Docket Number 50-70) ML23310A1132023-11-0909 November 2023 FRN-Notice of Consideration of Approval of Direct Transfer of Control of Vallecitos Nuclear Center Licenses Conforming License Amendments Opportunity for a Hearing Transmittal Letter ML23305A0522023-11-0101 November 2023 GE Hitachi Nuclear Energy Additional Supplemental Information - Revised Exhibit H ML23275A1742023-10-26026 October 2023 Acceptance Review of Application for Consent to Direct Transfer of Control of Vallecitos Nuclear Center Licenses and Conforming License Amendments ML23292A3362023-10-19019 October 2023 Northstar Vallecitos, LLC, Supplemental Information - Financial Qualifications ML23276B3952023-10-13013 October 2023 The U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML23269A1062023-09-26026 September 2023 GEH Description of Process for Decommissioning the Vallecitos Nuclear Center (Vnc) Shutdown Reactors - Getr Decommissioning Plan ML23261A5922023-09-15015 September 2023 GE-Hitachi Nuclear Energy Americas, LLC, License Termination Plan for the Vallecitos Boiling Water Reactor License DPR-1 ML23257A2492023-09-14014 September 2023 Cultural Resources Report ML23248A2322023-09-0505 September 2023 GE Hitachi Nuclear Energy - Supplemental Information - Proposed Conforming Amendments & License Conditions ML23244A2472023-09-0101 September 2023 GE-Hitachi Nuclear Energy Americas, LLC and Northstar Vallecitos, LLC, Application for Consent to Direct Transfers of Control of Licenses and Related Conforming License Amendments ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML23150A0962023-05-30030 May 2023 GE Hitachi Nuclear Energy, Nuclear Center (Vnc) Organization Change ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals IR 05000018/20230012023-05-0505 May 2023 GE Hitachi Nuclear Energy - NRC Inspection Report 05000018/2023001, 05000070/2023001, and 05000183/2023001 ML23123A0752023-04-12012 April 2023 Response to NRC Request for Inspection Documents ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23090A1802023-03-31031 March 2023 GEH - Financial Assurance Status Reports ML23083B3402023-03-24024 March 2023 GEH Annual Shutdown Reactor Reports for the Year 2022 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23054A3332023-02-23023 February 2023 GEH Notification of GE Company Stock Beneficial Ownership Filing ML23018A2832023-01-19019 January 2023 GE-Hitachi Nuclear Energy Americas, LLC Response to NRC Inspection Report 050-00018/2022-002; 050-00070/2022-002; 050-00183/2022-002 and Notice of Violation ML22339A1742022-12-13013 December 2022 GE Hitachi Nuclear Energy NRC Inspection Report 05000018/2022002 05000070/2022002 and 05000183/2022002 IR 05000018/20220022022-12-13013 December 2022 GE Hitachi Nuclear Energy NRC Inspection Report 05000018/2022002 05000070/2022002 and 05000183/2022002 2024-09-27
[Table view] |
Text
HITACHI Proprietary Information Notice to this letter contains GE Hitachi Nuclear Energy proprietary information which is to be withheld from public disclosure in accordance with 10 CFR 2.390. Upon removal of this attachment, the balance of this letter may be made public.
M210036 March 22,2021 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555-001 GE Hitachi Nuclear Energy Matt J. Feyrer Site Manager.
Vallecitos Nuclear Center 6705 Vallecitos Rd Sunol, CA 94586 USA T9259186018 Matt.feyrer@ge.com
Subject:
GEH Supplemental Information for Request for Additional Information (RAI)
Response Due April28, 2021
References:
- 1)
Letter, J.D. Parrot (NRC) to M.F. Feyrer, GE Hitachi Request for Alternate Decommissioning Schedule for VBWR at VNC - Request for Additional Information, (EPID L-2017-LLA-0052), dated 7/15/20.
- 2)
Letter, M.F. Feyrer to J.D. Parrot (NRC) Request to Extend Request for Additional Information (RAJ) Response Due Date to April28, 2021, dated 8/14/2020.
- 3)
Virtual meeting held 3/18/2021 between NRC and GEH Engineering discussing pending RAI responses.
On March 18, 2021, during a virtual meeting (Reference 3), GEH Engineering and VNC Management presented detailed information to the NRC relevant to the RAI identified in reference 1. The presentation slides used during that meeting are provided as Attachment 2 to this letter and are intended as supplemental information pending a full response to the RAI that is currently due by April28, 2021 (Reference 2). These slides contain GEH proprietary information that is requested to be withheld from public disclosure pursuant to 10 CFR 2.390.
If you have any questions regarding this matter, please contact me at (925) 918-6018.
