MONTHYEARML23125A2362023-05-0404 May 2023 05-04-2023 Email: Acceptance of Request to Amend License SNM-42 in Accordance with the Revised Physical Protection Plan - Enterprise Project Identifier L-2023-SPR-0000 Project stage: Acceptance Review ML23163A1242023-06-0606 June 2023 06-06-2023 Email: Request for Additional Information Proposed Changes to BWXT NOG-L Physical Protection Plan - EPID L-2023-SPR-0000 Project stage: RAI ML23243A8592023-09-0101 September 2023 Enclosure 1 - Amendment 46 to Materials License SNM-42 Project stage: Other ML23243A8582023-09-0101 September 2023 License Amendment 46 Approval of Physical Protection Plan, Revision 27 (Enterprise Project Identifier L-2023-SPR-0000) Project stage: Approval 2023-06-06
[Table View] |
|
---|
Category:Letter
MONTHYEARML24024A1502024-01-25025 January 2024 BWXT Nuclear Operations Group, Inc. Integrated Inspection Report 07000027/2023004 ML24019A1492024-01-24024 January 2024 BWXT Nuclear Operations Group, Inc. -Lynchburg, U.S. NRC Inspection Report 0700027/2022006 and Notice of Violation ML24016A1912024-01-17017 January 2024 TRISO-X - U.S. Nuclear Regulatory Commission Inspection Report 07007027/2023006 ML23325A0402023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc - Lynchburg'S (BWXT NOG-L) - 30 Day Written Report of Event Notification EN-56768 ML23325A0382023-11-16016 November 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg, Request for Exemption from Security Event Notification and Suspicious Activity Reporting Implementation in Accordance with 10 CFR 73.5 ML23292A1252023-10-25025 October 2023 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2023003 ML23269A0242023-09-26026 September 2023 BWXT Nuclear Operations Group, Inc. - Material Control and Accounting Program Inspection Report 07000027/2023402 (Cover Letter) ML23253A0012023-09-15015 September 2023 BWXT NOG-L - Physical Security Core Inspection Report 07000027/2023405 - Cover ML23256A0092023-09-14014 September 2023 BWXT Nuclear Operations Group, Inc. Lynchburg Inspection Schedule for Calendar Year 2024 ML23257A2052023-09-0606 September 2023 Bwx Technologies, Inc. Submittal of Revision 1 to Chapter 1, General Information and Chapter 2, Organization & Administration, of License SNM-42 License Application - Redacted Cover Letter ML23248A3072023-09-0505 September 2023 Lynchburg Technology Center - Physical Security Core Inspection Report 07000027/2023406 ML23243A8582023-09-0101 September 2023 License Amendment 46 Approval of Physical Protection Plan, Revision 27 (Enterprise Project Identifier L-2023-SPR-0000) ML23209A8272023-08-24024 August 2023 BWXT Nuclear Operations Group, Inc. - Lynchburg - Notice of Violation and Proposed Imposition of Civil Penalty - $87,500; NRC Inspection Report No. 07000027/2023007 ML23241A0432023-08-24024 August 2023 Bwx Technologies, Inc., Semi-Annual Effluent Monitoring Report for First Half of 2023 ML23171A9282023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Emergency Plan, Revision 36 ML23171A9302023-06-12012 June 2023 BWXT Nuclear Operations Group, Inc., Submittal of Mt. Athos Site Emergency Plan, Revision 36 ML23115A0202023-05-0505 May 2023 BWXT Nuclear Operations Group, Inc., - Lynchburg - NRC Inspection Report 07000027/2023006 and Apparent Violations ML23116A0862023-04-27027 April 2023 BWXT Nuclear Operations Group, Inc. Integrated Inspection Report 07000027/2023001 ML23108A3262023-04-25025 April 2023 Cover Letter - BWXT Amendment 45 ML23100A0532023-04-0606 April 2023 BWXT Nuclear Operations Group - Lynchburg - Physical