Letter Sequence Acceptance Review |
---|
|
|
|
Similar Documents at Hatch |
---|
Category:E-Mail
MONTHYEARML24281A1362024-10-0707 October 2024 NRR E-mail Capture - (External_Sender) Acceptance Review - Hatchs Revise Technical Specifications to Adopt TSTF-591 LAR (L-2024-LLA-0122) ML24278A0052024-10-0303 October 2024 Document Request for Hatch Nuclear Plant - IP 92702 Follow-Up Radiation Protection Inspection - Inspection Report 2024-04 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24211A0162024-07-26026 July 2024 NRR E-mail Capture - Request for Additional Information - Hatch, Units 1 and 2, Revise TS SRs (3.4.3.1 & 3.1.7.7) to Increase SRV Setpoints LAR ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24193A1182024-07-10010 July 2024 Email to SNC with RAI for Hatch Exemption Request ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24142A4992024-05-21021 May 2024 NRR E-mail Capture - Acceptance Review - Farley and Hatch - LAR to Revise TS 1.1 and Add Online Monitoring (OLM) Program (L-2024-LLA-0058) ML24138A1582024-05-17017 May 2024 NRR E-mail Capture - (External_Sender) Acceptance Review - Hatchs Revise TS Surveillance Requirements to Increase SRV Setpoints LAR (L-2024-LLA-0054) ML24100A4402024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) RAI - Hatch, Units 1 and 2, Revise Technical Specifications to Adopt Extended RICTs for RHRSW and Psw Systems LAR ML24100A0072024-04-0808 April 2024 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML24082A1212024-03-21021 March 2024 NRR E-mail Capture - (External_Sender) Re Acceptance Review - Hatchs Adopt Alternative Seismic Method for 50.69 Categorization of SSCs LAR (L-2024-LLA-0017) ML24067A0702024-03-0707 March 2024 NRR E-mail Capture - Change in Estimated Review Completion for Hatch Revise TS Table 1.1-1 (Modes) LAR (L-2022-LLA-0120) ML24009A1112024-01-0909 January 2024 NRR E-mail Capture - Acceptance Review - Hatch 1&2 LAR - Revise TS 3.7.1 & 3.7.2 to Adopt Risk-Informed Completion Times for RHRSW and Psw Systems (L-2023-LLA-0169) ML23354A2032023-12-18018 December 2023 Document Request for Hatch Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-01 ML23264A0142023-09-14014 September 2023 NRR E-mail Capture - (External_Sender) Draft Round-2 RAI - Hatch, Units 1 and 2, Revise TS 1.1-1 Modes LAR ML23249A2082023-09-0606 September 2023 NRR E-mail Capture - Change in Estimated Review Schedule and Level of Effort for Hatch 'Revise TS Table 1.1-1 (Modes)' LAR (L-2022-LLA-0120) ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23135A0922023-05-11011 May 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Request to Use Specific Provision of a Later Edition of the ASME BPV Code, Section XI (L-2023-LLR-0016) ML23073A0252023-03-13013 March 2023 NRR E-mail Capture - Fyi - Closeout the Evacuation Time Estimate (ETE) Reviews for SNC Fleet ML23065A0922023-03-0505 March 2023 NRR E-mail Capture - Revised Estimate Hours and Completion Date - Hatch RPV Head Closure Bolts LAR (L-2022-LLA-0120) ML23033A0952023-02-0202 February 2023 NRR E-mail Capture - (External_Sender) Re for Your Comments - State of Georgia - Hatch Units 1 and 2 - Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML23033A0282023-01-30030 January 2023 NRR E-mail Capture - Revised Estimates for Hatch RPV Studs LAR ML23026A0132023-01-19019 January 2023 NRR E-mail Capture - Revised Estimates for Hatch RPV Studs LAR ML23018A1872023-01-17017 January 2023 2023 HNP CGD Inspection Information Request ML23006A0662023-01-0505 January 2023 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - Revise NFPA-805 License Amendment Request ML22355A2082022-12-21021 December 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, Reactor Pressure Vessel 'Rpv Head Studs' LAR ML23006A0252022-12-13013 December 2022 NRR E-mail Capture - (External_Sender) for Your Comments - State of Georgia - Hatch Units 1 and 2 - TSTF-208 License Amendment Request ML22341A1212022-12-0606 December 2022 NRR E-mail Capture - Recap of Takeaways from Hatch Audit on Dec 1, 2022 ML23026A2372022-11-16016 November 2022 2023001 Hatch RP RFI Final ML22305A7032022-11-0101 November 2022 NRR E-mail Capture - Potential Audit for Hatch'S 'Rpv Head Studs' LAR