E-Mail from Sykes to Wert, CR3 Concrete Delamination Repair Schedule
ML101190439
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/26/2010
From: Sykes M D
NRC/RGN-II/DRP/RPB3
To: Munday J T, Wert L
Division Reactor Projects II
References
FOIA/PA-2010-0116
Download: ML101190439 (1)


Text

Franke, Mark From: Sykes, Marvin )F Sent: Tuesday, January 26, 2010 8:48 AM To: Wert, Leonard; Munday, Joel Cc: Franke, Mark; Diaz-Toro, Diana; Kennedy, Kriss; Saba, Farideh

Subject:

CR3 Concrete Delamination Repair Schedule The current plant schedules include these milestone dates to support mid-year restart. The licensee root cause is still not yet complete and therefore the specific details for concrete removal and repair have not been finalized.

Final root cause is expected mid-February.

Licensee is also developing PMT plan. [This information is provided for internal NRC use only]Relief Cut (I-Cut) Complete January 20 (Complete)

Tendon Detensioning Complete March 8 Delamination Removal Complete March 23 Concrete Repair Complete May 9 Tendon Retensioning Complete June 9 Post Repair Testing Complete June 17 Plant Restart June 22 RPB3 will continue to work closely with EngBr3 to coordinate inspection activities and develop schedules for status briefings and upcoming public meetings near Crystal River.Please call or e-mail if you have questions-Marvin 56