ML23115A320

From kanterella
Revision as of 19:19, 14 November 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Application for the Japanese Certificate of Competent Authority No. J/2045/B(U)F, Revision 14, Model No. Jrc-80y-20t - Accepted for Review - Cost Activity Code/Enterprise Project Identification Number (CAC 001794/EPID L-2023-DOT-0006)
ML23115A320
Person / Time
Site: 07103035
Issue date: 05/01/2023
From: Garcia-Santos N
Storage and Transportation Licensing Branch
To: Boyle R
US Dept of Transportation (DOT), Office of Hazardous Materials Safety
References
CAC 001794, EPID L-2023-DOT-0006
Download: ML23115A320 (3)


Text

Richard W. Boyle, Chief Sciences Branch Division of Engineering and Research Office of Hazardous Materials Safety U.S. Department of Transportation 1200 New Jersey Ave., S.E.

Washington, D.C. 20590

SUBJECT:

APPLICATION FOR THE JAPANESE CERTIFICATE OF COMPETENT AUTHORITY NO. J/2045/B(U)F, REVISION 14, MODEL NO. JRC-80Y-20T -

ACCEPTED FOR REVIEW - COST ACTIVITY CODE/ENTERPRISE PROJECT IDENTIFICATION NUMBER [CAC NO. 001794/EPID NO. L-2023-DOT-0006]

Dear Richard W. Boyle:

By letter dated April 3, 2023 (Agencywide Documents Access and Management System

[ADAMS] Accession Number ML23115A074), you submitted an application to the U.S. Nuclear Regulatory Commission (NRC) for the review of the Certificate of Competent Authority No.

J/2045/B(U)F, Revision 14, Model No. JRC-80Y-20T. In your application you requested that the NRC provides a recommendation to revalidate the Model No. JRC-80Y-20T package.

We have completed the acceptance review of your application and determined that it contains sufficient technical information in scope and depth. Therefore, your application has been accepted for detailed technical review. Your application has been assigned a Cost Activity Code/Enterprise Project Identification Number [001794/L-2023-DOT-0006]. Please reference these numbers and Docket No. 71-3035 in any future correspondence associated with this request.

Please note that the NRC staffs technical review of your submittal may identify issues that could require that you provide additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by June 2023. The schedule includes the issuance, if needed, of a request for additional information (RAI) by May 2023, and, provided that we receive your responses to the RAI within 15 days after its issuance, we anticipate issuing the revalidation recommendation by June 2023. The NRC staff estimates that completing the review of your submittal will require approximately 250 staff hours. Please note that these dates could change depending on the findings of our technical review, urgent assignments, or other factors, such as whether your responses to the RAI are or not adequate.

In accordance with title 10 of the Code of Federal Regulations, section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. The ADAMS database is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).May 1, 2023 R. Boyle 2 If you have any questions regarding this communication, please contact me at (301) 415-6999, or via e-mail to Norma.GarciaSantos@nrc.gov.

Sincerely, Norma Garcia Santos, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-3035 Certificate No.: J/2045/B(U)

Signed by Garcia Santos, Norma on 05/01/23

Ltr ML23115A320 OFFICE NMSS/DFM/STLB NSIR/DSO/SOSB NMSS/DFM/STLB NMSS/DFM/STLB NAME NGarcia NG JCurry JCYDiaz-Sanabria YD NGarcia NG DATE Apr 25, 2023 Apr 27, 2023 May 1, 2023 May 1, 2023