Category:Inspection Plan
MONTHYEARML24234A0102024-08-18018 August 2024 BWXT - Document Request - Plant Modifications Triennial - September 2024 ML24134A0262024-05-0909 May 2024 Document Request for Upcoming EP - FP Inspection ML23256A0092023-09-14014 September 2023 BWXT Nuclear Operations Group, Inc. Lynchburg Inspection Schedule for Calendar Year 2024 ML23115A1042023-04-18018 April 2023 Final- NRC Doc Request - BWXT IR 2023-002 - (Public) ML21314A4202021-11-10010 November 2021 NRC Document Request - BWXT RP-ENV - 2021004 ML21335A0292021-10-12012 October 2021 BWXT 2021-004 OPS Inspection Document Request ML20189A2622020-07-0202 July 2020 BWXT Nuclear Operations Group - Calendar Year 2021 Inspection Schedule Letter 2024-08-18
[Table view] Category:Letter
MONTHYEARML24281A1382024-10-0707 October 2024 BWXT Mca IR 2024405 Public Cover Letter ML24233A2702024-09-10010 September 2024 Cover Letter: Return of Argonaut Insurance Company Surety Bond ML24236A7672024-08-26026 August 2024 BWXT Nuclear Operations Group - Lynchburg - Physical Security Core Inspection Report 07000027-2024403 ML24234A0592024-08-16016 August 2024 BWXT Nuclear Operations Group, Inc., Semi-Annual Effluent Monitoring Report ML24205A0802024-07-24024 July 2024 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2024002 ML24179A1982024-06-27027 June 2024 BWXT Nuclear Operations Group, Inc. - Lynchburg Inspection Schedule for Calendar Year 2025 ML24151A4602024-06-20020 June 2024 BWXT Nuclear Operations Group, Inc. – NRC Core Inspection Report 07000027/2024006 and Apparent Violation ML24135A0762024-05-0101 May 2024 BWXT Nuclear Operations Group, Inc. - Lynchburg - Decommissioning Surety Bond ML24116A2842024-04-26026 April 2024 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027-2024001 ML24060A2822024-04-18018 April 2024 Cover Letter BWXT Amendment 47 (Public) ML24089A1862024-03-29029 March 2024 BWXT Nuclear Generating Group, Inc. - Material Control and Accounting Program Inspection Report 07000027/2024404 - Public ML24064A2142024-03-0404 March 2024 BWXT Nuclear Operations Group- Lynchburg - Physical Security Core Inspection Report 07000027/2024402 - Public Cover Letter ML24065A0142024-02-29029 February 2024 Response to Request for Additional Information Regarding Submittal for Exemption from Implementation of Security Event Notification and Suspicious Activity Reporting ML24064A0352024-02-27027 February 2024 BWXT Nuclear Operations Group- Lynchburg, Inc., Submittal of Fitness for Duty Program Annual Data Report for 2023 ML24061A0222024-02-27027 February 2024 BWXT Nuclear Operations Group, Inc., Lynchburg - Semi-Annual Effluent Monitoring Report ML24036A2482024-02-0808 February 2024 Request for Additional Information from BWXT NOG-L Regarding Submittal for Security Exemption-Enterprise Project Identifier L-2023-SPR-0013 ML24024A1502024-01-25025 January 2024 BWXT Nuclear Operations Group, Inc. – Integrated Inspection Report 07000027/2023004 ML24019A1492024-01-24024 January 2024 BWXT Nuclear Operations Group, Inc. -Lynchburg, U.S. NRC Inspection Report 0700027/2022006 and Notice of Violation ML24016A1912024-01-17017 January 2024 TRISO-X - U.S. Nuclear Regulatory Commission Inspection Report 07007027/2023006 ML23325A0382023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg, Request for Exemption from Security Event Notification and Suspicious Activity Reporting Implementation in Accordance with 10 CFR 73.5 ML23325A0402023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc - Lynchburg'S (BWXT NOG-L) - 30 Day Written Report of Event Notification EN-56768 ML23292A1252023-10-25025 October 2023 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2023003 ML23269A0242023-09-26026 September 2023 BWXT Nuclear Operations Group, Inc. - Material Control and Accounting Program Inspection Report 07000027/2023402 (Cover Letter) ML23253A0012023-09-15015 September 2023 BWXT NOG-L - Physical Security Core Inspection Report 07000027/2023405 - Cover ML23256A0092023-09-14014 September 2023 BWXT Nuclear Operations Group, Inc. Lynchburg Inspection