Security Core Inspection Report 07000027 2023403 Cover Letter ML23096A2252023-04-0404 April 2023 BWXT Nuclear Operations Group, Inc., Submittal of 60-Day Written Report for Event Notification Number EN-56336 ML23212A9182023-04-0404 April 2023 BWXT EN 56336 60 Day Report_Redacted ML23089A3842023-03-31031 March 2023 BWXT Nuclear Operations Group, Inc - Material Control and Accounting Program Inspection Report 07000027/2023401 ML23060A1122023-03-0606 March 2023 BWXT Nuclear Operations Group, Inc. - Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 07000027/2023005) ML23059A2802023-02-23023 February 2023 BWXT Nuclear Operations Group, Inc. Submittal of Lynchburg Facility Semi-Annual Effluent Report for 2022 ML23046A0872023-02-0909 February 2023 BWXT Nuclear Operations Group- Lynchburg, Inc., Fatigue Management Program Annual Data Report ML23025A0912023-01-30030 January 2023 BWXT Nuclear Operations Group, Inc. Integrated Inspection Report 07000027/2022004 ML22341A2132022-12-15015 December 2022 Letter - BWXT Amendment 44 ML22340A5982022-11-30030 November 2022 11-30-2022 Letter from BWXT NOG-L: Request to Amend License SNM-42 in Accordance with the Revised Fundamental Nuclear Material Control Plan (FNMCP) ML22318A2632022-11-14014 November 2022 BWXT-NOG L Physical Security Core Inspection Report 07000027/2022405 (Cover Letter) ML22297A1342022-10-27027 October 2022 BWXT Nuclear Operations Group, Inc. - Integrated Inspection Report 07000027/2022003 ML22297A2082022-10-25025 October 2022 BWXT Nuclear Operations Group - Lynchburg Material Control and Accounting Program Inspection Report 07000027 2022403 Cover Letter ML23075A1782022-10-0505 October 2022 22-061 BWXT Information to Be Withheld from the Pec, Submitted Under 10 CFR 2..390(b)(1) Letter Unsecured for ADAMS Redacted (Dated - 10-5-2022) ML22263A0442022-09-15015 September 2022 BWXT Nuclear Operations Group, Inc., Emergency Plan Revision 35 ML23075A1642022-09-0101 September 2022 BWXT Technologies Request for Closed Predecisional Enforcement Conference (Dated 9-1-2022) Unsecured for ADAMS ML22235A7222022-08-18018 August 2022 BWXT Nuclear Operations Group, Inc. - Lynchburg, Semi-Annual Effluent Monitoring Report ML22224A1782022-08-0505 August 2022 BWXT Nuclear Operations Group, Inc. - Lynchburg, Updated Financial Assurance Documents, Certification of Financial Assurance and Revised SNM-42 License Application, Chapter 10, Decommissioning ML22207B2302022-07-26026 July 2022 BWXT Nuclear Operations Group, Inc. - Lynchburg - Integrated Inspection Report 07000027/2022002 ML22153A5122022-07-12012 July 2022 BWXT Nuclear Operation Group, Inc. - Interim Approval of Chapter 10, Decommissioning (Enterprise Project Identifier L-2021-DFA-0010) ML22187A1872022-07-0606 July 2022 BWXT Nuclear Operations Group, Inc., Lynchburg - Inspection Schedule for Calendar Year 2023 ML22182A4832022-06-24024 June 2022 BWXT Nuclear Operations Group, Inc., Response to Request for Additional Information - Decommissioning Cost Updates ML22123A0502022-06-0606 June 2022 BWXT Nuclear Operations Group, Inc. - Lynchburg NRC Inspection Report No. 07000027/2021006 and Apparent Violations ML22151A0272022-05-18018 May 2022 BWXT Nog 60-Day Written Report Per 10 CFR 71.95(c) ML22143A8942022-05-18018 May 2022 Bwx Technologies, Inc., 60-Day Written Report - 16 CFR 71.~5(c) 2024-01-25
[Table view] |
Text
OFFICIAL USE ONLY SECURITY - RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 1, 2023 Daniel Ashworth, Manager Licensing and Safety Analysis BWXT Nuclear Operations Group, Inc.
