05000335/LER-1982-025, Forwards LER 82-025/03L-0
ML20055B796 | |
Person / Time | |
---|---|
Site: | Saint Lucie |
Issue date: | 07/16/1982 |
From: | Williams J FLORIDA POWER & LIGHT CO. |
To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
Shared Package | |
ML20055B797 | List: |
References | |
PNS-LI-82-292, NUDOCS 8207230307 | |
Download: ML20055B796 (1) | |
Similar Documents at Saint Lucie | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARL-99-229, Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C1999-10-21021 October 1999
[Table view]Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML17241A4981999-10-21021 October 1999 Informs That Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Submitted in 990811 Application Will Be Withheld from Public Disclosure L-99-222, Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points1999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points ML17241A4961999-10-13013 October 1999 Informs That on 990930,NRC Completed mid-cycle PPR of Plant, Units 1 & 2 & Did Not Identify Any New Areas That Warranted More than Core Insp Program.Previously Planned Regional Initiative Insp Re Fire Protection Issues Will Be Conducted ML20217F6171999-10-0808 October 1999 Forwards Insp Repts 50-335/99-11 & 50-389/99-11 on 990827 & 990907-09.No Violations Identified.Matl Encl Contained Safeguards Info as Defined by 10CFR73.21 & Disclosed to Unauthorized Individuals Prohibited by Section 147 of AEA ML17241A4861999-10-0606 October 1999 Discusses GL 97-06, Degradation of SG Internals, Issued by USNRC on 971231 & FP&L Responses for St Lucie & 980623.Staff Reviewed Responses & Found No New Concerns with Condition of SG Internals IR 05000335/19980141999-10-0505 October 1999 Discusses Notice of Violation & Exercise of Discretion Re Insp Rept 50-335/98-14 & 50-389/98-14 Concerning FP&L Analysis Methodology Associated with fire-induced Circuit Failure.Review Completed & Determination Provided ML17241A4751999-10-0404 October 1999 Forwards SE Authorizing Licensee 990405 & 0722 Relief Request 25 from ASME Code Section Xi,Requirements for Certain ISI of Reactor Pressure vessel-to-nozzle Welds at Plant,Unit 2,contained in Second 10-year ISI Program L-99-218, Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a1999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML20212M1601999-09-28028 September 1999 Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl L-99-215, Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant1999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant L-99-212, Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 19991999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4611999-09-23023 September 1999 Forwards SE Accepting Request for Relief from Certain Provisions of ASME Boiler & Pressure Vessel Code,Section XI, Contained in Second 10-year Interval Inservice Insp Program for Plant,Unit 2 ML17241A4641999-09-23023 September 1999 Informs That NRC Has Completed Review of Proposed Changes to Radiological Emergency Plan for Plant,Units 1 & 2.Safety Evaluation Accepting Changes Encl L-99-204, Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6)1999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4821999-09-20020 September 1999 Forwards Insp Repts 50-335/99-05 & 50-389/99-05 on 990711- 0821.Three Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy L-99-199, Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams1999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams L-99-195, Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program1999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML17355A4151999-09-0101 September 1999 Forwards Summary of 990812-13 Training Managers Conference in Atlanta,Georgia Re Recent Changes to Operator Licensing Program.List of Conference Attendees,Copy of Slide Presentations & List of Participant Questions Encl L-99-188, Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval1999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval L-99-192, Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 9910061999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 