Letter Sequence RAI |
---|
EPID:L-2022-LLA-0120, MTS - Meeting Summary - Public Meeting on March 28, 2023- Hatch RPV Head Closure Bolts LAR LAR (Approved, Closed) |
|
MONTHYEARNL-22-0406, Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes2022-08-19019 August 2022 Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes Project stage: Request ML22258A1532022-09-15015 September 2022 NRR E-mail Capture - Acceptance Review - Hatch Closure Studs in TS Table 1.1-1 Modes LAR (L-2022-LLA-0120) Project stage: Acceptance Review ML22305A7032022-11-0101 November 2022 NRR E-mail Capture - Potential Audit for Hatch'S 'Rpv Head Studs' LAR Project stage: Approval ML22320A0722022-11-17017 November 2022 Regulatory Audit in Support of Review of the Application to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs Project stage: Approval ML22355A2082022-12-21021 December 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, Reactor Pressure Vessel 'Rpv Head Studs' LAR Project stage: RAI NL-23-0003, Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 12023-01-20020 January 2023 Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1 Project stage: Response to RAI ML23033A0282023-01-30030 January 2023 NRR E-mail Capture - Revised Estimates for Hatch RPV Studs LAR Project stage: Approval ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs Project stage: Other PMNS20230217, Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch)2023-03-0303 March 2023 Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch) Project stage: Meeting ML23088A2282023-03-0303 March 2023, 28 March 2023, 3 April 2023 MTS - Meeting Summary - Public Meeting on March 28, 2023- Hatch RPV Head Closure Bolts LAR LAR Project stage: Request ML23065A0922023-03-0505 March 2023 NRR E-mail Capture - Revised Estimate Hours and Completion Date - Hatch RPV Head Closure Bolts LAR (L-2022-LLA-0120) Project stage: Approval ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 Project stage: Meeting ML23088A3882023-04-0303 April 2023 Summary of March 28, 2023, Observation Public Meeting Held with SNC, Regarding a License Amendment Request Regarding the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plan, Units 1 and 2 Project stage: Meeting PMNS20230486, Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch)2023-04-20020 April 2023 Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch) Project stage: Meeting ML23136B2952023-04-20020 April 2023, 19 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 Project stage: Request ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 Project stage: Meeting ML23249A2082023-09-0606 September 2023 NRR E-mail Capture - Change in Estimated Review Schedule and Level of Effort for Hatch 'Revise TS Table 1.1-1 (Modes)' LAR (L-2022-LLA-0120) Project stage: Approval ML23264A0142023-09-14014 September 2023 NRR E-mail Capture - (External_Sender) Draft Round-2 RAI - Hatch, Units 1 and 2, Revise TS 1.1-1 Modes LAR Project stage: Draft Other ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes Project stage: RAI PMNS20231395, Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch)2023-12-21021 December 2023 Notice of Public Meeting with Southern Nuclear Operating Company, Inc. (SNC) to Discuss Submitted License Amendment Request (LAR) for the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch) Project stage: Meeting ML23361A1092024-01-0808 January 2024 SNC Slides for Public Meeting on 1-8-24 to Discuss Hatch LAR - Revise TS Table 1.1-1 (Modes) to Relax Required No. of Fully Tensioned RPV Head Closure Studs Project stage: Meeting ML24012A1592024-01-30030 January 2024 Summary of January 8, 2024, Meeting Held with Southern Nuclear Operating Company, Inc., to Discuss a RAI License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Head Bolts Project stage: RAI NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. Project stage: Response to RAI ML24067A0702024-03-0707 March 2024 NRR E-mail Capture - Change in Estimated Review Completion for Hatch Revise TS Table 1.1-1 (Modes) LAR (L-2022-LLA-0120) Project stage: Approval 2023-03-03