ML22258A1532022-09-15015 September 2022 NRR E-mail Capture - Acceptance Review - Hatch Closure Studs in TS Table 1.1-1 Modes LAR (L-2022-LLA-0120) ML22251A1322022-09-0808 September 2022 NRR E-mail Capture - Fyi - Hatch TSTF-505 LAR ML22208A1332022-07-26026 July 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-208 LAR ML22207B8532022-07-25025 July 2022 NRR E-mail Capture - RCI - Hatch, Units 1 and 2, Revision to NFPA-805 LAR ML22157A3542022-06-0606 June 2022 NRR E-mail Capture - RAI - Hatch, Units 1 and 2, TSTF-505 LAR ML22157A3552022-06-0606 June 2022 NRR E-mail Capture - Revised Estimates - Hatch TSTF-505 LAR ML22140A1192022-05-20020 May 2022 NRR E-mail Capture - RAIs - Hatch, Units 1 and 2, TSTF-505 LAR ML22138A4122022-05-18018 May 2022 NRR E-mail Capture - Acceptance Review - Hatch TSTF-208 LAR (L-2022-LLA-0045) ML22140A1182022-05-13013 May 2022 NRR E-mail Capture - for Your Action: Hatch TSTF-505 - Follow Up from Audit Question 12 ML22116A1492022-04-26026 April 2022 NRR E-mail Capture - Acceptance Review - Hatch Revise NFPA 805 LAR (L-2022-LLF-0000) ML22055A6652022-02-24024 February 2022 NRR E-mail Capture - Acceptance Review - Hatch TSTF-580 LAR (L-2022-LLA-0022) ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21357A0912021-12-23023 December 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-207-A LAR (L-2021-LLA-0219) ML21354A5942021-12-20020 December 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-227 and TSTF-297 LAR (L-2021-LLA-0227) ML21347A9002021-12-13013 December 2021 NRR E-mail Capture - Updated Request: Additional Request for SNC to Place Document on the Portal ML21347A8532021-12-13013 December 2021 NRR E-mail Capture - Required: Hatch TSTF-505 LAR - Audit Plan - Additional Documents to Be Uploaded to the Portal ML21363A0872021-12-0606 December 2021 NRR E-mail Capture - (External_Sender) Question - Hatch - Eliminate Automatic Main Steam Line Isolation on High Turbine Building Area Temperature (L-2021-LLA-0188) ML21321A3812021-11-16016 November 2021 NRR E-mail Capture - Acceptance Review - Hatch TSTF-505 LAR (L-2021-LLA-0199) 2024-09-04
[Table view] |
Text
From: Kalathiveettil, Dawnmathews Sent: Thursday, February 24, 2022 1:51 PM To: Enfinger, Timothy Lee Cc: Joyce, Ryan M.; Markley, Michael; Lamb, John
Subject:
Acceptance Review - Hatch TSTF-580 LAR (L-2022-LLA-0022)
Good Evening Tim, By letter dated February 04, 2022 (ML22038A205), Southern Nuclear Operating Company (SNC, the licensee) submitted a license amendment request (LAR) for Edwin I. Hatch Nuclear Plant, Units 1 and 2. The proposed LAR revise technical specification (TS) to adopt TSTF-580, "Provide Exception from Entering Mode 4 With No Operable RHR Shutdown Cooling." The proposed change provides a TS exception to entering Mode 4 if both required Residual Heat Removal (RHR) shutdown cooling subsystems are inoperable.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license including the technical specifications must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your LAR and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> to complete. The NRC staff expects to complete this review on October 24, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
Best Regards, Dawnmathews T. Kalathiveettil Project Manager Plant Licensing Branch (LPL 2-1)
Division of Operating Reactor Licensing - O8 C02 Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Office Phone: 301-415-5905 Email: Dawnmathews.Kalathiveettil@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 1536 Mail Envelope Properties (BY5PR09MB566685CE599079CF357D515D973D9)
Subject:
Acceptance Review - Hatch TSTF-580 LAR (L-2022-LLA-0022)
Sent Date: 2/24/2022 1:51:05 PM Received Date: 2/24/2022 1:51:00 PM From: Kalathiveettil, Dawnmathews Created By: Dawnmathews.Kalathiveettil@nrc.gov Recipients:
"Joyce, Ryan M." <RMJOYCE@southernco.com>
Tracking Status: None "Markley, Michael" <Michael.Markley@nrc.gov>
Tracking Status: None "Lamb, John" <John.Lamb@nrc.gov>
Tracking Status: None "Enfinger, Timothy Lee" <TLENFING@SOUTHERNCO.COM>
Tracking Status: None Post Office: BY5PR09MB5666.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3757 2/24/2022 1:51:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: