ML12159A352

From kanterella
Jump to navigation Jump to search
June 6 2012 Public Meeting - NRC Slides
ML12159A352
Person / Time
Site: Oyster Creek
Issue date: 06/06/2012
From: Hunegs G
NRC/RGN-I/DRP/PB6
To:
HUNEGS, GK
Shared Package
ML12137A544 List:
References
Download: ML12159A352 (16)


Text

Oyster Creek Public Meeting June 6 6, 2012 Nuclear Regulatory Commission - Region I

Meeting Agenda

Introductions

Oyster Creek 2011 Performance Results Presentation from EPA Presentation from NRC Questions & Answers

NRC Annual Assessment Summary of Oyster Creek Exelon operated the plant safely Oyster Creek was in the Licensee Response Column of NRCs Action Matrix in 2011 The NRC plans to perform baseline inspections in 2012

NRC Inspection Activities at Oyster Creek for 2011 5589 hours0.0647 days <br />1.553 hours <br />0.00924 weeks <br />0.00213 months <br /> of direct inspection Two resident inspectors on site Event response Inspect p over 20 areas of p plant p performance Examples include operator performance, risk management, equipment issues, and fire protection

NRC Inspection Activities at Oyster Creek for 2011 Nine regional inspections Four team inspections Triennial Fire Protection EP Exercise Evaluation Operator Licensing Examinations Security Baseline

Environmental Protection Agency (EPA)

Region 2

Fukushima Lessons Learned July 2011 Near-Term Task Force (NTTF) report issued September/October 2011 NTTF recommendations prioritized into 3 tiers March 2012 The NRC staff issued the Tier 1 orders and requests for information

Orders The NRC staff ordered licensees to:

Develop strategies and procure additional equipment to address beyond-design-basis natural phenomena and multiunit events Include a reliable hardened vent in Mark I and Mark II containments Enhance spent fuel pool instrumentation for beyond design basis accidents

Requests for Information The NRC staff requested information on:

Whether facility configurations, as confirmed by seismic and flooding walkdowns, are in compliance with current facility design bases The adequacy of facility design bases with respect to seismic and flooding hazards Current communications system power supplies and their availability during a prolonged SBO event The required staffing necessary to respond to a multiunit, prolonged SBO event

Rulemaking Activities On March 20, 2011, the NRC issued an advanced notice of proposed rulemaking regarding a potential revision to the Station Blackout rule.

On April 18 18, 2011 2011, the NRC issued an advanced notice of proposed rulemaking regarding the integration of EOPs, SAMGs, and EDMGs.

Next Steps on Tier 1 Orders and Request for Information Develop implementation guidance for the orders and requests for information Review licensee responses to the orders and requests for information Conduct follow up inspections

More Information NRCs public website:

http://www.nrc.gov/japan/japan-info.html Frequently Asked Questions Contact Scott Burnell, Public Affairs Officer, at 301-415-8204 NRC isi accepting ti public bli comments t on any off the th recommendations Please send comments to JLD_Public.Resource@nrc.gov

NRC Social Media Channels Blog: http://public-blog.nrc-gateway.gov/

Flickr: http://www.flickr.com/photos/nrcgov/

Twitter: https://twitter.com/#!/nrcgov YouTube: http://www.youtube.com/user/NRCgov RSS: http://www.nrc.gov/public-involve/listserver.html#rss 13

Contacting the NRC Report an emergency (301) 816-5100 (call collect)

Report a safety concern (800) 695-7403 695 7403 Allegation@nrc.gov General information or questions www.nrc.gov

References http://www.state.nj.us/

http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/buried-pipes-tritium.html

End of Presentation Nuclear Regulatory Commission Region I Toms River, NJ June 6, 2012