[Table View] |
Similar Documents at Hatch |
---|
Category:E-Mail
MONTHYEARML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24220A2502024-10-15015 October 2024 Email to Ryan Joyce Re Decision on the Hatch Exemption ML24220A2472024-10-11011 October 2024 Email to Ryan Joyce Re Availability of EA-FONSI for Hatch Exemption ML24281A1362024-10-0707 October 2024 NRR E-mail Capture - (External_Sender) Acceptance Review - Hatchs Revise Technical Specifications to Adopt TSTF-591 LAR (L-2024-LLA-0122) ML24278A0052024-10-0303 October 2024 Document Request for Hatch Nuclear Plant - IP 92702 Follow-Up Radiation Protection Inspection - Inspection Report 2024-04 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24211A0162024-07-26026 July 2024 NRR E-mail Capture - Request for Additional Information - Hatch, Units 1 and 2, Revise TS SRs (3.4.3.1 & 3.1.7.7) to Increase SRV Setpoints LAR ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24193A1182024-07-10010 July 2024 Email to SNC with RAI for Hatch Exemption Request ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24142A4992024-05-21021 May 2024 NRR E-mail Capture - Acceptance Review - Farley and Hatch - LAR to Revise TS 1.1 and Add Online Monitoring (OLM) Program (L-2024-LLA-0058) ML24138A1582024-05-17017 May 2024 NRR E-mail Capture - (External_Sender) Acceptance Review - Hatchs Revise TS Surveillance Requirements to Increase SRV Setpoints LAR (L-2024-LLA-0054) ML24100A4402024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) RAI - Hatch, Units 1 and 2, Revise Technical Specifications to Adopt Extended RICTs for RHRSW and Psw Systems LAR ML24100A0072024-04-0808 April 2024 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML24082A1212024-03-21021 March 2024 NRR E-mail Capture - (External_Sender) Re Acceptance Review - Hatchs Adopt Alternative Seismic Method for 50.69 Categorization of SSCs LAR (L-2024-LLA-0017) ML24067A0702024-03-0707 March 2024 NRR E-mail Capture - Change in Estimated Review Completion for Hatch Revise TS Table 1.1-1 (Modes) LAR (L-2022-LLA-0120) ML24009A1112024-01-0909 January 2024 NRR E-mail Capture - Acceptance Review - Hatch 1&2 LAR - Revise TS 3.7.1 & 3.7.2 to Adopt Risk-Informed Completion Times for RHRSW and Psw Systems (L-2023-LLA-0169) ML23354A2032023-12-18018 December 2023 Document Request for Hatch Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-01 ML23264A0142023-09-14014 September 2023 NRR E-mail Capture - (External_Sender) Draft Round-2 RAI - Hatch, Units 1 and 2, Revise TS 1.1-1 Modes LAR ML23249A2082023-09-0606 September 2023 NRR E-mail Capture - Change in Estimated Review Schedule and Level of Effort for Hatch 'Revise TS Table 1.1-1 (Modes)' LAR (L-2022-LLA-0120) ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23135A0922023-05-11011 May 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Request to Use Specific Provision of a Later Edition of the ASME BPV Code, Section XI (L-2023-LLR-0016) ML23073A0252023-03-13013 March 2023 NRR E-mail Capture - Fyi - Closeout the Evacuation Time Estimate (ETE) Reviews for SNC Fleet ML23065A0922023-03-0505 March 2023 NRR E-mail Capture - Revised Estimate Hours and Completion Date - Hatch RPV Head Closure Bolts LAR (L-2022-LLA-0120) ML23033A0952023-02-0202 February 2023 NRR E-mail Capture - (External_Sender) Re for Your Comments - State of Georgia - Hatch Units 1 and 2 - Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML23033A0282023-01-30030 January 2023 NRR E-mail Capture - Revised Estimates for Hatch RPV Studs LAR ML23026A0132023-01-19019 January 2023 NRR E-mail Capture - Revised Estimates for Hatch RPV Studs LAR ML23018A1872023-01-17017 January 2023 2023 HNP