L-99-189, Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached1999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17355A4051999-08-20020 August 1999 Confirms 990813 Telcon Between M Dryden & at Boland Re Engineering Meeting to Be Conducted on 990908 in Atlanta,Ga to Discuss Engineering Issues at St Lucie & Turkey Point Facilities ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) L-99-181, Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d)1999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure ML17355A3971999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006 at St Lucie & Turkey Point Nuclear Plants.Sample Registration Ltr Encl L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) L-99-168, Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified1999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified L-99-169, Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates1999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates L-99-159, Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 21999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4191999-07-16016 July 1999 Forwards SE Accepting Response to GL-95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Unit 2 L-99-164, Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants1999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17241A4161999-07-15015 July 1999 Forwards Safety Evaluation Re Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power- Operated Gate Valves ML17241A4121999-07-14014 July 1999 Responds to Insp Rept Issued 990611.Due to Error,No Item Numbers Were Assigned to non-cited Violations Described in Rept.Forwards Corrected Pp to Be Replaced in Original L-99-155, Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager1999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML17241A4081999-07-0707 July 1999 Responds to 990302 & 0415 Ltrs Requesting Review of NRC Denial of FPL Appeal of 10CFR170 Fees Assessed for Costs of Resident Inspector Training Invoices RS0062-99 & RS0182-99 for Unit 1 & RS085-99 & RS0205-99 for Unit 2 ML20209F1541999-07-0606 July 1999 Informs That NRC in Process of Conducting Operational Safeguards Response Evaluations at Nuclear Power Reactors. Plant Chosen for Such Review Scheduled for Wk of 990823-26 L-99-151, Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 19981999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 L-99-153, Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 9906041999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 L-99-156, Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in1999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr L-99-143, Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl1999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML17241A3961999-06-25025 June 1999 Discusses Closure of TACs MA0574 & MA0575 Re Licensee Response to RAI in GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity, for Plant,Units 1 & 2.NRC Revised Info in Rvid as Result of NRC Review of Licensee Responses to GL 92-01 ML17241A3901999-06-25025 June 1999 Forwards Insp Repts 50-335/99-03 & 50-389/99-03 on 990418-0529.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement Policy 1999-09-28 Category:INCOMING CORRESPONDENCE MONTHYEARL-99-229, Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C1999-10-21021 October 1999
[Table view]Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C L-99-222, Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points1999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points L-99-218, Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a1999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a L-99-215, Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant1999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant L-99-212, Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 19991999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) L-99-204, Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6)1999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) L-99-199, Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams1999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams L-99-195, Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program1999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program