Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARTSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program Project stage: Request ML22181A7442022-06-30030 June 2022 Acceptance for Review Regarding Traveler TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program Project stage: Acceptance Review ML22235A7382022-08-19019 August 2022 NRR E-mail Capture - Draft RAIs for TSTF-591 (L-2022-PMP-0003) Project stage: Draft RAI ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: RAI ML23153A1442023-09-11011 September 2023 Draft SE of Traveler TSTF-591, Revise Risk-Informed Completion Time (RICT) Program Project stage: Draft Approval ML23262B2302023-09-21021 September 2023 Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program Project stage: Approval ML23262B2292023-09-21021 September 2023 Cover Letter Transmitting Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program Project stage: Approval ML23325A2182023-09-21021 September 2023, 18 December 2023 Final Model SE of TSTF-591 Project stage: Request ML23325A2142023-12-18018 December 2023 Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: Other ML23325A2132023-12-18018 December 2023 Cover Letter for Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: Other 2022-08-19
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML23205A2142023-08-10010 August 2023 Acceptance for Review Regarding Traveler TSTF-596, Revision 0, Expand the Applicability of the Surveillance Frequency Control Program (SFCP) ML23157A2062023-07-0505 July 2023 Acceptance for Review and Revised Schedule Regarding Traveler TSTF-576, Revise Safety/Relief Valve Requirements ML23145A2822023-06-0202 June 2023 Acceptance for Review Regarding Traveler TSTF-585, Provide an Alternative to the LCO 3.0.3 One Hour Preparation Time ML22256A2122022-09-28028 September 2022 Acceptance for Review Regarding Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22181A7442022-06-30030 June 2022 Acceptance for Review Regarding Traveler TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation ML22062B3362022-03-0808 March 2022 Acceptance Review of Traveler TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML20037A1292020-02-13013 February 2020 Acceptance for Review Regarding Traveler TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19211D1192019-08-22022 August 2019 Acceptance Review for Traveler TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19211D2842019-08-20020 August 2019 Acceptance Review for Traveler TSTF-554, Revise Reactor Coolant Leakage Requirements ML18057A1622018-03-26026 March 2018 Acceptance for Review Regarding Traveler TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, ML18057A1602018-03-26026 March 2018 Acceptance for Review Regarding Traveler TSTF-569, Revise Response Time Testing Definition, ML18057A1632018-03-0808 March 2018 Acceptance for Review Regarding Traveler TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML18057A1592018-03-0808 March 2018 Acceptance for Review Regarding Traveler TSTF-557, Spent Fuel Storage Rack Neutron Absorber Monitoring Program ML17325B6722017-11-28028 November 2017 Acceptance for Review Regarding Traveler TSTF-564, Safety Limit MCPR ML17236A1352017-08-29029 August 2017 Acceptance for Review Regarding Traveler TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases ML16194A0102016-08-11011 August 2016 Acceptance for Review Regarding Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement ML14223A7822014-08-14014 August 2014 Acceptance for Review Regarding Traveler TSTF-547, Revision 0, Clarification of Rod Position Requirements ML12163A1592012-06-13013 June 2012 TSTF-454, Extend PCIV Completion Times (NEDC-33046), Acceptance Letter ML12158A5472012-06-13013 June 2012 TSTF-523 Acceptance Letter and RAIs ML1128007042011-10-19019 October 2011 Acceptance for Review of Traveler TSTF-535, Revision 0, Revise Shutdown Margin Definition to Address Advanced Fuel Designs ML1111703472011-05-0606 May 2011 Acceptance for Review of Traveler TSTF-490, Revision 1, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML0827504932008-10-0707 October 2008 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML0715600542007-06-0707 June 2007 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 425, Revision 1, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5. 2023-08-10
[Table view] |
Text
June 30, 2022 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
ACCEPTANCE FOR REVIEW REGARDING TRAVELER TSTF-591, REVISION 0, "REVISE RISK INFORMED COMPLETION TIME (RICT)
PROGRAM" (EPID L-2022-PMP-0003)
Dear Members of the Technical Specifications Task Force:
By letter dated March 22, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22081A224), you submitted a request to the U.S. Nuclear Regulatory Commission (NRC) to incorporate Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program, into the standard technical specifications.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that Travelers are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours have been billed accordingly. The NRC staff estimates that the review will require approximately 350 staff hours including project management time.
The NRC staff has completed a preliminary review of your submission and determined it is sufficiently complete and appropriate to initiate a more comprehensive review. The review will generally follow the schedule below.
MILESTONE SCHEDULE DATE Issue Request for Additional Information August 10, 2022 Issue Draft Safety Evaluation January 6, 2023 Issue Final Safety Evaluation March 22, 2023 If you have any questions, please contact me at (301) 415-1774 or via e-mail to Michelle.Honcharik@nrc.gov.
Sincerely, Digitally signed by Michelle C. Michelle C. Honcharik Date: 2022.06.30 Honcharik 16:21:55 -04'00' Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation Project No. 753 cc: See next page
Technical Specifications Task Force Project No. 753 cc:
Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E-mail: brian.mann@excelservices.com Drew Richards STP Nuclear Operating Company 12090 FM 521 Mail Code: N5016 Wadsworth, TX 77483 Email: amrichards@stpegs.com Kevin Lueshen Constellation Energy Generation 4300 Winfield Road Warrenville IL 60555 Email: kevin.lueshen@constellation.com Jordan L. Vaughan Duke Energy EC07C / P.O. Box 1006 Charlotte, NC 28202 Email: jordan.vaughan@duke-energy.com Ryan M. Joyce Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-274-EC Birmingham, AL 35243 Email: rmjoyce@southernco.com Wesley Sparkman Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-226-EC Birmingham, AL 35242 Email: wasparkm@southernco.com
ML22181A744 *via e-mail NRR-106 OFFICE NRR/DSS/STSB/BC* NRR/DSS/STSB/PM*
NAME VCusumano MHoncharik DATE 6/30/2022 6/30/2022