CGD Inspection Information Request ML23006A0662023-01-0505 January 2023 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - Revise NFPA-805 License Amendment Request ML22355A2082022-12-21021 December 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, Reactor Pressure Vessel 'Rpv Head Studs' LAR ML23006A0252022-12-13013 December 2022 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - TSTF-208 License Amendment Request ML22341A1212022-12-0606 December 2022 NRR E-mail Capture - Recap of Takeaways from Hatch Audit on Dec 1, 2022 ML23026A2372022-11-16016 November 2022 2023001 Hatch RP RFI Final ML22305A7032022-11-0101 November 2022 NRR E-mail Capture - Potential Audit for Hatch'S 'Rpv Head Studs' LAR ML22258A1532022-09-15015 September 2022 NRR E-mail Capture - Acceptance Review - Hatch Closure Studs in TS Table 1.1-1 Modes LAR (L-2022-LLA-0120) ML22251A1322022-09-0808 September 2022 NRR E-mail Capture - Fyi - Hatch TSTF-505 LAR ML22208A1332022-07-26026 July 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-208 LAR ML22207B8532022-07-25025 July 2022 NRR E-mail Capture - RCI - Hatch, Units 1 and 2, Revision to NFPA-805 LAR ML22157A3552022-06-0606 June 2022 NRR E-mail Capture - Revised Estimates - Hatch TSTF-505 LAR ML22157A3542022-06-0606 June 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-505 LAR ML22140A1192022-05-20020 May 2022 NRR E-mail Capture - RAIs - Hatch, Units 1 and 2, TSTF-505 LAR ML22138A4122022-05-18018 May 2022 NRR E-mail Capture - Acceptance Review - Hatch TSTF-208 LAR (L-2022-LLA-0045) ML22140A1182022-05-13013 May 2022 NRR E-mail Capture - for Your Action: Hatch TSTF-505 - Follow Up from Audit Question 12 ML22116A1492022-04-26026 April 2022 NRR E-mail Capture - Acceptance Review - Hatch Revise NFPA 805 LAR (L-2022-LLF-0000) ML22055A6652022-02-24024 February 2022 NRR E-mail Capture - Acceptance Review - Hatch TSTF-580 LAR (L-2022-LLA-0022) ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21357A0912021-12-23023 December 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-207-A LAR (L-2021-LLA-0219) ML21354A5942021-12-20020 December 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-227 and TSTF-297 LAR (L-2021-LLA-0227) ML21347A8532021-12-13013 December 2021 NRR E-mail Capture - Required: Hatch TSTF-505 LAR - Audit Plan - Additional Documents to Be Uploaded to the Portal 2024-09-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24278A0052024-10-0303 October 2024 Document Request for Hatch Nuclear Plant - IP 92702 Follow-Up Radiation Protection Inspection - Inspection Report 2024-04 ML24211A0162024-07-26026 July 2024 NRR E-mail Capture - Request for Additional Information - Hatch, Units 1 and 2, Revise TS SRs (3.4.3.1 & 3.1.7.7) to Increase SRV Setpoints LAR ML24208A1742024-07-26026 July 2024 Request for Additional Information Regarding License Amendment Request to Revise TS SRs (3.4.3.1 & 3.1.7.7) to Increase S/Rv Setpoints ML24193A1182024-07-10010 July 2024 Email to SNC with RAI for Hatch Exemption Request ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23354A2032023-12-18018 December 2023 Document Request for Hatch Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-01 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23264A0142023-09-14014 September 2023 NRR E-mail Capture - (External_Sender) Draft Round-2 RAI - Hatch, Units 1 and 2, Revise TS 1.1-1 Modes LAR ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23018A1872023-01-17017 January 2023 2023 HNP CGD Inspection Information Request ML22355A2082022-12-21021 December 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, Reactor Pressure Vessel 'Rpv Head Studs' LAR ML23026A2372022-11-16016 November 2022 2023001 Hatch RP RFI Final ML22208A1332022-07-26026 July 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-208 LAR ML22157A3542022-06-0606 June 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-505 