P.O. Box 785 Lynchburg, VA 24505-0785
SUBJECT:
LICENSE AMENDMENT 46 - APPROVAL OF PHYSICAL PROTECTION PLAN, REVISION 27 (ENTERPRISE PROJECT IDENTIFIER L-2023-SPR-0000)
Dear Daniel Ashworth:
This refers to letter 23015, dated March 28, 2023 (not publicly available due to security-related information in the cover letter and classified information in the enclosure), in which BWXT Nuclear Operations Group, Inc. - Lynchburg, Inc. (BWXT NOG-L) submitted proposed changes to the Physical Protection Plan (PPP). The enclosure to the letter provided descriptions and justifications for the proposed PPP changes. BWXT NOG-L stated in the letter that a copy of the updated PPP (Revision 27) will be transmitted to the U.S. Nuclear Regulatory Commission (NRC), following the review and approval of the PPP changes by the NRC.
By correspondence dated June 6, 2023 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML23163A124), the NRC provided a Request for Additional Information (RAI) to BWXT NOG-L. By letter 23-41, dated June 27, 2023 (not publicly available due to security-related information in the cover letter and classified information in the enclosure), BWXT NOG-L responded to the NRC staffs RAI and revised the proposed changes to the PPP.
The NRC staff has completed its review of the request. The NRC has determined that the proposed changes to the PPP are acceptable, and issuance of this license amendment will not significantly impact the public health and safety and the environment, will not be inimical to the common defense and security, and will not endanger life or property or the common defense and security.
Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Sections 70.32(e) and 70.34, Safeguards Condition SG-6.1 of Materials License SNM-42 is hereby amended to reference Revision 27 of the PPP, submitted as Revision 27 by letter dated March 28, 2023, as revised by letter dated June 27, 2023.
The letter transmitted contains Security-Related Information. When separated from Enclosures 2 & 3, this letter is decontrolled.
OFFICIAL USE ONLY SECURITY - RELATED INFORMATION
OFFICIAL USE ONLY SECURITY - RELATED INFORMATION D. Ashworth 2 All other license conditions shall remain the same. Enclosures 1 and 2 to this letter provide the amended Materials License SNM-42. The NRC staffs review is documented in a Safeguards Evaluation Report, which is Enclosure 3 to this letter. This letter concludes action on this submittal, and Enterprise Project Identifier L-2023-SPR-0000 is considered CLOSED.
Enclosures 2 and 3 contain sensitive security-related information. Accordingly, they are marked as Official Use Only, and are withheld from public disclosure. When separated from the sensitive enclosures, this letter and Enclosure 1 are decontrolled and publicly available, in accordance with 10 CFR 2.390 of the NRCs "Agency Rules of Practice and Procedure."
In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter and Enclosure 1 will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. The ADAMS database is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737 between 8:00 a.m. and 4:00 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
If you have any questions regarding this matter, please contact James Downs of my staff at 301-415-7744, or via email to: James.Downs@nrc.gov.
Sincerely, Signed by Lav, Samantha on 09/01/23 Samantha C. Lav, Chief Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-27 License No. SNM-42
Enclosures:
- 1. Amendment 46 to Materials License SNM-42
- 2. Amendment 46 to Materials License SNM-42 (Non-Public)
- 3. Safeguards Evaluation Report (Non-Public) cc: bwxt@listmgr.nrc.gov OFFICIAL USE ONLY SECURITY - RELATED INFORMATION
ML23243A857 (Pkg.), ML23243A858 (Ltr.)
ML23243A859 (Encl. 1), ML23243A860 (Encl. 2), ML23243A857 (Encl. 3)
NMSS/DFM/
OFFICE NMSS/DFM/FFLB/PM NMSS/DFM/FFLB/LA FFLB/BC NAME JDowns JGoodridge SLav DATE 08/31/2023 09/01/2023 09/01/2023