Schedule for Calendar Year 2024 ML23257A2052023-09-0606 September 2023 Bwx Technologies, Inc. Submittal of Revision 1 to Chapter 1, General Information and Chapter 2, Organization & Administration, of License SNM-42 License Application - Redacted Cover Letter ML23248A3072023-09-0505 September 2023 Lynchburg Technology Center - Physical Security Core Inspection Report 07000027/2023406 ML23243A8582023-09-0101 September 2023 License Amendment 46 Approval of Physical Protection Plan, Revision 27 (Enterprise Project Identifier L-2023-SPR-0000) ML23241A0432023-08-24024 August 2023 Bwx Technologies, Inc., Semi-Annual Effluent Monitoring Report for First Half of 2023 ML23209A8272023-08-24024 August 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg - Notice of Violation and Proposed Imposition of Civil Penalty - $87,500; NRC Inspection Report No. 07000027/2023007 ML23171A9282023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Emergency Plan, Revision 36 ML23171A9302023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Mt. Athos Site Emergency Plan, Revision 36 ML23115A0202023-05-0505 May 2023 BWXT Nuclear Operations Group, Inc., - Lynchburg - NRC Inspection Report 07000027/2023006 and Apparent Violations ML23116A0862023-04-27027 April 2023 BWXT Nuclear Operations Group, Inc. Integrated Inspection Report 07000027/2023001 ML23108A3262023-04-25025 April 2023 Cover Letter - BWXT Amendment 45 ML23100A0532023-04-0606 April 2023 BWXT Nuclear Operations Group - Lynchburg - Physical Security Core Inspection Report 07000027 2023403 Cover Letter ML23212A9182023-04-0404 April 2023 BWXT EN 56336 60 Day Report_Redacted ML23096A2252023-04-0404 April 2023 BWXT Nuclear Operations Group, Inc., Submittal of 60-Day Written Report for Event Notification Number EN-56336 ML23089A3842023-03-31031 March 2023 BWXT Nuclear Operations Group, Inc - Material Control and Accounting Program Inspection Report 07000027/2023401 ML23060A1122023-03-0606 March 2023 BWXT Nuclear Operations Group, Inc. - Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 07000027/2023005) ML23059A2802023-02-23023 February 2023 BWXT Nuclear Operations Group, Inc. Submittal of Lynchburg Facility Semi-Annual Effluent Report for 2022 ML23046A0872023-02-0909 February 2023 BWXT Nuclear Operations Group- Lynchburg, Inc., Fatigue Management Program Annual Data Report ML23025A0912023-01-30030 January 2023 BWXT Nuclear Operations Group, Inc. Integrated Inspection Report 07000027/2022004 ML22341A2132022-12-15015 December 2022 Letter - BWXT Amendment 44 ML22340A5982022-11-30030 November 2022 11-30-2022 Letter from BWXT NOG-L: Request to Amend License SNM-42 in Accordance with the Revised Fundamental Nuclear Material Control Plan (FNMCP) ML22318A2632022-11-14014 November 2022 BWXT-NOG L Physical Security Core Inspection Report 07000027/2022405 (Cover Letter) ML22297A1342022-10-27027 October 2022 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2022003 ML22297A2082022-10-25025 October 2022 BWXT Nuclear Operations Group - Lynchburg Material Control and Accounting Program Inspection Report 07000027 2022403 Cover Letter ML23075A1782022-10-0505 October 2022 22-061 BWXT Information to Be Withheld from the Pec, Submitted Under 10 CFR 2..390(b)(1) Letter Unsecured for ADAMS Redacted (Dated - 10-5-2022) ML22263A0442022-09-15015 September 2022 BWXT Nuclear Operations Group, Inc., Emergency Plan Revision 35 2024-09-10
[Table view] Category:Schedule and Calendars
MONTHYEARML24179A1982024-06-27027 June 2024 BWXT Nuclear Operations Group, Inc. - Lynchburg Inspection Schedule for Calendar Year 2025 ML22187A1872022-07-0606 July 2022 BWXT Nuclear Operations Group, Inc., Lynchburg - Inspection Schedule for Calendar Year 2023 ML21174A0272021-06-23023 June 2021 BWXT Nuclear Operations Group, Inc. - Calendar Year 2022 Inspection Schedule ML20189A2622020-07-0202 July 2020 BWXT Nuclear Operations Group - Calendar Year 2021 Inspection Schedule Letter 2024-06-27
[Table view] |
Text
July 2, 2020 Mr. B. Joel Burch Vice President and General Manager BWXT Nuclear Operations Group, Inc.
P.O. Box 785 Lynchburg, VA 24505-0785
SUBJECT:
BWXT NUCLEAR OPERATIONS GROUP - CALENDAR YEAR 2021 INSPECTION SCHEDULE
Dear Mr. Burch:
Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the BWXT Nuclear Operations Group, Inc. (NOG) facility for calendar year 2021. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.
Please note that any regional initiative or other reactive inspection is not included in the schedule. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Noel Pitoniak at (404) 997-4634 with any questions or concerns you may have regarding this letter or the inspection schedule.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).
B. Burch 2 ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Suzanne K. Dennis, Acting Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 70-27 License No. SNM-42
Enclosure:
BWXT Nuclear Operations Group - Calendar Year 2021 Inspection Schedule (See page 2) cc: w/ encl: Distribution via LISTSERV
ML20189A262 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DFFI RII:DFFI NAME N. Pitoniak S. Dennis DATE 07/2/2020 07/6/2020 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO BWXT NUCLEAR OPERATIONS GROUP -
CALENDAR YEAR 2021 INSPECTION SCHEDULE NCS1 Dates January 25 - 29, 2021 Number of Inspectors 2 Inspection Procedure (IP) 88015 - Nuclear Criticality Safety MC&A1 Dates February 1 - 5, 2021 Number of Inspectors 2 85207, 85209, 85211, 85303, 85305, 85307, 85309, Inspection Procedures (IPs) 85311, 85313, 85315, 85407, 85408 PHYSEC (HQ FOF)
February 22 - 26, 2021 Dates March 22 - 26, 2021 Number of Inspectors TBD Inspection Procedure (IP) 96001 OPS1 Dates April 19 - 23, 2021 Number of Inspectors 2 Inspection Procedure (IP) 88020 - Operational Safety PHYSEC Dates May 17 - 21, 2021 Number of Inspectors 1 Inspection Procedures (IPs) 81700.08, 81820 PHYSEC Dates July 12, 2021 to July 16, 2021 Number of Inspectors 2 Inspection Procedure (IP) 81700.02 MC&A2 Dates July 19 - 23, 2021 Number of Inspectors 2 85207, 85209, 85211, 85303, 85305, 85307, 85309, Inspection Procedures (IPs) 85311, 85313, 85315, 85407, 85408 Enclosure
NCS2 Dates July 26 - 30, 2021 Number of Inspectors 2 Inspection Procedure (IP) 88015 - Nuclear Criticality Safety PMT Dates September 20 - 24, 2021 Number of Inspectors 3 Inspection Procedure (IP) 88072 - Permanent Plant Modifications (Triennial)
PHYSEC Dates October 18 - 22, 2021 Number of Inspectors 2 Inspection Procedure (IP) 81700.04 EPX Dates October 25 - 29, 2021 (Placeholder)
Number of Inspectors 3 Inspection Procedure (IP) 88051 - Emergency Preparedness Exercise OPS2 Dates November 1 - 5, 2021 Number of Inspectors 2 Inspection Procedure (IP) 88020 - Operational Safety ENV/RP Dates December 6 - 10, 2021 Number of Inspectors 2 88030 - Radiation Protection Inspection Procedure (IP) 88045 - Effluent Control and Environmental Protection 2