LAR ML22140A1192022-05-20020 May 2022 NRR E-mail Capture - RAIs - Hatch, Units 1 and 2, TSTF-505 LAR ML22073A0842022-03-21021 March 2022 an NRC Fire Protection Team Inspection (NRC Inspection Report Nos. 05000321/2022011 and 05000366/2022011) and Request for Information ML22025A2142022-01-21021 January 2022 Plant Hatch 2022001 RP Baseline Inspection Information Request ML21265A3402021-09-22022 September 2021 NRR E-mail Capture - Request for Additional Information - Hatch, Unit 1, Emergency TS 3.7.2 LAR ML21111A3032021-04-21021 April 2021 NRR E-mail Capture - RAI - Hatch Unit 2 - One-Time Emergency RHR LAR (L-2020-LRO-0068) ML21110A6842021-04-20020 April 2021 NRR E-mail Capture - RAI - Hatch Unit 2 - One-Time Emergency RHR LAR (L-2020-LRO-0068) ML21013A4112021-01-13013 January 2021 Notification of Edwin I. Hatch Nuclear Plant Design Bases Assurance Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000321/2021010 and 05000366/2021010 ML20293A0752020-10-14014 October 2020 NRR E-mail Capture - RAIs for SNC Fleet EP LAR (L-2020-LLA-0150 and L-2020-LLA-0151) ML20253A2732020-09-0909 September 2020 Requalification Program Inspection Hatch Nuclear Station ML20149K6252020-05-27027 May 2020 NRR E-mail Capture - RAIs for SNC Fleet Fire Protection Exemption Requests NL-19-1532, Units 1 and 2 - Response to Requests for Additional Information Regarding Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures. Systems and Components for Nuclear Power Reactors2019-12-18018 December 2019 Units 1 and 2 - Response to Requests for Additional Information Regarding Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures. Systems and Components for Nuclear Power Reactors ML19336A0142019-12-0101 December 2019 NRR E-mail Capture - RAI: Hatch Emergency TS 3.7.1 Residual Heat Removal Service Water (RHRSW) System LAR ML19280A0082019-10-0404 October 2019 NRR E-mail Capture - Request for Additional Information (RAI) - Hatch TSTF-51 LAR (L-2019-LLA-0091) ML19224C0552019-08-12012 August 2019 NRR E-mail Capture - RAI - Edwin I. Hatch Nuclear Plant, LAR Regarding Degraded Voltage (L-2019-LLA-0108) ML19220A0362019-08-0808 August 2019 NRR E-mail Capture - RAI - Edwin I. Hatch Nuclear Plant, LAR Regarding Adoption of NFPA 805, Request for Additional Information, EPID L-2018-LLA-0107 ML19164A2582019-06-13013 June 2019 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML19107A4962019-04-17017 April 2019 NRR E-mail Capture - Request for Additional Information - Hatch 1 & 2 Application to Adopt Title 10 of Code of Federal Regulations 50.69 RISK-INFORMED Categorization and Treatment of Structures, Systems and Components for Power Reactors ML19088A0092019-03-29029 March 2019 NRR E-mail Capture - Hatch 1 and 2 - LAR to Adopt NFPA 805 Fire Protection Standard, EPID L-2018-LLA-0107, Request for Additional Information ML19029B3402019-01-23023 January 2019 Southern Nuclear Operating Company, Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2 Draft Request for Additional Information for the License Amendment Requests to Adopt the Risk-Informed Provisions of Title 10 of the Code of Federal Regulat ML19016A3422019-01-10010 January 2019 U2 ISI 2019001 RFI - Bcc ML18355A4772019-01-0404 January 2019 Request for Additional Information Revise TS 5.2.2.g and Update Emergency Plan Minimum On-Shift Staff Tables ML18337A4032018-12-0606 December 2018 Request for Additional Information Revise Technical Specification 5.2.2.G and Updating Emergency Plan Minimum On-Shift Staff Tables ML18085A0132018-03-0808 March 2018 Draft Request for Additional Information on Alternative RR-V-11, Proposed Extension to Main Steam Safety Relief Valve Testing Requirements ML18058A0812018-02-27027 February 2018 Enclosurequest for Additional Information(Rai for Review of Southern Nuclear Operating Company'S Decommissioning Funding Plan Updates for Joseph M. Farley,Unit 1 and 