|
---|
Category:Preliminary Safety Analysis Report (PSAR)
MONTHYEARML24144A0922024-05-23023 May 2024 Enclosure 1: Hermes 2 Preliminary Safety Analysis Report ML24144A0942024-05-23023 May 2024 Enclosure 3: KP-TR-022-NP Hermes 2 Postulated Event Methodology Revision 1 ML24138A2132024-05-16016 May 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapters 3, 5 and 13 (non-proprietary) ML24136A2552024-05-15015 May 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapter 9 ML24073A3192024-03-13013 March 2024 Enclosure 1: Changes to Hermes 2 PSAR Chapter 13 ML24072A2992024-03-12012 March 2024 Enclosure 1 - Changes to Hermes 2 PSAR Chapter 7 ML24039A1912024-02-0808 February 2024 Kairos Power LLC, Changes to Hermes 2 PSAR Chapter 2 ML24031A1392024-01-30030 January 2024 Kairos Power LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 3 ML24026A3012024-01-26026 January 2024 Kairos Power, LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 7 ML24025C6872024-01-24024 January 2024 Kairos Power LLC, Changes to PSAR Chapter 3 and 9 ML24011A2922024-01-11011 January 2024 Kairos Power LLC, Preliminary Safety Analysis Report, Chapter 9 ML24009A2492024-01-0909 January 2024 Kairos Power LLC, Changes to Hermes 2 Preliminary Safety Analysis Report (PSAR) Chapter 9 ML24003A7672024-01-0303 January 2024 Kairos Power LLC, Changes to Hermes 2 Construction Permit Application (PSAR) Chapters 4, 5, 7, and 13 ML23356A0802023-12-22022 December 2023 Enclosure 1: Kairos Power, LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 13 ML23355A1632023-12-21021 December 2023 Enclosure 1: Changes to Hermes 2 PSAR Chapter 4 ML23355A1942023-12-21021 December 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 3 and Chapter 5 ML23349A1492023-12-15015 December 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 2 ML23151A7452023-05-31031 May 2023 Enclosure 1 - Preliminary Safety Analysis Report ML23115A3952023-04-25025 April 2023 Kairos Power, LLC - Enclosure 1, Changes to Hermes PSAR Chapters 2, 3, 4, 7, 8, 9, 13, and 14 ML23034A2142023-02-0303 February 2023 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (Psar), Revision 1, Chapter 2 ML22353A6252022-12-19019 December 2022 Kairos Power LLC, Transmittal of Changes to Preliminary Safety Analysis Report Chapter 6 and Response to NRC Question on Dhrs Testing ML22286A2432022-10-13013 October 2022 Kairos Power, LLC - Preliminary Safety Analysis Report ML22285A2292022-10-12012 October 2022 Enclosure 1: Changes to PSAR Chapter 4 ML22284A1532022-10-11011 October 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapter 13 ML22284A1562022-10-11011 October 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3, 4, 6, and 14 ML22279B0642022-10-0606 October 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3 and 7 ML22272A5952022-09-29029 September 2022 Enclosure 1: HER-PSAR-001, Preliminary Safety Analysis Report, Rev. 1 ML22263A0352022-09-19019 September 2022 Kairos Power, LLC - Transmittal of Changes to Construction Permit Application - Exemptions Enclosure, PSAR Chapter 1, PSAR Chapter 3, and PSAR Chapter 14S ML22263A0342022-09-19019 September 2022 Enclosure 2 - Changes to PSAR Chapter 15 (Non-Proprietary) ML22259A1412022-09-16016 September 2022 Kairos Power, LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapters 3 and 4 ML22256A3012022-09-13013 September 2022 Enclosure 1: Changes to Hermes PSAR Chapters 3, 4, and 6 ML22250A6802022-09-0707 September 2022 Enclosure 1: Changes to PSAR Chapters 4 and 5 ML22242A1682022-08-30030 August 2022 Kairos Power LLC, Changes to Construction Permit Application - PSAR Chapters 3, 4, 8, and 13 ML22237A3262022-08-25025 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapters 3, 4, 5, 9 and 14 ML22236A5952022-08-24024 August 2022 Kairos Power, LLC, Preliminary Safety Analysis Report, Chapter 6 ML22231B0302022-08-19019 August 2022 Enclosure 1: Change to Hermes PSAR Chapter 14 ML22230D0492022-08-18018 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report (PSAR) Chapter 4.2 ML22252A2592022-08-18018 August 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Table 4.2-5 ML22230D0532022-08-18018 August 2022 Enclosure 1 - Changes to PSAR Table 4.2-5 ML22224A2022022-08-12012 August 2022 Enclosure 2: Changes to Preliminary Safety Analysis Report Chapter 13 ML22210A3192022-07-29029 July 2022 Enclosure 1: Changes to PSAR Chapter 4 and Chapter 6 ML22209A1392022-07-27027 July 2022 Enclosure 1: Change to Hermes PSAR Chapter 5 ML22181B0562022-06-30030 June 2022 Enclosure 1: Changes to PSAR Chapter 7 ML22181B1592022-06-30030 June 2022 Enclosure 1 - Changes to PSAR Chapters 3, 4, and 6 (Non-Proprietary) ML22181B1762022-06-30030 June 2022 Enclosure 1 - Changes to PSAR Chapter 4.2 ML22181B1132022-06-27027 June 2022 Enclosure 1: Changes to PSAR Chapter 3 ML22178A2382022-06-27027 June 2022 Enclosure 1: Changes to PSAR Chapter 9 ML22171A0172022-06-20020 June 2022 Kairos Power, LLC Preliminary Safety Analysis Report ML22167A1922022-06-16016 June 2022 Kairos Power LLC, Changes to Construction Permit Application - PSAR Chapter 14 ML22161B0142022-06-10010 June 2022 Kairos Power LLC, Changes to Preliminary Safety Analysis Report Chapter 7 2024-05-23
[Table view] |
Text
KP-NRC-2206-015
Enclosure 1 Changes to PSAR Chapter 4.2
(Non-Proprietary)
Preliminary Safety Analysis Report Reactor Description
core. A fuel -free carbon matrix shell is located on the surface of the fuel region to protect the fuel primarily from mechanica l damage.
