Perry Nuclear Power Plant, Unit No. 1 - Request for Additional Information Concerning Relocation of Surveillance Frequencies to Control Licensee Control (TAC No. MF3720)(L-14-106)
ML14232A225
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/09/2014
From: Brown E A
Plant Licensing Branch III
To: Harkness E J
FirstEnergy Nuclear Operating Co
Eva Brown, NRR/DORL 415-2315
References
L-14-106, TAC MF3720
Download: ML14232A225 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Ernest J. Harkness Site Vice President FirstEnergy Nuclear Operating Company Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 September 9, 2014 SUBJECT: PERRY NUCLEAR POWER PLANT, UNIT NO. 1 -REQUEST FOR ADDITIONAL INFORMATION CONCERNING RELOCATION OF SURVEILLANCE FREQUENCIES TO LICENSEE CONTROL (TAC NO. MF3720)(L-14-106) Dear Mr. Harkness: By application to the U.S. Nuclear Regulatory Commission (NRC) dated March 25, 2014 (Agencywide Documents Access and Management System Accession No. ML 14084A 165), FirstEnergy Nuclear Operating Company (FENOC, the licensee) submitted a license amendment request for the Perry Nuclear Power Plant. The proposed amendment would relocate specific technical specification surveillance requirement frequencies to a licensee controlled program. The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with Mr. Phil Lashley of your staff on August 18, 2014, it was agreed that FENOC would provide a response within 30 days from the date of this letter. The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources.

E. Harkness -2 -Should circumstances result in the need to revise the requested response date, please contact me at (301) 415-2315. Docket No. 50-440 Enclosure: Request for Additional Information cc w/encl: Distribution via Listserv Sincerely, IRA/ Eva A. Brown, Senior Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION RELOCATION OF CERTAIN TECHNICAL SPECIFICATION SURVEILLANCE REQUIREMENT FIRSTENERGY NUCLEAR OPERATING COMPANY PERRY NUCLEAR POWER PLANT UNIT NO. 1 DOCKET NO. 50-440 1. In Regulatory Position 4.2 of Regulatory Guide 1.200, Revision 2 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML090410014), the U.S. Nuclear Regulatory Commission staff stated that it expects licensees to submit "a discussion of the resolution of the peer review (or self-assessment, for peer reviews performed using the criteria in Nuclear Energy Institute 00-02) findings and observations that are applicable to the parts of the probabilistic risk assessment (PRA) required for the application." In Enclosure B to the submittal dated March 25, 2014 ADAMS Accession No. ML 14084A 165), the licensee provided a summary of the results for the following:

  • 1997 probabilistic safety assessment peer review certification;
  • 2008 gap analysis self-assessment to American Society of Mechanical Engineers/American Nuclear Society (ASME/ANS) for PRA Standard RA-Sb-2005, "Addenda to ASME RA-S-2002 Standard for Probabilistic Risk Assessment for Nuclear Power Plant Applications";
  • 2012 focused-scope peer review for the internal flooding portion of the PRA model. Provide a list of the Facts and Observations (F&Os) from the peer reviews and self-assessment listed above, relevant to this submittal, and explain how the F&Os were dispositioned for this application. Enclosure E. Harkness -2 -Should circumstances result in the need to revise the requested response date, please contact me at (301) 415-2315. Docket No. 50-440 Enclosure: Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION: Sincerely, IRA/ Eva A Brown, Senior Project Manager Plant Licensing 111-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation PUBLIC LPLIII-2 Reading File RidsAcrsAcnw_MaiiCTR Resource RidsNrrDorllplll-2 Resource RidsRg3MaiiCenter Resource RidsNrrDeEicb Resource RidsNrrDeEeeb Resource RidsNrrDraApla Resource RidsNrrDorl Resource RidsNrrPMPerry Resource TMartinez RidsNrrLASRohrer Resource RGrover DGennardo GThomas RidsNrrDssStsb GSingh ADAMS Accession No. ML 14232A225 OFFICE LPL3-2/PM LPL3-2/LA NAME EBrown SRorher DATE 9/8/14 9/9 /14 *via memo APLA/BC* LPLIII-2/BC HHamzehee TTate 8/19/14 9/9 /14 OFFICIAL RECORD COPY