2;Edwin I. Hatch,Units 1 and 2; and Vogtle Electric Generating Plant, Unit ML17306A0872017-11-0808 November 2017 Request for Additional Information Regarding the Decommissioning Funding Status Reports (EPID L-LRO-2017-0008) ML17284A3542017-11-0707 November 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools ML17270A1402017-09-27027 September 2017 PIR Notification Letter 2017 ML17290A3172017-09-19019 September 2017 NRR E-mail Capture - Hatch 1 and 2 - Draft Request for Additional Information Request for Alternative No. HNP-ISI-ALT-05-05 ML17111A5792017-04-26026 April 2017 Request for Additional Information, Fourth 10-Year ISI Interval Relief Requests ML17110A2112017-04-24024 April 2017 Request for Additional Information ML16330A1282016-12-0505 December 2016 Request for Additional Information ML16307A1842016-11-0202 November 2016 Request for Additional Information (Non-Proprietary) ML16271A1692016-10-17017 October 2016 Request for Additional Information ML16222A2952016-08-29029 August 2016 Request for Additional Information ML16205A0012016-07-22022 July 2016 Requalification Program Inspection - Plant Hatch 2024-07-26
[Table view] |
Text
From: Dawnmathews Kalathiveettil Sent: Wednesday, December 21, 2022 12:31 PM To: Quarles, Adam Graham Cc: Chamberlain, Amy Christine; Michael Markley; John Lamb
Subject:
RAI - Hatch, Units 1 and 2, 'RPV Head Studs' LAR (EPID: L-2022-LLA-0120)
Importance: High
- Adam, By letter dated August 19, 2022 (Agencywide Documents and Access Management System (ADAMS) Accession No. ML22231B055), Southern Nuclear Operating Company (SNC, the licensee) submitted a license amendment request (LAR) for Edwin I. Hatch Nuclear Plant (Hatch), Units 1 and 2. Specifically, the licensee is proposing to relax the required number of fully tensioned reactor pressure vessel (RPV) head closure studs in Technical Specification (TSs) Table 1.1-1, MODES of the Hatch units.
The licensee included with the application calculations performed by its contractor, Dominion Engineering, Inc. (DEI) that determined the impact of out-of-service studs on RPV closure stresses, stud stresses, closure flange separation, and fatigue usage. These calculations are documented in C-037-2201-00-01, Revision 0, Hatch Unit 1 Operation with One Stud Out of Service Evaluation (Enclosure 2 to the application) and C-037-2201-00-02, Revision 0, Hatch Unit 2 Operation with Two Studs Out of Service Evaluation (Enclosure 3 to the application).
By letter dated November 17, 2022 (ADAMS Accession No. ML22320A072), the NRC informed SNC of the need for a regulatory audit from November 30, 2022, to January 31, 2023. Audit meetings were held between SNC, its contractor, and NRC staff on December 1st and December 14th, 2022.
To complete its review, the NRC staff requests additional information (RAI) as shown below.
These questions were previously provided to SNC during the audit to make sure that the RAI is understandable, the regulatory basis is clear, to ensure there is no proprietary information, and to determine if the information was docketed previously.
This request is now released formally with a 30-day calendar response period from the date of this e-mail. If you have any questions, you may contact me at 301-415-5905.
REQUEST FOR ADDITIONAL INFORMATION Title 10 of the Code of Federal Regulations (10 CFR) Part 50.36, Technical Specifications, specifies the content required to be included in TSs.
10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities, Appendix A, General Design Criteria [GDC] for Nuclear Power Plants, includes the following GDCs applicable to the licensees LAR:
- GDC 1, Quality Standards and Records, requires, in part, that structures, systems, and components important to safety be designed, fabricated, erected, and tested to quality standards commensurate with the importance of the safety function to be performed.