The fuel annulus is composed of a carbon matrix embedded with TRISO fuel particles with a packing fraction of approximately 37%. The fuel particles are located near the pebble surface which reduces particle temperature s relative to non -annular de signs. The TRISO particles are fabricated in accordance with a fuel specification that is similar to DOE s AGR program fuel particles matching critical parameters related to fuel performance. The kernels are composed of UCO, a mixture of UO 2, UC, and UC 2 phases, which differs from the traditional TRISO fuel particle kernels containing only UO 2. The addition of carbon to the kernel mitigates the generation of CO gas thus reducing the risk of kernel migration, over -
pressurization of the particle with CO gas, and CO gas reactions with the SiC layer. The fuel pebbles are safety -related.
T he reactor also contains mo derator pebbles. These pebbles have the same diameter as the fuel pebbles, contain no uranium, and are made of graphite matrix material. The moderator pebbles have the same buoyancy characteristics as the fuel pebbles. As described in Section 4.5, these pebbles provide neutron moderation. The moderator pebbles are non -safety related.
Typical f F uel properties are provided in Table 4.2 -1 (particle) and Table 4.2 -2 (pebble). The primary safety -related functions performed b y each of the fuel components are described in Table 4.2 -3.
4.2.1.2 Fuel Qualification The qualification of the initial reactor fuel is based on U.S. and international historical experience with TRISO fuel elements and the advancement in fuel technology through the DOE AGR program. This historical experience provides confidence that the reactor will operate with large thermal margins and therefore the integrity of the fuel is not expected to be challen ged. The DOE initiated the AGR project in the early 2000s to design and develop a High Temperature Gas Reactor to support the U.S. domestic electricity and process heat market. A critical part of this effort was evaluating past issues with U.S.
manufacture d particle fuel in comparison to the successful German experience. The result was a TRISO fuel particle design that was fabricated at laboratory and engineering scale s and irradiated in a series of tests in the Advanced Test Reactor at the Idaho National L aboratory (INL). These irradiation tests serve as a foundation for the qualification of a TRISO fuel particle design for application in the KP -FHR test reactor.
The fuel qualification program is described in the Fuel Qualification Methodology for the Kai ros Power Fluoride Salt -Cooled High Temperature Reactor (KP -FHR) topical r eport (Reference 2 ). The main elements of this qualification program are:
- Fuel Specification, Manufacturing, and Quality Control through Inspection
- Fuel Element Phenomena Identification and Ranking Table
- Development of Operating Envelope
- Fuel Element Laboratory Testing
- Fuel Irradiation Test Program
- Fuel Performance Modelling
- Fuel Surveillance Program The AGR test experience provides confidence that TRISO p article failure fractions in particles manufactured to similar specifications in a quality -controlled program will result in similar very low failure fractions.
Kairos Power Hermes Reactor 4 - 4 Revision 0 Preliminary Safety Analysis Report Reactor Description
Table 4.2 -1 : Fuel Particle Properties
Property Nominal Specified Value
Kernel diameter ( µ m) 425
Buffer thickness ( µ m ) 100
PyC thickness ( µ m ) 40
SiC thickness ( µ m ) 35 Kernel density (g/cm 3 ) > 10.4
Buffer density (g/cm 3) 1.05
PyC density (g/cm 3 ) 1.90
SiC density (g/cm 3) > 3.19
C/U atomic ratio 0.40
O/U atomic ratio 1.50
PyC BAF < 1.045
Kairos Power Hermes Reactor 4 -14 Revision 0 Preliminary Safety Analysis Report Reactor Description
Table 4.2 -2 : Fuel Pebble Dimensions and Properties
Property Specified Mean Nominal Value
Fuel Pebble
Outer shell outer radius ( c m) 2.0 Average Pebble Density (g/cm 3) 1.74
TRISO particles packing fraction (%) ~37
Pebble Uranium loading (g) 6.0
Number of particles per pebble ~ 16,000
Moderator Pebble
Moderator Pebble Radius (cm) 2.0 Average Density (g/cm 3) 1.74
Kairos Power Hermes Reactor 4 -15 Revision 0