(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Letter Sequence Request |
---|
|
|
MONTHYEARML20066K2702020-03-0606 March 2020 Updated GEH Morris Operation (Mo) Decommissioning Funding Plan (DFP) Project stage: Request ML20134H8852020-04-30030 April 2020, 13 May 2020 GEH-Morris Operation Independent Spent Fuel Storage Installation Exemption from 10 CFR 72.42(c) Project stage: Request ML20182A7002020-06-30030 June 2020 GEH Morris Operation (Mo) Submittal of License Renewal Application Project stage: Other ML20213C3252020-07-31031 July 2020 7-31-2020 Email Acknowledgement of NRC Receipt of GEH Morris Operation LRA and Start of Acceptance Review.Pdf Project stage: Acceptance Review ML20289A4932020-10-0808 October 2020 NRC 699 (10-8-2020 Call on GE Hitachi Nuclear Energy Americas LLC (GEH) GEH-Morris Rsis, Signed) Project stage: Other ML20275A2802020-10-15015 October 2020 GEH-Morris License Renewal Rsi, Request for Supplemental Information for Acceptance Review of the Application for Renewal of the Morris Operation License No. SNM-2500 (Cac/Epid Nos. 001028/L-2020-RNW-0024 and 000993/L-2020-LNE-0004) Project stage: Acceptance Review ML21085A8592021-03-22022 March 2021 3/22/2021 E-mail Request for Clarification of 2/26/2021 Rsi Response for GEH-Morris License Renewal Application Project stage: Approval ML21168A2582021-06-17017 June 2021 GE-Hitachi Nuclear Energy Americas, LLC, Updated Morris Operation Decommissioning Funding Plan Project stage: Request ML21242A2812021-08-25025 August 2021 NRC 699 (8-25-2021 Call with GEH on Morris Renewal Draft Rais, Signed) Project stage: Draft RAI ML21214A3102021-08-30030 August 2021 Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 (Cac/Epid Nos. 001028/L-2020-RNW-0024) Project stage: RAI ML21216A2722021-12-21021 December 2021, 29 December 2021, 5 January 2022 GEH Morris Decommissioning Funding Plan Approval Project stage: Request ML22027A5162022-01-27027 January 2022 GEH - Morris Operation (Mo) Response to Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 Project stage: Response to RAI ML22132A0722022-05-12012 May 2022 GEH Morris Operation (Mo) Response to NRC Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 Project stage: Response to RAI ML22146A3912022-05-19019 May 2022 List of Illinois Threatened & Endangered Species for Grundy and Will Counties - Proposed License Renewal for Morris Operation Independent Spent Fuel Storage Installation Project stage: Other ML22181B0942022-07-31031 July 2022 NUREG-2237, Environmental Impact Statement for the Holtec Internationals License Application for a Consolidated Interim Storage Facility for Spent Nuclear Fuel in Lea County, New Mexico Final Report Project stage: Other ML22249A0952022-09-0808 September 2022 Proprietary Determination Letter for GEH-Morris License Renewal Application Submittals Project stage: Other ML22286A0012022-10-12012 October 2022 NRC Form 699 for Technical Discussions from March 15 to 17 of 2022 Related to the Application of the Castor geo69 Storage System (Docket No. 72-1052) (Redacted) Project stage: Other ML22242A0162022-11-22022 November 2022 Cover Letter for GEH Morris Operation ISFSI Subsequent License Renewal Project stage: Other ML22234A2562022-11-22022 November 2022, 28 November 2022, 30 November 2022 License Renewal of GEH Morris Operation Independent Spent Fuel Storage Installation License No. SNM-2500 Project stage: Request ML22242A0442022-11-28028 November 2022 GEH Morris Operation FRN Notice of Issuance for Subsequent License Renewal of SNM-2500 Project stage: Other ML22270A2692022-11-30030 November 2022 Environmental Assessment for Proposed Renewal of NRC License SNM-2500 for the GE-Hitachi Nuclear Energy Morris Operation Independent Spent Fuel Storage Installation, Grundy County, Illinois Project stage: Request ML23076A2722023-03-17017 March 2023 HI-STORM 100 Amendment 16 RAI 3-3 Clarification Project stage: Other ML24002B1432024-01-0202 January 2024 Attachment (Redacted) - Email Dated 1/2/24 Dbussmann (Gns) to Ngarcia (Nrc), Staggered RAIs Castor geo69 Storage, Applicants Proprietary Review of Staggered RAIs Castor geo69 Storage Application-Shielding Evaluation (Public) Project stage: RAI ML24067A1852024-02-0808 February 2024 Attachment 1 - Conversation Record HI-STORM Flood/Wind Storage System Amendment 7: Staffs Observation on 1/26/2024 Meeting Project stage: Meeting L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) Project stage: Response to RAI 2022-01-27
[Table View] |
|
---|
Category:Letter
MONTHYEARML24299A0682024-10-25025 October 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24284A1182024-10-10010 October 2024 GEH - Notification of GE Company Stock Beneficial Ownership Filing ML24296B1562024-07-0303 July 2024 GE-Hitachi Nuclear Energy Americas, LLC - Updated GEH Morris Operation Decommissioning Funding Plan, Revision 6 (Redacted Version of ML24185A193) ML24156A0752024-06-10010 June 2024 Application for Exemption from Select Requirements of Title 10 of the Code of Federal Regulations Part 73 for the Morris Operation - Acknowledgement of Withdrawal and Notification of the U.S. Nuclear Regulatory Commission Staff Efforts Clos ML24145A1292024-05-24024 May 2024 Morris Operation Request to Withdraw Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation IR 07200001/20230012024-03-0707 March 2024 GE Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation NRC Inspection Report 07200001/2023001 ML24057A2742024-02-26026 February 2024 GE-Hitachi Nuclear Energy Americas, LLC, 2023 GEH Morris Operation Annual Effluent Report ML24032A1082024-02-0101 February 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24004A1652024-01-0404 January 2024 Morris Operation (Mo) Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23345A0812023-12-11011 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed IR 07200001/20234012023-11-28028 November 2023 GE Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation NRC Security Inspection Report 07200001/2023401 ML23276B3952023-10-13013 October 2023 The U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML23177A0892023-06-26026 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 2 ML23171A9762023-06-20020 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 1 ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23054A3332023-02-23023 February 2023 GEH Notification of GE Company Stock Beneficial Ownership Filing ML23044A3282023-02-10010 February 2023 GEH Morris Operation Submittal of Updated Consolidated Safety Analysis Report (CSAR, Rev 15A, Feb 2023) ML22350A4702022-12-12012 December 2022 GEH Morris Operation Submittal of Biennial Report 10CFR72.48; Changes, Tests, and Experiments ML22242A0162022-11-22022 November 2022 Cover Letter for GEH Morris Operation ISFSI Subsequent License Renewal ML22313A1452022-11-0909 November 2022 Usfws Illinois-Iowa Ecological Services Field Office - Species List for Proposed License Renewal for GE-Hitachi Morris Operation Independent Spent Fuel Storage Installation - Project Code: 2022-0044583 ML22249A0952022-09-0808 September 2022 Proprietary Determination Letter for GEH-Morris License Renewal Application Submittals ML22249A3652022-09-0606 September 2022 GEH Notification of GE Company Stock Beneficial Ownership Filing ML22146A3512022-05-19019 May 2022 Usfws Illinois-Iowa Ecological Services Field Office - Species List for Proposed License Renewal for Morris Operation Independent Spent Fuel Storage Installation - Project Code: 2022-0044583 ML22132A0722022-05-12012 May 2022 GEH Morris Operation (Mo) Response to NRC Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 ML22084A5782022-03-23023 March 2022 GNF-A/GEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML22068A1322022-03-0909 March 2022 GE-Hitachi Nuclear Energy Americas, LLC, Notification of Stock Beneficial Ownership Filing ML22054A0292022-02-22022 February 2022 GE-Hitachi Nuclear Energy Americas, LLC, 2021 Morris Operation Annual Effluent Report ML22042A4152022-02-11011 February 2022 GE-Hitachi Nuclear Energy Americas, LLC - GEH Notification of GE Company Stock Beneficial Ownership Filings ML22027A5162022-01-27027 January 2022 GEH - Morris Operation (Mo) Response to Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 ML21216A2752022-01-0505 January 2022 GEH Morris DFP Close-out Letter ML21326A2662021-11-22022 November 2021 GEH Notification of GE Company Stock Beneficial Ownership Filing ML21319A2202021-11-17017 November 2021 Letter - Proprietary Determination for GEH Morris DFP Submittals ML21340A2432021-09-28028 September 2021 Illinois Threatened and Endangered Species by County, as of December 2020 IR 07200001/20214012021-09-27027 September 2021 GE-Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation - NRC Security Inspection Report 07200001/2021401 ML21252A1382021-09-0909 September 2021 GEH - Morris Operation (Mo) Decommissioning Funding Plan (DFP) Redacted Versions ML22063B1752021-08-30030 August 2021 Email and Letter from D. Hunter of Miami Tribe NRC Preliminary Determination Under Section 106 of the NHPA for Proposed GE-Hitachi Morris Operation ISFSI License Renewal ML21214A3102021-08-30030 August 2021 Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 (Cac/Epid Nos. 001028/L-2020-RNW-0024) ML21138A9052021-08-0202 August 2021 Letter to Hannahville Indian Community Re NRC Preliminary Determination Under Section 106 of the National Historic Preservation Act ML21186A0082021-08-0202 August 2021 Letter to Citizen Potawatomi Nation Re NRC Preliminary Determination Under Section 106 of the NHPA ML21186A0092021-08-0202 August 2021 Letter to Forest County Potawatomi Re NRC Preliminary Determination Under Section 106 of the NHPA ML21186A0112021-08-0202 August 2021 Letter to Ho-Chunk Nation Re NRC Preliminary Determination Under Section 106 of the NHPA ML21188A2052021-08-0202 August 2021 Letter to Kickapoo Tribe in Kansas Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2312021-08-0202 August 2021 Letter to Little Traverse Bay Bands of Odawa Indians Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2522021-08-0202 August 2021 Letter to Match-E-Be-Nash-She-Wish Band of Potawatomi Indians Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2602021-08-0202 August 2021 Letter to Menominee Indian Tribe of Wisconsin Re NRC Preliminary Determination Under Section 106 of the NHPA 2024-07-03
[Table view] |
Text
GE Hitachi Nuclear Energy HITACHI Scott P. Murray Manager, Facility Licensing 3901 Castle Hayne Road Security Related and Proprietary Information Notice P.O. Box 780 The Enclosure to this letter contains both security related and Wilmington, NC 28402 USA proprietary information which is to be withheld from public disclosure in accordance with 10CFR2.390. T (910) 819-5950 scott.murray@ge.com M200036 March 6, 2020 Director, Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Attn: Document Control Desk
Subject:
Updated GEH Morris Operation (MO) Decommissioning Funding Plan (DFP)
References:
- 1) NRC License SNM-2500, Docket 72-1
- 2) GEH MO DFP, SNM -2500, Revision 3, 12/14/18
- 3) GEH/GNF-A Financial Assurance of Decommissioning Funds - Surety Bond Riders, 3/19/19
Dear Sir or Madam:
GE Hitachi Nuclear Energy Americas, LLC (GEH) hereby provides an updated decommissioning funding plan (DFP) pursuant to 10 CFR 72.30(c) for the Morris Operation SNM-2500 license (Reference 1).
The decommissioning cost estimate was reviewed and updated in 2019 by an independent third-party engineering firm. As a result of this update, the cost estimates primarily for waste inventory and disposal costs have been lowered and prior approval is requested to allow lowering the financial assurance surety b'ond amount.
The updated MO DFP is provided as an enclosure to this letter and replaces the previously submitted version (Reference 2). Please note that the DFP contains both security related and sensitive proprietary information and is requested to be withheld from public disclosure in accordance with 10 CFR 2.390.
Revised DFP sections compared to the previous version are identified with a vertical line in the right-hand margin on each revised page.
Please contact me at (910) 819-5950 if you have any questions.
Si7~A Scott P. Murray, Manager Facility Licensing
Enclosure:
GEH MO SNM-2500 Decommissioning funding Plan, Revision 4, 2/28/20 Cc: K. Banovac, USNRC NMSS DFM SPM 20-011