- GDC 14, Reactor coolant pressure boundary, requires the design, fabrication, erection, and testing of the reactor coolant pressure boundary so as to have an extremely low probability of abnormal leakage, or rapidly propagating failure, and of gross rupture.
- GDC 30, Quality of reactor coolant pressure boundary, which requires in part, that components comprising the reactor coolant pressure boundary be designed, fabricated, erected, and tested to the highest quality standards practical.
Hatch Unit 1 was licensed to the applicable Atomic Energy Commission (AEC) preliminary general design criteria identified in Federal Register 32 FR 10213, published July 11, 1967 (ML043310029). The Hatch Unit 1 Updated Final Safety Analysis Report (UFSAR), Appendix F, Conformance to the AEC Criteria, contains the comparison of the applicable AEC criteria to the 10 CFR 50, Appendix A, GDCs.
NRC staff has reviewed the application and the information provided during the regulatory audit.
To complete its review, the NRC staff requests additional information as shown below.
RAI-01
The NRC authorized relief requests, in 2017 and 2019 (ML17205A345 and ML19035A550 respectively), from inspection of RPV stud #33 based on impracticality. The 2017 authorization was a contingency in case the two planned stud removal techniques were not successful during refueling outage 2R24. Similarly, the 2019 relief was authorized, through the end of the current ISI interval (December 31, 2025), in case attempts to remove RPV stud #33 were not successful during the Hatch Unit No. 2 refueling outage 2R25.
a) Please provide a summary of all attempts to inspect and/or remove stud #33 since the 2017 authorization, including techniques applied for removal of each attempt, results achieved, and acceptance criteria for terminating removal efforts.
b) Also, please provide post-tensioning values for the as-left condition of stud #33 for each outage.
RAI-02
In its LAR dated August 19, 2022, the licensee states that Table 1.1-1 is proposed to be revised to address the increased possibility that a RPV head closure stud cannot be fully tensioned and avert the possible need for an exigent or emergency license amendment during the Spring 2023 refueling outage.
a) Please describe the technical basis supporting the assertion that stud #33 or any other stud cannot be fully tensioned.
b) Please provide any estimated calculations or inspection results that would indicate that the known flaw on stud #33 would propagate to a point such that sufficient tensioning is not achievable.
RAI-03
In its LAR dated August 19, 2022, the licensee requests approval of operation of Hatch, Unit 2, with two RPV studs less than fully tensioned and Hatch, Unit 1, with one stud less than fully tensioned. Based on the 2017 and 2019 relief requests, the NRC understands the impracticality
assessment regarding stud #33. Based on review of Section 2.3 of the SNC submittal, the NRC has concerns regarding the basis for the need regarding the request to allow a second stud to be less than fully tensioned in Hatch Unit 2 and the basis for any RPV studs to be less than fully tensioned in Hatch Unit 1.
Please provide the safety basis to have additional studs less than fully tensioned in Unit 1 and 2 when there is no apparent degradation or inspection results supporting such action.
RAI-04
In its 2019 relief request, the licensee told the NRC that it planned to remove stud #33 and requested relief as a contingency. In its LAR, the licensee states that, There were no attempts to remove the stud during the 2021 refueling outage (2R26), but asserts that these amendments are needed to avert the possible need for an exigent or emergency license amendment during the Spring 2023 refueling outage. Because this condition has existed for more than six years and the licensee has had opportunities to remove/repair stud #33, the NRC has concerns that the entry conditions for an exigent or emergency amendment may be challenging to address. During the audit on December 14, 2022, SNC stated that there are no repair plans for stud #33 for the Spring 2023 refueling outage and that no inspection is planned because of the prior relief authorization through 2025.
a) Please confirm outage-specific repair plans for stud #33 that are expected to be completed during the spring 2023 refueling outage for Hatch, Unit 2.
b) Please provide justification for SNCs request for NRC approval and LAR issuance by February 25, 2023, prior to completion of the Spring 2023 outage.
