Exelon Slides 7/17/2018 PSDAR Meeting
ML18201A237
Person / Time
Site: Oyster Creek
Issue date: 07/17/2018
From: Dostal J P
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Lamb J G, NRR/DORL/LSPB, 415-3100
References
EPID L-2018-LRO-0022
Download: ML18201A237 (10)


Text

Decommissioning Plant Manager Jeff DostalOyster Creek NGSJuly 17, 2018

-PSDAR Public Meeting

Background

2Commercial Operation Date: December 23, 1969Capacity 637 megawatts (More than 600,000 homes)No. of employees: Approximately 450Total acreage: 779 acres Powering the CommunityExelon Contributions $20 MillionOyster Creek gave$400,000+ in 2017Community PartnersUnited Way of Monmouth and Ocean CountiesPopcorn Park ZooLacey Food BankNew Jersey Special OlympicsLighthouse CenterLacey Township Athletic FoundationMarine Mammal Stranding CenterConserve Wildlife Foundation 3

Powering the CommunityCommunity Outreach

-Energy Education Day

-Community Information Night

-Career and Science Fairs

-Weekly Interactions With Regional & Community-Based Media

-Volunteer Day Activities

-NRC Public Meetings

-State of the Plant Dinner

-Stakeholder Information Forum Oyster Creek conducts more than 15 tours per year, on averageOyster Creek visits more than20 schools and civic groupsper year, on average 4

Oyster Creek Physical Characteristics11Site is bounded by the streams of Oyster Creek and Forked River.The main source of cooling water is the Barnegat Bay via an intake canal along the South Branch of the Forked River.Upon Shutdown water usage will continue to be reduced, in the first two months flow through the Intake canal will be reduced by 96%.Total acreage: 779 acres

-152 acres on the West side of Route 9

-627 acres on Finninger Farm

-217 acres to be donated to Lacey Township Oyster Creek Decommissioning Strategy SAFSTOR (Target is March 2024)Exelon continues to assess all options for the decommissioning of Oyster Creek. We have selected SAFSTOR as our current strategy.

  • The planning for SAFSTOR has been performed while ensuring an efficient shift to Decon / Dismantlement can be made at any time.
  • In all strategies moving fuel to dry storage as soon as possible reduces risk and is the most efficient option.
  • All structures and systems not supporting fuel storage will be drained, deenergized and retired in place, ready for removal.
  • Restructure the site to an ISFSI only protected area with the rest of the industrial site in a dormant state
  • SafStor Strategy allows for natural radioactive decay, reducing dose to workers during decommissioning, and reducing the amount of contaminated waste material

.6 Site Decommissioning Phased Approach Oyster Creek Time Line (SafStor)Phase Objectives:Form & Charter Transition TeamsDevelop & Implement staffing plansStrategic Decisions developedDevelop and submit key LARs, PSDAR, and DCEPerform Scoping & Screening of SSCsPhase Objectives:Offload the coreImplement Permanently De

-fueled E-PlanImplement Certified Fuel Handler ProgramPhase Objectives:DC Activities start based on strategic planMovement of Fuel to ISFSI IAW Strategic PlanRetire Systems not required to support Fuel StorageImplement Defueled License & Tech SpecsPhase Objectives:Transition to Post Zr Window milestone E-planMovement of Fuel to ISFSIFinal system layup and SafStor PrepsComplete preparations for collapsing Site Protected AreaPhase Objectives:Transition to ISFSI only E-PlanContinue with DC activities based on strategic decisions Implement ISFSI only Security Plan 7Shutdown Decision Until Permanent ShutdownShutdown through Fuel Permanently Removed from RxAll Fuel Permanently Removal from Rx Until End of Zr WindowEnd of Zr Window Until Fuel Pool EmptyFuelin the SFP or ISFSI until Removed by DOELicense Termination Removal of ISFSI Pad & Site RestorationPhase III:2 to 5 Years Phase II:10 to 18 Months Transition Planning:5 to 2 Years Phase I:< 30 DaysPhase IV:10 to 49 Years Phase V: 2 to 4 YearsPhase Objectives:Restore Site based on Strategic decision Decommissioning TransitionSAFSTOR / DECONSiteRestorationSept2018Oct2018Oct 2019March 2024Sep 2034Dec 2077Sep 2078Jan 2018Rx PermanentDefueledDTO Fully StaffedEndZr WindowISFSI OnlyFuel AcceptedBy DOESite Decon& DemoCompleteLicenseTermination OC P-1 P-2 P-3 P-4EstimatedAll Fuel in Dry StorageNov 2023 Decommissioning

-Independent Spent Fuel Storage Installation 8*Fuel will be moved to dry storage as soon as possible.

  • The ISFSI site will be approximately six acres
  • Dry Cask storage systems have been certified to maintain structural integrity and function from flooding, high winds, and impacts.

9Oyster Creek Decommissioning Risk ChangePhase 130 DaysPhase 2 Phase 4Permanent Shutdown DecisionAnnouncedPermanent Shutdown T-5 Yrs T-1 T-0"End-of-Life""Decommissioning"Fuel in Fuel Pool to End of Zirc Fire WindowRx Shutdown to Permanent DefueledEnd of Zirc Fire to Fuel Pool EmptyMilestonesRisk and Need for Offsite REPFuel in ISFSI to license terminationDecommissioning TransitionSAFSTOR& DECONSite RestorationPhase 5Site Restoration Phase 3DTO StaffedJan 2015 Jan 2018 Sep 17 2018 Oct 2018 March 2021 Nov 2021 March 2022 Power OperationsPart 50LicenseDecommissioningPart 50LicensePart 50LicensePart 72LicenseOffsite Radiological REP RequirementNot to Scale T-2*Make Strategic Decisions

  • Develop Tactical Decom Plans
  • Submit License Amendments and Exemptions
  • Submit Post

-Shutdown Decom Activities Report and Decom Cost Estimate

  • Implement Decom Plans
  • Move fuel and SNM from Rx to Fuel Pool
  • Minimize system operation to those that support fuel storageLicense Terminated
  • All Fuel Transferred to DOE*Removal of ISFSI and final site restoration
  • Site placed in SAFSTOR*Establish ISFSI Only state
  • Site Decon & Dismantlement Key Takeaways
  • Exelon is committed to operating Oyster Creek safely and efficiently with a smooth transition into Site Decommissioning.
  • Nuclear, environmental, and industrial safety remain the core principles that drive our decommissioning plans.
  • The nuclear industry is developing expertise in decommissioning as a result of other industry shutdowns, we will continue building on that experience from earlier efforts.
  • Exelon will maintain an effective Emergency Plan throughout the decommissioning process.
  • Exelon does not have any plans for land use or development of the Oyster Creek site at this time.