Matt Feyrer, Site Manager Vallecitos Nuclear Center : GEH Affidavit : VBWR Seismic Evaluation Presentation (contains proprietary information) cc: NRC Region IV Administrator S. Anderson, NRC RIV J. Parrott, NRC NMSS/DFM MJF 21-002
US NRC March 22, 2021 M210036 Page 1 of 2 It Matthew J. Feyrer, state as follows:
AFFIDAVIT (1)
I am the Operations Manager, of the Vallecitos Nuclear Center, GE Hitachi Nuclear Energy Americas, L.L.C.
(GEH) and have been delegated the function by GEH of reviewing the information described in paragraph (2) which is sought to be withheld in Attachment2 to GEH's letter, M210036, Matt Feyrer to USNRC entitled GEH Supplemental Information for Request for Additional Information (RAI) Response Due April 28, 2021, and have been authorized to apply for its withholding.
(2)
GEH proprietary information is contained in Attachments 2 to this letter and is identified by the statement "GEH Proprietary Information -Non-public".
(3)
In making this application for withholding of proprietary information of which it is the owner or licensee, GEH relies upon the exemption from disclosure set forth in the Freedom of Information Act (FOIA), 5 USC Sec.
552(b)(4), and the Trade Secrets Act, 18 USC Sec. 1905, and NRC regulations 10 CFR 9.17(a)(4), and 2.390(a)(4) for trade secrets (Exemption 4). The material for which exemption from disclosure is here sought also qualifies under the narrower definition of trade secret, within the meanings assigned to those terms for purposes of FOIA Exemption 4 in, respectively, Critical Mass Energy Project v. Nuclear Regulatory Commission. 975 F2d 871 (DC Cir. 1992), and Public Citizen Health Research Group v. FDA, 704 F2d 1280 (DC Cir. 1983).
(4)
The information sought to be withheld is considered to be proprietary for the reasons set forth in paragraphs (4 )a. and (4 )b. Some examples of categories of information that fit into the definition of proprietary information arc:
- a.
Information that discloses financial, a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GEH's competitors without license from GEH constitutes a competitive economic advantage over GEH and/or other companies.
- b.
Information that, if used by a competitor, would reduce their expenditure of resources or improve their competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
(5)
To address 10 CFR 2.390(b)(4), the information sought to be withheld is being submitted to the NRC in confidence. The information is of a sort customarily held in confidence by GEH and is in fact so held. The information sought to be withheld has, to the best of my knowledge and belief, consistently been held in confidence by GEH, not been disclosed publicly, and not been made available in public sources. All disclosures to third parties, including any required transmittals to the NRC, have been made, or must be made, pursuant to regulatory provisions or proprietary and/or confidentiality agreements that provide for maintaining the information in confidence. The initial designation of this information as proprietary information, and the subsequent steps taken to prevent its unauthorized disclosure are as set forth in the following paragraphs (6) and (7).
(6)
Initial approval of proprietary treatment of a document is made by the manager of the originating component, who is the person most likely to be acquainted with the value and sensitivity of the information in relation to industry knowledge, or who is the person most likely to be subject to the terms under which it was licensed to GEH. Access to such documents within GEH is limited to a "need to know" basis.
(7)
The procedure for approval of external release of such a document typically requires review by the staff manager, project manager, principal scientist, or other equivalent authority for technical content, competitive effect, and determination of the accuracy of the proprietary designation. Disclosures outside GEH are limited to regulatory bodies, customers, and potential customers, and their agents, suppliers, and licensees, and others with a legitimate need for the information, and then only in accordance with appropriate regulatory provisions or proprietary and/or confidentiality agreements.
US NRC March 22, 2021 M210036 Page 2 of 2 (8) The information identified in paragraph (2) above is classified as proprietary because it contains details of GEH's processes, design and manufacturing facilities.
(9)
Public disclosure of the information sought to be withheld is likely to cause substantial harm to GEH's competitive position and foreclose or reduce the availability of profit-making opportunities. The facility design and licensing methodology is part of GEH's comprehensive safety and technology base, and its commercial value extends beyond the original development cost. The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation process. In addition, the technology base includes the value derived from providing analyses done with NRC-approved methods.
The research, development, engineering, analytical and NRC review costs comprise a substantial investment of time and money by GEH. The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial. GEH's competitive advantage will be lost if its competitors arc able to usc the results of the GEH experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of this information to GEH would be lost if the information were disclosed to the public. Making such information available to competitors without there having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall and deprive GEH of the opportunity to exercise its competitive advantage to seck an adequate return on its large investment in developing and obtaining these very valuable analytical tools.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on this 22nd day of March 2021.
Matthew J. Feyrer GE Hitachi Nuclear Energy Americas, L.L.C.