RAI-05
During the audit on December 14, 2022, the NRC asked about industry operating experience at boiling water reactors concerning stuck reactor vessel studs and removal success. The licensee discussed some known pressurized water reactor (PWR) examples and mentioned the precedents in its LAR submittal.
a) Please provide available industry operating experience for stuck RPV studs at other boiling water reactor (BWRs) and methods used to repair/replace such studs.
b) If applicable, please confirm that this is the first request for a BWR to change its design and licensing basis to allow operation with one or more reactor vessel studs less than fully tensioned.
RAI-06
Table 3 of DEI Calculation C-037-2201-00-02 for Hatch Unit 2, the Stud Condition column indicates Cases B1, C1, B2, and C2 are for one untensioned/failed stud, but the description of the cases in Section 5.2.3 of DEI Calculation C-037-2201-00-02 states the cases are for two untensioned studs separated by nine tensioned studs (Cases B1 and B2) and two studs that fail in service separated by nine tensioned studs (Cases C1 and C2).
Please clarify that the stud conditions that were analyzed in Table 3 of DEI Calculation C-037-2201-00-02 for Hatch Unit 2 were for two untensioned studs separated by nine tensioned studs for Cases B1 and B2 and two studs (separated by nine tensioned studs) that fail in service for Cases C1 and C2.
RAI-07
The NRC staff noted that the application did not discuss the impact of the proposed change to the Hatch TS Table 1.1-1 to have less than a full set of tensioned studs on the RPV threads-in-flange. Because these are the threads into which the studs are installed in the RPV flange, there could be a potential impact of the licensees proposed change on the RPV threads-in-flange.
The NRC staff noted that American Society of Mechanical EngineersSection XI Code Case (CC) N-864 may be used by licensees to forgo the inservice inspection (ISI) examination of the RPV threads-in-flange for a certain number of ISI intervals without the need for an alternative request, because the Code Case is conditionally approved in Regulatory Guide (RG) 1.147, Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1, Revision 20, which is incorporated by reference in 10 CFR 50.55a. The technical basis for CC N-864 is in EPRI Technical Report 3002007626, Nondestructive Evaluation: Reactor Pressure Vessel Threads in Flange Examination Requirements, March 2016 (ML16221A068). The analysis of the RPV threads-in-flange in the EPRI report assumes a full set of tensioned studs, and is, therefore, inconsistent with the proposed change to the Hatch TS Table 1.1-1 to have less than a full set of tensioned studs. Therefore, if the licensee is using CC N-864 or will use CC N-864 in its ISI program for the Hatch RPV threads-in-flange. Please discuss this apparent inconsistency.
a) Please state whether CC N-864 is used now or will be used in the future in the ISI program for the Hatch RPV threads-in-flange.
b) If CC N-864 is used now or will be used in the future in the ISI program, please show that the impact of the proposed change during preload conditions is bounded by the maximum applied stress intensity factor for the Preload case in Table 6-1 of the EPRI report.
Best Regards, Dawnmathews T. Kalathiveettil Hatch Project Manager Plant Licensing Branch (LPL 2-1)
DORL - O8 C02 Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office Phone: 301-415-5905 Email: Dawnmathews.Kalathiveettil@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 1869 Mail Envelope Properties (BY5PR09MB5666220797CE5A2611105A9797EB9)
Subject:
RAI - Hatch, Units 1 and 2, 'RPV Head Studs' LAR (EPID L-2022-LLA-0120)
Sent Date: 12/21/2022 12:30:59 PM Received Date: 12/21/2022 12:30:00 PM From: Dawnmathews Kalathiveettil Created By: Dawnmathews.Kalathiveettil@nrc.gov Recipients:
"Chamberlain, Amy Christine" <ACCHAMBE@southernco.com>
Tracking Status: None "Michael Markley" <Michael.Markley@nrc.gov>
Tracking Status: None "John Lamb" <John.Lamb@nrc.gov>
Tracking Status: None "Quarles, Adam Graham" <AGQUARLE@southernco.com>
Tracking Status: None Post Office: BY5PR09MB5666.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 10783 12/21/2022 12:30:00 PM Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: