MONTHYEARML24291A0272024-10-31031 October 2024 NRC Letter to C. Mayer Illinois SHPO Request to Initiate Section 106 Consultation for Subsequent License Renewal of Units 2 and 3 RS-24-103, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-10-21021 October 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-102, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-5912024-10-21021 October 2024 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-591 RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24225A2132024-09-26026 September 2024 Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval ML24253A0942024-09-23023 September 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID L-2024-Sle-0002) (Docket Numbers: 50-237 and 50-249) ML24270A0332024-09-20020 September 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVPLTR 24-0030, ISFSI Annual Effluent Release Report2024-09-20020 September 2024 ISFSI Annual Effluent Release Report IR 05000237/20244022024-09-19019 September 2024 – Security Baseline Inspection Report 05000237/2024402 and 05000249/2024402 - (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000237/20240022024-08-14014 August 2024 Integrated Inspection Report 05000237/2024002 and 05000249/2024002 ML24215A2912024-08-14014 August 2024 Request for Withholding Information from Public Disclosure Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations IR 05000237/20240102024-08-0909 August 2024 NRC Age-Related Degradation Inspection Report 05000237/2024010 and 05000249/2024010 ML24157A0792024-08-0808 August 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID L-2024-Sle-0002) (Docket Numbers: 50-237, and 50-249) IR 05000237/20230112024-08-0707 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 IR 05000237/20200012024-08-0606 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 - Integrated Inspection Report 05000237/2020001 and 05000249/2020001 ML24184A1712024-08-0202 August 2024 SLRA Schedule Letter RS-24-073, Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information2024-07-31031 July 2024 Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information ML24136A1322024-07-30030 July 2024 Transmittal Letter for Renewed License ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24193A0882024-07-24024 July 2024 Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Unit 1 Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations (Docket 50-10) ML24204A1862024-07-24024 July 2024 – Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2; TSTF-591, Revision 0; and 10 CFR 50.69 IR 05000237/20243012024-06-27027 June 2024 NRC Initial License Examination Report 05000237/2024301; 05000249/2024301 ML24138A0572024-06-26026 June 2024 – Issuance of Amendment Nos. 285 and 278 Application to Adopt TSTF-564, Safety Limit MCPR ML24138A1812024-06-18018 June 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24128A2742024-06-14014 June 2024 Notice of Acceptance and Opportunity for Hearing - Letter RS-24-063, Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-222024-06-14014 June 2024 Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-22 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24156A2332024-06-11011 June 2024 Letter Supplemental Information for Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24183A2752024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel SVPLTR 24-0020, Registration of Use of Casks to Store Spent Fuel2024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel RS-24-056, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2024-05-28028 May 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24145A0432024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel 10 CFR 72.212 SVPLTR 24-0019, Registration of Use of Casks to Store Spent Fuel2024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel ML24158A0012024-05-22022 May 2024 License Amendment Request to Adopt TSTF-564 (EPID L-2023-LLA-0120) Illinois State Concurrence ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24135A0722024-05-10010 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report ML24129A1352024-05-0808 May 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-59 ML24134A1132024-05-0808 May 2024 Retraction: LER 2303-001-00 for Dresden Nuclear Power Station, Unit 2, HPCI Inoperable Due to Air Void Accumulation ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) 2024-09-06
[Table view] Category:Schedule and Calendars
MONTHYEARML24184A1712024-08-0202 August 2024 SLRA Schedule Letter RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) ML1105407242011-02-23023 February 2011 2/23/11 Ltr to F. Schiffley Re Participation in Commission Meeting on 50.46a Risk-informed Emergency Core Cooling System Rule on 3/24/11 RS-07-017, Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations.2007-08-13013 August 2007 Amergen Energy Company, LLC, Response to NRC Regulatory Issue Summary 2007-17, Preparation and Scheduling of Operator Licensing Examinations. RS-06-134, Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations.2006-09-20020 September 2006 Response to NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator License Examinations. 2024-08-02
[Table view] |
Text
Christopher D. Wilson Director, License Renewal Constellation Energy Generation, LLC 200 Energy Way, KSA-3E Kennet Square, PA 19348
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE LETTER
Dear Mr. Wilson:
By letter dated April 17, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24108A007), Constellation Energy Generation, LLC (Constellation) submitted an application for subsequent license renewal of Renewed Facility Operating License Nos. DPR-19 and DPR-25 for Dresden Nuclear Power Station (Dresden),
Units 2 and 3, to the U.S. Nuclear Regulatory Commission (NRC, staff). By letter dated May 1, 2024 (ML24092A341), and Federal Register Notice published May 7, 2024 (89 FR 38197), the NRC noted the receipt and availability of this application.
On June 14, 2024 (ML24128A274), the NRC staff determined that the application contained sufficient information for the agency to formally docket the application and begin its safety and environmental reviews and stated that it was in the process of formulating its review schedule and resource estimates.
This letter forwards the NRC staffs review schedule for the Dresden subsequent license renewal application (SLRA) (Enclosure). The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by Title 10 of the Code of Federal Regulations (10 CFR) Parts 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, and 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants. Based on the information provided in the SLRA, the NRC staff has estimated that the review of the SLRA will take approximately 14,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> to complete. This estimate is inclusive of contractor support that the NRC will use for its review. If there are emergent complexities or challenges in the review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated via separate correspondence.
Milestones for hearing activities that may be needed are not included in the enclosed schedule or the estimated hours because these dates, if needed, would be established by the Commission or the Atomic Safety and Licensing Board and new resource considerations would need to be developed.
In performing the safety review, the staff will pilot the implementation of the new tiering approach in the evaluation of your ageing management programs. This is a graded approach that should result in a more streamlined review. In addition, the staff will also implement other review efficiencies identified over the last year. August 2, 2024 The review schedule also relies on your responses to the NRC staffs requests for additional information, if needed, being of high quality and provided in a timely manner. A timely response is defined as 30 days from the date of the request, or within such other time as may be specified in the request in accordance with 10 CFR 2.108, Denial of application for failure to supply information. You should also be prepared to provide high quality support in a timely and organized manner during technical audits determined to be necessary by the NRC staff. Delays in the NRC staffs receipt of necessary information could result in changes to the schedule for evaluating and processing the SLRA, up to and including the denial of the SLRA in accordance with the NRCs regulations. The NRC staff requests that you inform in writing, as early as possible, should potential delays arise in your support of the schedule. The NRC staffs goal is to complete the review of the SLRA in 18 months provided that Constellation fully addresses the staffs information needs in a timely manner. The staff is committed to complete the milestones ahead of schedule, whenever feasible.
If you have any questions on this matter, please contact Mr. Mark Yoo, Senior Project Manager for the safety review of the SLRA, by email at Mark.Yoo@nrc.gov or Mr. Tam Tran, Project Manager for the environmental review, by email at Tam.Tran@nrc.gov.
Sincerely, Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-237 and 50-249
Enclosure:
Review Schedule cc w/encl: Listserv Signed by Smith, Brian on 08/02/24
ML24184A171 OFFICE NRR/DNRL/NLRP/PM NRR/DNRL/NLIB/LA NMSS/REFS/EPMB1/PM NAME MYoo KBratcher TTran DATE 7/2/24 7/2/24 7/30/24 OFFICE NMSS/REFS/EPMB1/BC NRR/DNRL/NLRP/BC NRR/DNRL/D NAME SKoenick LGibson BSmith DATE 8/2/24 8/2/24
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE
Milestone Scheduled Actual
Receive Subsequent License Renewal Application (SLRA) 04/2024 04/17/24 Publish Federal Register Notice (FRN) - SLRA Availability 04/2024 05/07/24 Publish FRN - Docketing Acceptance/Rejection and 06/2024 06/24/24 Opportunity for Hearing Publish FRN - Notice of Intent to Prepare an 08/2024 Environmental Impact Statement and Conduct Scoping Public Meeting - Overview of Subsequent License 08/2024 Renewal Process and Environmental Scoping Deadline for Filing Hearing Requests and Petitions for 08/2024 08/23/24 Intervention
Environmental Scoping Period Ends 09/2024
Issue Draft Supplemental Environmental Impact Statement 06/2025 (SEIS)
Public Meeting - Draft SEIS Meeting, If Needed TBD Draft SEIS Comment Period Ends 07/2025 Issue Safety Evaluation 09/2025 Issue Final SEIS 10/2025 Advisory Committee on Reactor Safeguards Full Committee 11/2025 Meeting U.S. Environmental Protection Agency FRN Published - 11/2025 Availability of Final SEIS Decision - Director, Office of Nuclear Reactor Regulation 12/2025
Enclosure