L-99-188, Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval1999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval L-99-192, Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 9910061999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 L-99-189, Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached1999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) L-99-181, Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d)1999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) L-99-168, Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified1999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 L-99-159, Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 21999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 L-99-169, Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates1999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates L-99-164, Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants1999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants L-99-155, Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager1999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager L-99-156, Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in1999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr L-99-151, Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 19981999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 L-99-153, Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 9906041999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 L-99-143, Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl1999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl L-99-139, Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16)1999-06-17017 June 1999 Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16) L-99-141, Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-1391999-06-14014 June 1999 Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-139 L-99-129, Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3)1999-06-0909 June 1999 Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3) L-99-128, Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-9812091999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 L-99-130, Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 19981999-06-0707 June 1999 Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 1998 ML17241A3561999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 ML20195F3941999-05-27027 May 1999 FOIA Request That Memo from J Calvo to Fl Lebdon Re TIA - St Lucie,Unit 1 Environ Qualification of Woodward Governor Controls Be Placed in PDR L-99-118, Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage1999-05-24024 May 1999 Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage L-99-112, Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F1999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F ML17241A3391999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F L-99-110, Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI1999-05-20020 May 1999 Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI ML17241A3301999-05-17017 May 1999 Forwards LER 99-004-00 Re as Found Cycle 10 Psv Setpoints Outside TS Limits,Which Occurred on 990415.Root Cause Determination Not Yet Complete.Suppl to Include Root Cause & Corrective Actions Will Be Submitted ML17309A9821999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl L-99-104, Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl1999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl L-99-107, Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated1999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17229B1071999-04-28028 April 1999 Forwards 1998 Annual Environ Operating Rept for St Lucie Unit 2. Rept Includes Discussions of 5-inch Barrier Net Maint & Taprogge Condenser Tube Cleaning Sys Ball Loss,As Agreed at First Biennial Sea Turtle Meeting Held on 980120 L-99-103, Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices1999-04-22022 April 1999 Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices L-99-097, Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6)1999-04-21021 April 1999 Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6) L-99-082, Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in .Both Invoices Are for Fees Re Inspector GG Warnick1999-04-15015 April 1999 Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in .Both Invoices Are for Fees Re Inspector GG Warnick ML17229B0951999-04-0808 April 1999 Requests Approval of Encl Revised Relief Request 6,in Response to 990322 Telcon with NRC & 10CFR55.55a(a)(3). Request States That Visual VT-3 Exams Will Be Conducted IAW IWA-2213 & Repairs Will Be IAW Util ASME Section IX Program 1999-09-25 Category:UTILITY TO NRC MONTHYEARL-90-332, Forwards Evaluation of Potential Safety Impact of Failed Control Element Assemblies on Limiting Transients for Facility1990-09-13013 September 1990
[Table view]Forwards Evaluation of Potential Safety Impact of Failed Control Element Assemblies on Limiting Transients for Facility ML17223A9341990-09-10010 September 1990 Forwards Addl Info Re Generic Implications & Resolution of Control Element Assembly (CEA) Failure at Facility,Per NRC Request.Description of Testing Program for Old Style CEAs in Unit 1 Core Encl L-90-323, Forwards Addl Info Re Generic Implications & Resolution of Control Element Assembly (CEA) Failure at Facility,Per NRC Request.Description of Testing Program for Old Style CEAs in Unit 1 Core Encl1990-09-10010 September 1990 Forwards Addl Info Re Generic Implications & Resolution of Control Element Assembly (CEA) Failure at Facility,Per NRC Request.Description of Testing Program for Old Style CEAs in Unit 1 Core Encl L-90-315, Advises That Util Has Completed Evaluation of NUREG-0737, Item II.D.1,SER Item 81990-08-30030 August 1990 Advises That Util Has Completed Evaluation of NUREG-0737, Item II.D.1,SER Item 8 L-90-311, Forwards Forms NIS-1 & NIS-2, Owners Rept for Inservice Insps as Required by Provisions of ASME Code Rules, Per1990-08-28028 August 1990 Forwards Forms NIS-1 & NIS-2, Owners Rept for Inservice Insps as Required by Provisions of ASME Code Rules, Per L-90-304, Forwards Corrected Monthly Operating Repts for Jul 1990 for St Lucie Units 1 & 2 & Summary of Operating Experience1990-08-20020 August 1990 Forwards Corrected Monthly Operating Repts for Jul 1990 for St Lucie Units 1 & 2 & Summary of Operating Experience L-90-286, Forwards fitness-for-duty Program Performance Data for Jan-June 19901990-08-17017 August 1990 Forwards fitness-for-duty Program Performance Data for Jan-June 1990 L-90-301, Discusses Generic Implications & Resolution of Control Element Assemblies Failure at Plant1990-08-16016 August 1990 Discusses Generic Implications & Resolution of Control Element Assemblies Failure at Plant ML17223A8751990-08-0909 August 1990 Responds to Violations Noted in Insp Rept 50-335/90-14. Corrective Actions:Rcs Flow Determination by Calorimetric Procedure Repeated W/Supervisor of Individual Observing & Individual Counseled by Supervisor L-90-291, Responds to Violations Noted in Insp Rept 50-335/90-14. Corrective Actions:Rcs Flow Determination by Calorimetric Procedure Repeated W/Supervisor of Individual Observing & Individual Counseled by Supervisor1990-08-0909 August 1990 Responds to Violations Noted in Insp Rept 50-335/90-14. Corrective Actions:Rcs Flow Determination by Calorimetric Procedure Repeated W/Supervisor of Individual Observing & Individual Counseled by Supervisor L-90-232, Forwards Rept Detailing Investigative Analysis of Unsatisfactory Blind Specimen Results,Identification of Causes & Corrective Actions Taken by Lab to Prevent Recurrence,Per Unsatisfactory Performance Testing1990-07-27027 July 1990 Forwards Rept Detailing Investigative Analysis of Unsatisfactory Blind Specimen Results,Identification of Causes & Corrective Actions Taken by Lab to Prevent Recurrence,Per Unsatisfactory Performance Testing ML17348A4701990-07-27027 July 1990 Forwards Rept Detailing Investigative Analysis of Unsatisfactory Blind Specimen Results,Identification of Causes & Corrective Actions Taken by Lab to Prevent Recurrence,Per Unsatisfactory Performance Testing L-90-276, Advises That NIS-1 & NIS-2 Forms,As Part of Inservice Insp Rept,Will Be Submitted by 9008311990-07-25025 July 1990 Advises That NIS-1 & NIS-2 Forms,As Part of Inservice Insp Rept,Will Be Submitted by 900831 L-90-245, Forwards Decommissioning Financial Assurance Repts for Plants,Per 10CFR50.33(k) & 50.75(b)1990-07-25025 July 1990 Forwards Decommissioning Financial Assurance Repts for Plants,Per 10CFR50.33(k) & 50.75(b) L-90-281, Submits Addl Info Re Implementation of Programmed Enhancements Per Generic Ltr 88-17, Loss of Dhr. All Mods for Unit 1 Completed & Operational.Mods for Unit 2 Schedule for Upcoming Refueling Outage1990-07-25025 July 1990 Submits Addl Info Re Implementation of Programmed Enhancements Per Generic Ltr 88-17, Loss of Dhr. All Mods for Unit 1 Completed & Operational.Mods for Unit 2 Schedule for Upcoming Refueling Outage L-90-271, Responds to NRC Ltr Re Violations Noted in Insp Repts 50-335/90-09 & 50-389/90-09.Corrective Actions:Procedural Expectation Re Hanging & Removal of Deficiency Tags Will Be Reemphasized to Personnel Generating Work Orders1990-07-20020 July 1990 Responds to NRC Ltr Re Violations Noted in Insp Repts 50-335/90-09 & 50-389/90-09.Corrective Actions:Procedural Expectation Re Hanging & Removal of Deficiency Tags Will Be Reemphasized to Personnel Generating Work Orders L-90-273, Forwards Implementation Status of 10CFR50.62 Mod at Facility Re Requirements for Reduction of Risk from ATWS Events for Light Water Cooled Nuclear Power Plants1990-07-19019 July 1990 Forwards Implementation Status of 10CFR50.62 Mod at Facility Re Requirements for Reduction of Risk from ATWS Events for Light Water Cooled Nuclear Power Plants ML17223A8581990-07-19019 July 1990 Forwards Implementation Status of 10CFR50.62 Mod at Facility Re Requirements for Reduction of Risk from ATWS Events for Light Water Cooled Nuclear Power Plants L-90-258, Responds to NRC Bulletin 90-001, Loss of Fill Oil in Transmitters Mfg by Rosemount. No Rosemount Transmitters Models 1153 Series B,1153 Series D & 1154 Mfg Prior to 890711 Supplied by Different Vendor1990-07-18018 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill Oil in Transmitters Mfg by Rosemount. No Rosemount Transmitters Models 1153 Series B,1153 Series D & 1154 Mfg Prior to 890711 Supplied by Different Vendor ML17223A8491990-07-18018 July 1990 Responds to NRC Bulletin 90-001, Loss of Fill Oil in Transmitters Mfg by Rosemount. No Rosemount Transmitters Models 1153 Series B,1153 Series D & 1154 Mfg Prior to 890711 Supplied by Different Vendor L-90-272, Forwards Addl Info Requested Re Generic Implications & Resolution of Control Element Assembly Failure at Plant.Encl Confirms Util Intent to Follow C-E Regulatory Response Group Action Program1990-07-17017 July 1990 Forwards Addl Info Requested Re Generic Implications & Resolution of Control Element Assembly Failure at Plant.Encl Confirms Util Intent to Follow C-E Regulatory Response Group Action Program L-90-250, Responds to Violations Noted in Insp Repts 50-335/90-13 & 50-389/90-13.Corrective Actions:Maint Personnel Counseled & Aware of Importance of Verifying Design Configuration Requirements1990-07-0909 July 1990 Responds to Violations Noted in Insp Repts 50-335/90-13 & 50-389/90-13.Corrective Actions:Maint Personnel Counseled & Aware of Importance of Verifying Design Configuration Requirements ML17223A8421990-07-0909 July 1990 Responds to Violations Noted in Insp Repts 50-335/90-13 & 50-389/90-13.Corrective Actions:Maint Personnel Counseled & Aware of Importance of Verifying Design Configuration Requirements ML17348A3881990-07-0505 July 1990 Requests Audit of NRC Records to Independently Verify Reasonableness of Charges Assessed Against Util,Per 10CFR170 Svcs L-90-249, Requests Audit of NRC Records to Independently Verify Reasonableness of Charges Assessed Against Util,Per 10CFR170 Svcs1990-07-0505 July 1990 Requests Audit of NRC Records to Independently Verify Reasonableness of Charges Assessed Against Util,Per 10CFR170 Svcs L-90-246, Forwards Results of Beach Survey Procedure & Reduction of Field Survey Data,Per Tech Spec 4.7.6.1.1.Unit 1 Updated Fsar,Section 2.4.2.2,concluded That Dune Condition Acceptable Per Tech Spec 5.1.31990-07-0303 July 1990 Forwards Results of Beach Survey Procedure & Reduction of Field Survey Data,Per Tech Spec 4.7.6.1.1.Unit 1 Updated Fsar,Section 2.4.2.2,concluded That Dune Condition Acceptable Per Tech Spec 5.1.3 ML17223A8391990-07-0303 July 1990 Forwards Results of Beach Survey Procedure & Reduction of Field Survey Data,Per Tech Spec 4.7.6.1.1.Unit 1 Updated Fsar,Section 2.4.2.2,concluded That Dune Condition Acceptable Per Tech Spec 5.1.3 L-90-239, Forwards Rev 6 to Guard Training & Qualification Plan.Rev Withheld (Ref 10CFR73.21)1990-07-0202 July 1990 Forwards Rev 6 to Guard Training & Qualification Plan.Rev Withheld (Ref 10CFR73.21) ML17223A8371990-06-27027 June 1990 Provides Details of Implementation Plan Re Recommendations & Schedular Requirements in Generic Ltr 89-10,per 891228 Ltr.Design Basis Review of safety-related motor-operated Valves & Determination of Switch Settings in Progress ML17308A4981990-06-27027 June 1990 Responds to Generic Ltr 90-04 Re Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions L-90-202, Provides Details of Implementation Plan Re Recommendations & Schedular Requirements in Generic Ltr 89-10,per .Design Basis Review of safety-related motor-operated Valves & Determination of Switch Settings in Progress1990-06-27027 June 1990 Provides Details of Implementation Plan Re Recommendations & Schedular Requirements in Generic Ltr 89-10,per .Design Basis Review of safety-related motor-operated Valves & Determination of Switch Settings in Progress L-90-210, Responds to Generic Ltr 90-04 Re Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions1990-06-27027 June 1990 Responds to Generic Ltr 90-04 Re Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions L-90-219, Forwards Corrected Proposed Tech Spec Figure 3.4-2 Per 900207 Application for Amend to License NPF-16,incorporating Revised Pressure/Temp Limits & Results of Revised Low Temp Overpressure Protection Analysis Into Tech Specs1990-06-19019 June 1990 Forwards Corrected Proposed Tech Spec Figure 3.4-2 Per 900207 Application for Amend to License NPF-16,incorporating Revised Pressure/Temp Limits & Results of Revised Low Temp Overpressure Protection Analysis Into Tech Specs L-90-213, Forwards Ma Smith to WR Cunningham of EPA Requesting Mod to Plant NPDES Permit to Permit Cleaning of Facility & to Establish Discharge Limits for Chemical Cleaning Wastes1990-06-18018 June 1990 Forwards Ma Smith to WR Cunningham of EPA Requesting Mod to Plant NPDES Permit to Permit Cleaning of Facility & to Establish Discharge Limits for Chemical Cleaning Wastes ML17223A8271990-06-18018 June 1990 Forwards Ma Smith 900601 Ltr to WR Cunningham of EPA Requesting Mod to Plant NPDES Permit to Permit Cleaning of Facility & to Establish Discharge Limits for Chemical Cleaning Wastes L-90-201, Forwards Revised Combined Semiannual Radioactive Effluent Release Rept for Jan-June 19881990-06-18018 June 1990 Forwards Revised Combined Semiannual Radioactive Effluent Release Rept for Jan-June 1988 L-90-204, Forwards Rev 16 to Topical QA Rept1990-06-12012 June 1990 Forwards Rev 16 to Topical QA Rept ML17348A2981990-06-12012 June 1990 Forwards Rev 16 to Topical QA Rept. L-90-189, Advises That Air Operated safety-related Components Will Perform All Design Basis Events,Per .All Actions Required by Generic Ltr 88-14 Complete for Plant1990-05-31031 May 1990 Advises That Air Operated safety-related Components Will Perform All Design Basis Events,Per .All Actions Required by Generic Ltr 88-14 Complete for Plant L-90-199, Submits Rept Detailing Investigative Analysis of Unsatisfactory Blind Specimen Results,Identification of Causes & Corrective Actions Taken by Lab to Prevent Recurrence,Per 10CFR26,App A.2.8(e)(4)1990-05-29029 May 1990 Submits Rept Detailing Investigative Analysis of Unsatisfactory Blind Specimen Results,Identification of Causes & Corrective Actions Taken by Lab to Prevent Recurrence,Per 10CFR26,App A.2.8(e)(4) L-90-190, Forwards Info Re Status of 10CFR50.62 Mods to Meet ATWS Requirements as of 900515.Plant Change/Mod Package Necessary for Installing ATWS Will Be Issued by 900630.Hardware Procurement for Diverse Scram Sys Approx 90% Complete1990-05-22022 May 1990 Forwards Info Re Status of 10CFR50.62 Mods to Meet ATWS Requirements as of 900515.Plant Change/Mod Package Necessary for Installing ATWS Will Be Issued by 900630.Hardware Procurement for Diverse Scram Sys Approx 90% Complete L-90-161, Forwards Final Response to NRC Bulletin 88-010, Nonconforming Molded-Case Circuit Breakers. One Untraceable Circuit Breaker Installed in Unit 2 Qualified SPDS & Replaced W/Traceable Breaker1990-05-0808 May 1990 Forwards Final Response to NRC Bulletin 88-010, Nonconforming Molded-Case Circuit Breakers. One Untraceable Circuit Breaker Installed in Unit 2 Qualified SPDS & Replaced W/Traceable Breaker L-90-148, Forwards St Lucie Unit 2 Annual Environ Operating Rept, Vol 1 19891990-04-21021 April 1990 Forwards St Lucie Unit 2 Annual Environ Operating Rept, Vol 1 1989 L-90-128, Forwards Rev 26 to Physical Security Plan.Rev Withheld (Ref 10CFR2.790(a)(3))1990-04-17017 April 1990 Forwards Rev 26 to Physical Security Plan.Rev Withheld (Ref 10CFR2.790(a)(3)) L-90-138, Responds to Violations Noted in Insp Repts 50-335/90-02 & 50-389/90-02.Corrective Actions:Nuclear Plant Supervisor Required to Remain in Control Room During Significant Changes in Power Operation & Preventive Maint Upgraded1990-04-13013 April 1990 Responds to Violations Noted in Insp Repts 50-335/90-02 & 50-389/90-02.Corrective Actions:Nuclear Plant Supervisor Required to Remain in Control Room During Significant Changes in Power Operation & Preventive Maint Upgraded L-90-131, Responds to NRC Bulletin 89-001, Failure of Westinghouse Steam Generator Tube Mechanical Plugs. Removal & Replacement of Cold Leg Side Plugs of Heat Number 3513 for Unit 1 Completed During Refueling Outage1990-04-0505 April 1990 Responds to NRC Bulletin 89-001, Failure of Westinghouse Steam Generator Tube Mechanical Plugs. Removal & Replacement of Cold Leg Side Plugs of Heat Number 3513 for Unit 1 Completed During Refueling Outage L-90-121, Forwards St Lucie Unit 2 Underwater Intrusion Detection Sys Safenet Barrier Conceptual Design, for Expeditious Review & Approval to Permit Sys Installation in Time Frame Discussed in 900228 Meeting1990-04-0202 April 1990 Forwards St Lucie Unit 2 Underwater Intrusion Detection Sys Safenet Barrier Conceptual Design, for Expeditious Review & Approval to Permit Sys Installation in Time Frame Discussed in 900228 Meeting ML17308A4911990-04-0202 April 1990 Forwards Description & Summary of Safety Evaluations of Plant Changes/Mods Reportable Per 10CFR50.59.Repair &/Or Replacement of Protective Coatings on Surfaces Inside Bldg Pose No Unreviewed Safety Question L-90-110, Forwards Description & Summary of Safety Evaluations of Plant Changes/Mods Reportable Per 10CFR50.59.Repair &/Or Replacement of Protective Coatings on Surfaces Inside Bldg Pose No Unreviewed Safety Question1990-04-0202 April 1990 Forwards Description & Summary of Safety Evaluations of Plant Changes/Mods Reportable Per 10CFR50.59.Repair &/Or Replacement of Protective Coatings on Surfaces Inside Bldg Pose No Unreviewed Safety Question L-90-120, Forwards Status of 10CFR50.62, Requirements for Reduction of Risk from ATWS Mods at Plant as of 900315.Diverse Scram Sys Module Prototype Fabrication in Progress1990-03-30030 March 1990 Forwards Status of 10CFR50.62, Requirements for Reduction of Risk from ATWS Mods at Plant as of 900315.Diverse Scram Sys Module Prototype Fabrication in Progress 1990-09-13 |
Event date: | |
---|---|
Report date: | |
3351982025R00 - NRC Website | |
text
)
o P C. 80x 529100 MI AMI, F L 33152 o
.Jh,ffff lq gy FLORIDA POWER & LIGHT COMPANY
~: 0 July 16, 1982 PNS-LI-82-292 Mr. James P. O'Reilly Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
REPORTABLE OCCURRENCE 335-82-25 l
ST. LUCIE UNIT 1 DATE OF OCCURRENCE: JUNE 16, 1982 TECHNICAL SPECIFICATION 3.3.3.8.a PRESSURIZER SAFETY VALVE ACOUSTIC FLOW POSITION INDICATOR The attached Licensee Event Report is being submitted in accordance with Technical Specification 6.9 to provide 30 day notification of the subject occurence.
Very truly yours,
(
s.W%.fi%-
iams, Jr
{0 v
Vice President 6
Nuclear Energy l
PLP/pyc Attachment cc: Director, Office of Inspection and Enforcement (30)
Harold F.
Reis, Esquire File 933.1 SL
'f;
~
up.
WI QW... g.J 6
/
)
8207230307 820716 PDR ADOCK 05000335 PDR S
PEOPLE.. SERVING PEOPLE