TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program

From kanterella
(Redirected from ML22081A224)
Jump to navigation Jump to search

Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program
ML22081A224
Person / Time
Site: Technical Specifications Task Force
Issue date: 03/22/2022
From: Joyce R, Lueshen K, Richards A, Sparkman W, Vaughan J
Technical Specifications Task Force
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
TSTF-22-04 TSTF-591
Download: ML22081A224 (45)


Text

TECHNICAL SPECIFICATIONS TASK FORCE TSTF A JOINT OWNERS GROUP ACTIVITY March 22, 2022 TSTF-22-04 PROJ0753 Attn: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Transmittal of TSTF-591, Revision 0, "Revise Risk Informed Completion Time (RICT) Program" Enclosed for NRC review is TSTF-591, Revision 0, "Revise Risk Informed Completion Time (RICT) Program."

The following information is provided to assist the NRC staff in prioritizing their review of TSTF-591:

  • Applicability: TSTF-591 is applicable to all Pressurized Water Reactor and Boiling Water Reactor plants that have adopted TSTF-505, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b."
  • Classification: TSTF-591 revises the Risk Informed Completion Time Program," to reference Regulatory Guide (RG) 1.200, Revision 3, instead of Revision 2, and to make other changes.
  • Specialized Resource Availability: TSTF-591 is a high priority change. The TSTF requests that TSTF-591 be reviewed within 12 months and be made available for adoption under the Consolidated Line Item Improvement Process (CLIIP).

The Technical Specifications Task Force should be billed for the review of the traveler.

Should you have any questions, please do not hesitate to contact us.

Andrew M. Richards, Jr. (PWROG/W) Ryan M. Joyce (BWROG)

Kevin Lueshen (PWROG/CE) Jordan L. Vaughan (PWROG/B&W)

Wesley A. Sparkman (PWROG/AP1000) cc: Michelle Honcharik, Technical Specifications Branch Victor Cusumano, Technical Specifications Branch 11921 Rockville Pike, Suite 100, Rockville, MD 20852 Phone: 804-339-7034 Administration by EXCEL Services Corporation

PWROG-12, Rev. 0 TSTF-591, Rev. 0 Technical Specifications Task Force Improved Standard Technical Specifications Change Traveler Revise Risk Informed Completion Time (RICT) Program NUREGs Affected: 1430 1431 1432 1433 1434 2194 Classification: 1) Technical Change Recommended for CLIIP?: Yes Correction or Improvement: Improvement NRC Fee Status: Not Exempt Benefit: Prevents Unnecessary Actions Changes Marked on ISTS Rev 5.0 PWROG RISD & PA (if applicable): PA-LSC-1922 See attached.

Revision History OG Revision 0 Revision Status: Active Revision Proposed by: TSTF Revision

Description:

Original Issue Owners Group Review Information Date Originated by OG: 07-Oct-21 Owners Group Comments (No Comments)

Owners Group Resolution: Approved Date: 22-Oct-21 TSTF Review Information TSTF Received Date: 07-Mar-22 Date Distributed for Review 07-Mar-22 TSTF Comments:

(No Comments)

TSTF Resolution: Approved Date: 22-Mar-22 NRC Review Information NRC Received Date: 22-Mar-22 NRC Comments:

The TSTF provided a draft of TSTF-591 to the NRC in November 2021, and the NRC and TSTF held a teleconference on January 26, 2022, to discuss the draft. The NRC had three comments:

1. The NRC was concerned that the term "approaches" in the proposed paragraph e could be confusing as the term is used differently in RG 1.200, Rev. 3. The TSTF worked with industry PRA experts to revise paragraph e. to no longer use that term.
2. The NRC emphasized that newly developed methods with open findings on the method could not be 22-Mar-22 Copyright(C) 2022, EXCEL Services Corporation. Use by EXCEL Services associates, utility clients, and the U.S. Nuclear Regulatory Commission is granted. All other use without written permission is prohibited.

PWROG-12, Rev. 0 TSTF-591, Rev. 0 OG Revision 0 Revision Status: Active used. The industry stated that is in the committed guidance. However, a new paragraph was added as the penultimate paragraph in Section 3.1 of the traveler justification emphasizing that the endorsed guidance does not permit the use of newly developed methods with open peer review findings without prior NRC approval.

3.The NRC is still considering the time frame for submittal of the report. The industry and NRC agreed that submittal of the traveler did not need to wait on this issue, and it can be resolved during NRC review.

On February 2, 2022, the NRC made public an internal memorandum titled, "Staff Response to Nuclear Energy Institutes Proposed Technical Specification Changes Associated with the Use of Newly Developed Methods for Risk-Informed Completion Times." The memorandum provided recommended wording for the TS Risk Informed Completion Time Program that differed slightly from the 2021 NRC recommendation. To facilitate the NRCs review of the traveler, Appendix A of the traveler was revised to compare the travelers proposed wording to both the NRCs 2021 and 2022 proposals.

Affected Technical Specifications 5.5.20 Risk Informed Completion Time Program NUREG(s)- 1430 1431 1432 Only 5.6.8 Risk Informed Completion Time (RICT) Program Upgrade NUREG(s)- 1430 1431 1432 Only Report 5.5.17 Risk Informed Completion Time Program NUREG(s)- 1433 1434 Only 5.6.6 Risk Informed Completion Time (RICT) Program Upgrade NUREG(s)- 1433 Only Report 5.6.7 Risk Informed Completion Time (RICT) Program Upgrade NUREG(s)- 1434 Only Report 22-Mar-22 Copyright(C) 2022, EXCEL Services Corporation. Use by EXCEL Services associates, utility clients, and the U.S. Nuclear Regulatory Commission is granted. All other use without written permission is prohibited.

TSTF-591, Rev. 0

1.

SUMMARY

DESCRIPTION The proposed change revises the Technical Specifications (TS) Section 5.5 Program, "Risk Informed Completion Time Program," to reference Regulatory Guide (RG) 1.200, Revision 3, instead of Revision 2, and to make other changes. A new report is added to TS Section 5.6, "Reporting Requirements," to inform the NRC of the use of newly developed probabilistic risk assessment (PRA) methods to calculate a Risk Informed Completion Time (RICT). The proposed change affects the Standard Technical Specifications (STS) in NUREG-1430, NUREG-1431, NUREG-1432, NUREG-1433, and NUREG-14341.

2. DETAILED DESCRIPTION 2.1. Current Technical Specifications Requirements The Risk Informed Completion Time Program (RICT Program) was added by TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b,"

(Agencywide Documents Access and Management System (ADAMS) Accession No. ML18183A493), which was approved by the Nuclear Regulatory Commission (NRC) on November 21, 2018 (ADAMS Accession No. ML18269A041).

Paragraph e of the RICT Program, states:

The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2.

Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.

2.2. Reason for the Proposed Change Prior to the approval of TSTF-505, Revision 2, the NRC and the industry agreed that some terms used in Paragraph e of the RICT Program, such as, "approaches," "methods," and "approved by NRC for generic use," were not well defined. As a result, the TS requirements were unclear regarding when prior NRC approval would be needed in order to use a new or different method or approach. However, many licensees were anxious to submit license amendment requests (LARs) based on TSTF-505, Revision 2, and the industry and NRC agreed that the NRC should 1

NUREG-1430 provides the STS for Babcock & Wilcox plant designs.

NUREG-1431 provides the STS for Westinghouse plant designs.

NUREG-1432 provides the STS for Combustion Engineering plant designs.

NUREG-1433 provides the STS for BWR/4 plant designs, but is also representative of the BWR/2, BWR/3, and, in this case, BWR/5 design.

NUREG-1434 provides the STS for BWR/6 plant designs, and is representative, in some cases, of the BWR/5 plant design.

Page 1

TSTF-591, Rev. 0 approve Revision 2 and the industry and NRC would continue to work on clarification of Paragraph e.

The industry and NRC held a series of public meetings and teleconferences in 2019, 2020, and 2021 discussing changes to Paragraph e. In late 2020, the NRC determined that the revised language should reference RG 1.200, Revision 3, which was under development. RG 1.200, Revision 3, was issued in December 2020. In January 2021 the industry proposed wording for Paragraph e that referenced RG 1.200, Revision 3.

In April 2021 the NRC proposed a different TS reference to RG 1.200, Revision 3. The industry responded in May 2021. A teleconference was held with the NRC on June 3, 2021, and the NRC suggested that the industry submit a TSTF traveler with the proposed revisions to the RICT Program and the associated reporting requirement in order to facilitate closure of the issue.

2.3. Description of the Proposed Change The RICT Program is Specification 5.5.20 in NUREG-1430, NUREG-1431, and NUREG-1432, Revision 5, and Specification 5.5.17 in NUREG-1433 and NUREG-1434, Revision 5.

Paragraph e of the RICT Program is replaced with the following:

e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor].

Changes to these means of assessing the hazard groups require prior NRC approval.

New paragraphs f and g are added that state:

f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X] before a newly developed method is used to calculate a RICT.

A new reporting requirement is added to TS Section 5.6, "Reporting Requirements." The new report is Specification 5.6.8 in NUREG-1430, NUREG-1431, and NUREG-1432; Specification 5.6.6 in NUREG-1433; and Specification 5.6.7 in NUREG-1434. It states:

5.6.[8] Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods; Page 2

TSTF-591, Rev. 0

b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
d. All changes to key assumptions related to newly developed methods or their implementation.

Both the RICT Program and the RICT Program Upgrade Report are bracketed in the Standard Technical Specifications (STS), indicating that the specifications only apply to licensees that have adopted TSTF-505 by license amendment.

A model application is attached. The model may be used by licensees desiring to adopt the traveler following NRC approval.

3. TECHNICAL EVALUATION 3.1. Change From Referencing RG 1.200, Revision 2, To Revision 3 The primary change in this traveler is to replace a requirement to maintain and upgrade the PRA in accordance with RG 1.200, Revision 2, with a reference to RG 1.200, Revision 3.

RG 1.200, Revision 3, was issued in December 2020 and addresses new industry guidance and issues identified since Revision 2 was issued. Specifically, Revision 3:

  • Endorses, with staff exceptions and clarifications, the requirements in ASME/ANS RA-S Case 1, "Case for ASME/ANS RA-Sb-2013 Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment of Nuclear Power Plant Applications," dated November 22, 2017;
  • Endorses the following portions of the Pressurized Water Reactor Owners Group (PWROG) report, PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review," issued July 2020:

o Requirements for the peer review of newly developed methods; o Process for determining whether a change to a PRA is classified as PRA maintenance or a PRA upgrade; o Definitions related to newly developed methods, PRA maintenance, and PRA upgrade.

  • Enhances guidance related to key assumptions and sources of uncertainty; Page 3

TSTF-591, Rev. 0

  • Provides a glossary of key terms; and
  • Provides a list of hazards to be considered in the development and use of PRA.

A significant improvement in RG 1.200, Revision 3, is the inclusion of guidance that enables peer-reviewers to evaluate newly developed methods. NEI 17-07, Revision 2, discusses peer review of PRA upgrades that include newly develop methods.

These changes permit licensees to revise their PRA models used to calculate a RICT to incorporate most newly developed methods in accordance with the requirements of the ASME/ANS PRA Standard without prior NRC approval, while giving the NRC oversight capability. The documents endorsed in RG 1.200, Rev. 3, provide clear definitions of what constitutes a PRA method and what is a newly developed method (NDM) (i.e., a method that has been developed separately from a state-of-practice method or that involves a fundamental change to a state-of-practice model). RG 1.200 Regulatory Position C.2.2.2.2, states "An acceptable approach to performing a peer review for an NDM is the guidance in NEI 17-07, Revision 2. In particular, NEI 17-07, Revision 2, states, in part, that, if an NDM is deemed not technically acceptable in the NDM peer review report, or if at least one finding-level F&O [facts and observations] on the NDM remain open, a licensee or applicant may not use it in a PRA supporting risk-informed licensing applications. If open finding-level F&Os from an NDM peer review cannot be successfully closed via an NRC-endorsed peer review process, the NDM could be submitted to the NRC to determine the acceptability of the NDM. Submitted applications that use NDMs with open finding-level F&Os related to the NDM will be subject to review by the NRC to determine acceptability of the NDM, its implementation in the PRA, and its potential impact on the application." Therefore, an NDM with open finding-level F&Os cannot be used by a licensee without prior NRC approval. The licensee's implementation of the NDM may have open finding-level F&Os, but those finding-level F&Os must be dispositioned, as described in Section 3.3.

The proposed TS requirements ensure that changes to the PRA models used in the RICT program, including changes involving newly-developed methods, are properly evaluated. To provide the NRC with oversight, a required report will be submitted to the NRC when a newly developed method is used in the RICT Program.

3.2. RICT Program Changes The current RICT Program, Paragraph e, begins by stating, "The risk assessment approaches and methods shall be acceptable to the NRC." It also states, "Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval." These sentences are replaced because the phrases, "risk assessment approaches and methods," "this license amendment," and "outside these approval boundaries," are undefined or unclear when used within a plant's TS.

The proposed Paragraph e states, "A RICT calculation must include the following hazard groups:

[list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal Page 4

TSTF-591, Rev. 0 events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval." The proposed requirement clearly states the types of changes that require prior NRC approval. For example, if a licensee's TSTF-505 submittal described a Seismic Margins Analysis used to calculate a RICT and the licensee desires to use a seismic PRA, prior NRC approval is required. The proposed TS encompass the current Paragraph e requirements that the PRA models must be acceptable to the NRC, that they must be those used to support the TSTF-505 license amendment, and that prior NRC approval is needed to change those models.

The Paragraph e phrase, "other methods approved by the NRC for generic use" is deleted. There is no established regulatory process for the NRC to approve a PRA method for generic use.

The current RICT Program, Paragraph e, states, "The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2." It is replaced by a new Paragraph f which states, "The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3,

'Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities'." The reference to the "as-built, as-operated, and maintained plant," is unnecessary because it is incorporated in RG 1.200, Revision 3. RG 1.200, Revision 3, Staff Regulatory Position C.1, states, "The base PRA serves as the foundational representation of the as-built and as-operated plant necessary to support an application." The term "maintained" does not appear in RG 1.200, Rev. 3, in this context and is not necessary because "maintained" is encompassed within "as-operated." The proposed change refers to the regulatory positions in RG 1.200, Revision 3.

RG 1.200, Revision 3, contains other information that does not convey the regulatory positions; which are only contained in Section C of the RG.

Separating the proposed Paragraph f from Paragraph e conveys meaning. The proposed Paragraph e describes when prior NRC approval is required. The proposed Paragraph f describes PRA model maintenance and upgrade in accordance with RG 1.200, Rev. 3, which does not typically require prior NRC approval.

As described in Section 3.1, Revision 3 of RG 1.200 discusses the use of newly developed methods. If a licensee uses a newly developed method in the RICT Program, a report is required to be submitted to the NRC. Paragraph g requires the report and references a new reporting requirement in Section 5.6, of the TS.

3.3. Addition of a TS Reporting Requirement The proposed change adds a new reporting requirement to Section 5.6 of the TS titled, "Risk Informed Completion Time (RICT) Program Upgrade Report." The report is required to be submitted by the Section 5.5 RICT Program if a newly developed method is to be used. The details of the reporting requirement are in Section 5.6.

The proposed report must be submitted following a PRA upgrade associated with a newly developed method and prior to using that method to calculate a RICT.

Page 5

TSTF-591, Rev. 0 The proposed report must include:

  • The PRA models upgraded to include newly developed methods;
  • A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
  • Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
  • All changes to key assumptions related to newly developed methods or their implementation.

In accordance with Title 10 of the Code of Federal Regulations, Part 50.4, all reports from a licensee to the Nuclear Regulatory Commission must be sent to the Document Control Desk using the specified address.

3.4. Comparison to NRC Proposals In April 2021 the NRC provided proposed TS wording referencing RG 1.200, Revision 3, for industry comment. In February 2022, the NRC provided an alternate recommendation (ADAMS Accession No. ML19226A207). Appendix A provides a comparison of the NRC's proposals to the proposed traveler.

4. REGULATORY EVALUATION The regulation at Title 10 of the Code of Federal Regulations (10 CFR) Section 50.36(b) requires:

Each license authorizing operation of a utilization facility will include technical specifications. The technical specifications will be derived from the analyses and evaluation included in the safety analysis report, and amendments thereto, submitted pursuant to [10 CFR] 50.34 ["Contents of applications; technical information"]. The Commission may include such additional technical specifications as the Commission finds appropriate.

Per 10 CFR 50.90, whenever a holder of a license desires to amend the license, application for an amendment must be filed with the Commission, fully describing the changes desired, and following as far as applicable, the form prescribed for original applications.

Per 10 CFR 50.92(a), in determining whether an amendment to a license will be issued to the applicant, the Commission will be guided by the considerations which govern the issuance of initial licenses to the extent applicable and appropriate.

Section IV, "The Commission Policy," of the "Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors" (58FR39132), dated July 22, 1993, states in part that improved STS have been developed and will be maintained for each NSSS Page 6

TSTF-591, Rev. 0 owners group. The Commission Policy encourages licensees to use the improved STS as the basis for plant-specific Technical Specifications." The industry's proposal of travelers and the NRC's approval of travelers is the method used to maintain the improved STS as described in the Commission's Policy. Following NRC approval, licensees adopt travelers into their plant-specific technical specifications following the requirements of 10 CFR 50.90. Therefore, the traveler process facilitates the Commission's policy while satisfying the requirements of the applicable regulations.

The regulation at 10 CFR 50.36(a)(1) also requires the application to include a "summary statement of the bases or reasons for such specifications, other than those covering administrative controls." The proposed traveler does not affect the Bases and, therefore, does not affect compliance with 10 CFR 50.36(a)(1).

In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the approval of the proposed change will not be inimical to the common defense and security or to the health and safety of the public.

5. REFERENCES
1. TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," July 2, 2018, NRC ADAMS Accession No. ML18183A493.
2. Final Revised Model Safety Evaluation of Traveler TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," November 21, 2018, ADAMS Accession No. ML18269A041.
3. Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities," December 2020.

Page 7

TSTF-591, Rev. 0 Model Application

TSTF-591, Rev. 0

[DATE] 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 DOCKET NO.PLANT NAME

[50]-[xxx]

SUBJECT:

Application to Revise Technical Specifications to Adopt TSTF-591, "Revise Risk Informed Completion Time (RICT)

Program" Pursuant to 10 CFR 50.90, [LICENSEE] is submitting a request for an amendment to the Technical Specifications (TS) for [PLANT NAME, UNIT NOS.].

[LICENSEE] requests adoption of TSTF-591, "Revise Risk Informed Completion Time (RICT)

Program," which is an approved change to the Standard Technical Specifications (STS), into the

[PLANT NAME, UNIT NOS] TS. TSTF-591 revises the Technical Specifications (TS) Section 5.5 Program, "Risk Informed Completion Time Program," to reference Regulatory Guide (RG) 1.200, Revision 3, instead of Revision 2, and to make other changes. A new report is added to TS Section 5.6, "Reporting Requirements," to inform the NRC of newly developed methods used to calculate a RICT.

The enclosure provides a description and assessment of the proposed changes. Attachment 1 provides the existing TS pages marked to show the proposed changes. Attachment 2 provides revised (clean) TS pages. The proposed change does not affect the TS Bases.

[LICENSEE] requests that the amendment be reviewed under the Consolidated Line Item Improvement Process (CLIIP). Approval of the proposed amendment is requested within 6 months of completion of the NRCs acceptance review. Once approved, the amendment shall be implemented within [90] days.

There are no regulatory commitments made in this application.

In accordance with 10 CFR 50.91, a copy of this application, with attachments, is being provided to the designated [STATE] Official.

If you should have any questions regarding this submittal, please contact [NAME, TELEPHONE NUMBER].

[In accordance with 10 CFR 50.30(b), a license amendment request must be executed in a signed original under oath or affirmation. This can be accomplished by attaching a notarized affidavit confirming the signature authority of the signatory, or by including the following statement in the cover letter: "I declare under penalty of perjury that the foregoing is true and correct.

Page 1

TSTF-591, Rev. 0 Executed on (date)." The alternative statement is pursuant to 28 USC 1746. It does not require notarization.]

Sincerely,

[Name, Title]

Enclosure:

Description and Assessment Attachments: 1. Proposed Technical Specification Changes (Mark-Up)

2. Revised Technical Specification Pages

[The attachments are to be provided by the licensee and are not included in the model application.]

cc: NRC Project Manager NRC Regional Office NRC Resident Inspector State Contact Page 2

TSTF-591, Rev. 0 ENCLOSURE DESCRIPTION AND ASSESSMENT

1.0 DESCRIPTION

[LICENSEE] requests adoption of TSTF-591, "Revise Risk Informed Completion Time (RICT)

Program," which is an approved change to the Standard Technical Specifications (STS), into the

[PLANT NAME, UNIT NOS] TS. TSTF-591 revises the Technical Specifications (TS) Section 5.5 Program, "Risk Informed Completion Time Program," to reference Regulatory Guide (RG) 1.200, Revision 3, instead of Revision 2, and to make other changes. A new report is added to TS Section 5.6, "Reporting Requirements," to inform the NRC of newly developed methods used to calculate a RICT.

2.0 ASSESSMENT 2.1 Applicability of Safety Evaluation

[LICENSEE] has reviewed the safety evaluation for TSTF-591 provided to the Technical Specifications Task Force in a letter dated [DATE]. This review included the NRC staffs evaluation, as well as the information provided in TSTF-591. [LICENSEE] has concluded that the justifications presented in TSTF-591 and the safety evaluation prepared by the NRC staff are applicable to [PLANT, UNIT NOS.] and justify this amendment for the incorporation of the changes to the [PLANT] TS.

2.2 Variations

[LICENSEE is not proposing any variations from the TS changes described in TSTF-591 or the applicable parts of the NRC staffs safety evaluation.] [LICENSEE is proposing the following variations from the TS changes described in TSTF-591 or the applicable parts of the NRC staffs safety evaluation:]

[The [PLANT] TS utilize different [numbering][and][titles] than the STS on which TSTF-591 was based. Specifically, [describe differences between the plant-specific TS numbering and/or titles and the TSTF-591 numbering and titles.] These differences are administrative and do not affect the applicability of TSTF-591 to the [PLANT] TS.]

[The [PLANT] TS contain requirements that differ from the STS on which TSTF-591 was based but are encompassed in the TSTF-591 justification. [Describe differences and why TSTF-591 is still applicable.]

[The [PLANT] Risk Informed Completion Time Program, Paragraph e, is different from the TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," wording used as the starting point in TSTF-591. These differences do not affect the applicability of the proposed change.]

[The [PLANT] license contains a condition that serves the same purpose as Paragraph e in TSTF-505, Revision 2, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative Page 3

TSTF-591, Rev. 0 4b." [LICENSEE] proposes to remove the license condition and to insert the proposed Paragraph e of the Risk Informed Completion Time Program. [Describe the differences between the license condition and the TSTF-505, Revision 2, Paragraph e and why they do not affect the applicability of TSTF-591.))

3.0 REGULATORY ANALYSIS

3.1 No Significant Hazards Consideration Analysis

[LICENSEE] requests adoption of TSTF-591, "Revise Risk Informed Completion Time (RICT)

Program," which is an approved change to the Standard Technical Specifications (STS), into the

[PLANT NAME, UNIT NOS] Technical Specifications (TS). TSTF-591 revises the Technical Specifications (TS) Section 5.5 Program, "Risk Informed Completion Time Program," to reference Regulatory Guide (RG) 1.200, Revision 3, instead of Revision 2, and to make other changes. A new report is added to TS Section 5.6, "Reporting Requirements," to inform the NRC of newly developed methods used to calculate a RICT.

[LICENSEE] has evaluated if a significant hazards consideration is involved with the proposed amendment(s) by focusing on the three standards set forth in 10 CFR 50.92, "Issuance of amendment," as discussed below:

1. Does the proposed amendment involve a significant increase in the probability or consequences of an accident previously evaluated?

Response: No The proposed change updates the standard for maintaining and updating PRA models used to calculate a RICT from NRC-approved Regulatory Guide 1.200, Revision 2, to NRC-approved Regulatory Guide 1.200, Revision 3. A new report is added to inform the NRC when a newly developed method is used.

The proposed change does not involve a significant increase in the probability of an accident previously evaluated because the change involves no change to the plant or its modes of operation. The proposed change does not increase the consequences of an accident because the design-basis mitigation function of the affected systems is not changed and the consequences of an accident during the extended Risk Informed Completion Time are no different from those during the existing Completion Time. The submittal of information-only reports has no effect on the initiators or consequences of any accidents previously evaluated.

Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.

2. Does the proposed amendment create the possibility of a new or different kind of accident from any accident previously evaluated?

Response: No Page 4

TSTF-591, Rev. 0 The proposed change updates the standard for maintaining and updating PRA models used to calculate a RICT from NRC-approved Regulatory Guide 1.200, Revision 2, to NRC-approved Regulatory Guide 1.200, Revision 3. A new report is added to inform the NRC when a newly developed method is used.

The proposed change does not change a design function or method of operation of the plant. The proposed change does not involve a physical alteration of the plant (no new or different kind of equipment will be installed).

Therefore, the proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.

3. Does the proposed amendment involve a significant reduction in a margin of safety?

Response: No The proposed change updates the standard for maintaining and updating PRA models used to calculate a RICT from NRC-approved Regulatory Guide 1.200, Revision 2, to NRC-approved Regulatory Guide 1.200, Revision 3. A new report is added to inform the NRC when a newly developed method is used.

The proposed change supports the extension of Completion Times provided risk is assessed and managed in accordance with the NRC-approved RICT Program. The proposed change does not alter any design basis or safety limits. The proposed change affects the standard used to maintain the PRA models used in the RICT Program by changing from one NRC-approved standard to a later NRC-approved version and requiring submittal of an information-only report. The RICT Program will continue to assure that adequate margins of safety are maintained.

Therefore, the proposed change does not involve a significant reduction in a margin of safety.

Based on the above, [LICENSEE] concludes that the proposed change presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and, accordingly, a finding of "no significant hazards consideration" is justified.

3.2 Conclusion In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.

4.0 ENVIRONMENTAL CONSIDERATION

A review has determined that the proposed amendment would change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in Page 5

TSTF-591, Rev. 0 10 CFR 20, or would change an inspection or surveillance requirement. However, the proposed amendment does not involve (i) a significant hazards consideration, (ii) a significant change in the types or a significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure.

Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed amendment.

Page 6

TSTF-591, Rev. 0 Appendix A Comparison of NRC April 2021 and February 2, 2022, Proposed TS Wording to the Traveler Proposed Wording

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum 5.5.X 5.5.X 5.5.X

e. A RICT must be calculated e. A risk-informed completion e. A RICT calculation must
  • It is not necessary to define using [list specific time (RICT) must be include the following RICT in paragraph e as it is approaches used (e.g., calculated using the hazard groups: [list specific defined in the first internal events probabilistic following techniques [list hazards and the associated paragraph of the program.

risk assessment (PRA), fire specific probabilistic risk PRA models or alternate

  • The NRC's 2022 proposal PRA, addition of bounding assessment (PRA) and non- means of assessing the uses the term "in the license seismic risk to RICT PRA techniques such as hazard for each applicable amendment request." This calculations, etc.)] based on FIVE, Seismic Margins] hazard group approved by is inappropriate for a TS the as-built, as-operated, used in the license NRC. For example, requirement as there is no and as-maintained plant. amendment request. internal flood and internal indication which license Changes to these PRA and events PRA model, internal amendment request is being non-PRA techniques fire PRA model, and referenced.

require prior U.S. Nuclear seismic penalty factor].

  • In the NRC 2021 proposal, Regulatory Commission Changes to these means of there is no explicit (NRC) approval. assessing the hazard groups requirement for NRC prior require prior NRC approval. It's implied that a approval. license amendment is required if the parenthetical TS description is changed.
  • In the NRC 2021 proposal, the first sentence states on how a RICT is calculated and also discusses maintenance (as-build, as-operated, as-maintained plant), which is confusing, and duplicative of RG 1.200, Regulatory Position Page A-1

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum C.1.

f. PRA models used to f. PRA models used to f. The PRA models used to
  • Reg Guide 1.200, Rev. 3, calculate a RICT shall be calculate a RICT shall be calculate a RICT shall be only has 4 regulatory maintained and upgraded in maintained and upgraded to maintained and upgraded in positions (C.1 - C.4).

accordance with processes reflect the as-built, as- accordance with the Therefore, stating described in Regulatory operated, and as-maintained processes endorsed in the Regulatory Positions C.1-Positions C.1, C.2, C.3, and plant in accordance with regulatory positions of C.4 is unnecessary.

C.4 in Regulatory Guide processes described in Regulatory Guide 1.200,

  • It not necessary to state, "to (RG) 1.200, Revision 3, Regulatory Positions C.1, Revision 3, "Acceptability reflect the as-built, as-

"Acceptability of C.2, C.3, and C.4 in of Probabilistic Risk operated, and as-maintained Probabilistic Risk Regulatory Guide (RG) Assessment Results for plant," as that requirement Assessment Results for 1.200, Revision 3, Risk-Informed Activities." is included in the regulatory Risk-Informed Activities." Acceptability of positions of RG 1.200, Rev.

Probabilistic Assessment 3, Regulatory Position C.1.

Results for Risk-Informed

  • It is not necessary to state Activities, issued the date of the Reg Guide if December 2020. the revision is specified.
f. Use of any newly g. Before use by the licensee,
  • The details in the NRC's developed methods, as NDMs, as defined in RG 2021 proposal Paragraph f defined in RG 1.200, 1.200, Revision 3, must be and 2022 proposal Revision 3, must meet all subjected to a peer review Paragraph g duplicate applicable review process. The NDMs used in requirements in RG 1.200, requirements in Tables 1- the licensees PRA model regulatory positions C.1 7.2-2 through 1-7.2-7 of must meet all applicable through C.4. This is Pressurized-Water Reactor review requirements in unnecessary and repetitive.

Owners Group (PWROG)- Tables 1-7.2-2 through 1- As a result, there is no need 19027-NP, Revision 2, 7.2-7 of Pressurized-Water to specifically discuss the "Newly Developed Method Reactor Owners Group review requirements for Requirements and Peer (PWROG)-19027-NP, newly developed methods Page A-2

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum Review," in accordance Revision 2, Newly in the TS. The with the process in NEI 17- Developed Method correspondence between the 07, Revision 2, Requirements and Peer NRC's proposal and RG "Performance of PRA Peer Review, issued July 2020. 1.200, Rev. 3, is detailed Reviews Using the The licensee must use the below.

ASME/ANS PRA peer review process in

  • Regulatory Position Standard." The peer review Nuclear Energy Institute C.2.2.2.1 states that NEI report described in Section (NEI) 17-07, Revision 2, 17-07, Rev. 2, is endorsed 9.1 of NEI 17-07, Revision Performance of PRA Peer for peer review of a PRA 2 for both the acceptability Reviews Using the upgrade (which includes and implementation of the ASME/ANS PRA newly developed methods).

newly developed method Standard, issued August

  • Regulatory Position must be available to the 2019. All peer review C.2.2.2.2 states "An NRC for oversight and findings on NDM must be acceptable set of inspection activities. closed using an NRC- requirements against which endorsed process prior to the adequacy of a newly use in calculating a RICT. If developed method can be any applicable requirements assessed is provided in in Tables 1- 7.2-2 through PWROG-19027-NP, 1-7.2-7 of PWROG-19027- Revision 2."

NP, Revision 2, are not met,

  • PWROG-19027-NP, use of the NDM requires Revision 2, states, "The prior NRC approval. The generic expectation is that peer review report newly developed methods described in Section 9.1 of satisfy the set of NEI 17- 07, Revision 2, for requirements discussed in both the acceptability and this section," which implementation of the includes Table 1-7.2-2 NDM must be retained. through 1-7.2-7.
  • Regulatory position Page A-3

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum C.2.2.2.2 recognizes that Section 5.2 of PWROG-19027-NP states that the peer review report must be publicly available.

  • Regulatory Guide 1.200, Revision 3, Regulatory Position C.2.2.2.2 states that if NDM is deemed not technically acceptable in the NDM peer review report, or if at least one finding-level F&O on the NDM remain open, a licensee or applicant may not use it in a PRA supporting risk-informed licensing applications.
  • It is not necessary to state that if it is desired to not meet a TS requirement, prior NRC approval is required.
g. A summary report g. A report shall be submitted
  • The term "summary" is describing the newly in accordance with confusing.

developed method and its Specification 5.6.[X] before

  • Revised to include the implementation must be a newly developed method restriction on use until after submitted in accordance is used to calculate a RICT. the report is submitted to with Section 5.6.x . avoid it being missed.

Page A-4

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum 5.6.X 5.6.X A summary report describing A summary report describing A report describing newly

  • The term "summary" is the newly developed method the NDM and its developed methods and their confusing.

and its implementation shall implementation shall be implementation must be

  • The first three paragraphs of be submitted to the NRC submitted to the NRC submitted following a the NRC's 2021 proposal following a PRA upgrade following a PRA upgrade. probabilistic risk assessment appear to be redundant to unless it has already been (PRA) upgrade associated each other and to the submitted to the NRC by a The summary report must be with newly developed proposed paragraph "g".

licensee. submitted following a PRA methods and prior to the first

  • A "newly developed upgrade associated with an use of those methods to method" that has been A summary report shall also NDM before using that calculate a RICT. previously submitted by a be submitted if the licensee method in the RICT program licensee no longer satisfies uses an already submitted or within 60 days after the the definition of a "newly newly developed method with licensee completes disposition developed method" and a exceptions, deviations, or of all peer review comments, report is not required. If a clarifications from the whichever date occurs sooner. licensee takes an exception precedent. The summary report shall or deviation from the describe the scope of the already submitted method, A summary report describing upgrade and shall include the it is a "newly developed a newly developed method following: method." Therefore, it is and its implementation must not required to be stated in be submitted following a PRA the TS.

upgrade associated with a newly developed method prior

  • The proposed schedules for to using that method in the submitting a report, before RICT program or within 60 use in the RICT program or days after completing the within 60 days after the focused peer review, focused peer review, whichever date occurs sooner.

whichever is sooner, have The summary report shall Page A-5

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum describe the scope of the different purposes (before upgrade and shall include: The report shall include: use of the method versus submittal of a "for

a. the PRA models upgraded, a. The PRA models upgraded information" report). The
a. The PRA models and the NDM used to include newly developed RICT program is not upgraded, and the methods; affected by a new method newly developed that is not used to calculate method used; b. a description of the b. A description of the a RICT, so the report timing
b. A description of the acceptability of the NDM acceptability of the newly should be based on that acceptability of the consistent with Section 5.2 developed methods purpose.

newly developed of PWROG-19027-NP, consistent with Section 5.2 method consistent with Revision 2 of PWROG-19027-NP, Section 5.2 of Revision 2, "Newly PWROG-19027-NP, Developed Method Revision 2, "Newly Requirements and Peer Developed Method Review;"

Requirements and Peer Review;" c. all open findings and how c. Any open findings from the

  • Item c is revised to refer to
c. All open finding those findings from the peer-review of the the impact on the RICT and how those NDM implementation were implementation of the calculation, not the PRA.

findings from the closed or were newly developed methods Only impacts on the RICT newly developed demonstrated not to have a and how those findings calculation are relevant to method significant impact on the were dispositioned; and the report.

implementation PRA

  • The 2022 NRC and how those recommendation to describe findings were how open findings are resolved1 or closed is not included as demonstrated not to closed findings do not need have a significant to be described. The term impact on the PRA; "dispositioned" is used Page A-6

TSTF-591, Rev. 0 NRC 4/20/21 Proposal NRC 2/2/2022 TSTF-591 Proposal Discussion Memorandum and d. all changes to key d. All changes to key which is equivalent to

d. All changes to key assumptions related to the assumptions related to "demonstrated to not have a assumptions related NDM or its implementation newly developed methods significant effect" on the to the newly or their implementation. RICT.

developed method or its

  • Footnotes are not used in implementation. the Administrative Controls. Item c was Footnote 1: For PRA peer changed from "resolved" to reviews, the terms "dispositioned" to address "resolving a finding" and the issue in the footnote.

"closing a finding" have different meanings. A peer review finding may only be "closed" using a process endorsed by the NRC. All NDM related findings shall be "closed" prior to the use of that NDM in a RICT program.

Page A-7

TSTF-591, Rev. 0 Technical Specifications Changes

TSTF-591, Rev. 0 No changes. For Information Only. Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)


REVIEWER'S NOTE ----------------------------------

The Risk Informed Completion Time is only applicable in MODES supported by the licensee's PRA. Licensees applying the RICT Program to MODES other than MODES 1 and 2 must demonstrate that they have the capability to calculate a RICT in those MODES or that the risk indicated by their MODE 1 and 2 PRA model is bounding with respect to the lower MODE conditions.

b. A RICT may only be utilized in MODE 1, 2 [, and 3, and MODE 4 while relying on steam generators for heat removal];
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.

Babcock & Wilcox STS 5.5-24 Rev. 5.0

TSTF-591, Rev. 0 Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)

e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval. ]
e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval.
f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X]

before a newly developed method is used to calculate a RICT. ]

[ 5.5.21 Spent Fuel Storage Rack Neutron Absorber Monitoring Program This Program provides controls for monitoring the condition of the neutron absorber used in the spent fuel pool storage racks to verify the Boron-10 areal density is consistent with the assumptions in the spent fuel pool criticality analysis. The program shall be in accordance with NEI 16-03-A, "Guidance for Monitoring of Fixed Neutron Absorbers in Spent Fuel Pools," Revision 0, May 2017 [, with the following exceptions:

1. . . . ].]

Babcock & Wilcox STS 5.5-25 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.7 Steam Generator Tube Inspection Report (continued)

2. The location, orientation (if linear), measured size (if available), and voltage response for each indication. For tube wear at support structures less than 20 percent through-wall, only the total number of indications needs to be reported;
3. A description of the condition monitoring assessment and results, including the margin to the tube integrity performance criteria and comparison with the margin predicted to exist at the inspection by the previous forward-looking tube integrity assessment;
4. The number of tubes plugged [or repaired] during the inspection outage; and

[5. The repair methods utilized and the number of tubes repaired by each repair method.]

d. An analysis summary of the tube integrity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results;
e. The number and percentage of tubes plugged [or repaired] to date, and the effective plugging percentage in each SG;
f. The results of any SG secondary side inspections; and

[g. Insert any plant-specific reporting requirements, if applicable.]

5.6.8 Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods;
b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and Babcock & Wilcox STS 5.6-5 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6

d. All changes to key assumptions related to newly developed methods or their implementation.

Babcock & Wilcox STS 5.6-6 Rev. 5.0

TSTF-591, Rev. 0 No changes. For Information Only. Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)

a. The RICT may not exceed 30 days;

REVIEWER'S NOTE ----------------------------------

The Risk Informed Completion Time is only applicable in MODES supported by the licensee's PRA. Licensees applying the RICT Program to MODES other than MODES 1 and 2 must demonstrate that they have the capability to calculate a RICT in those MODES or that the risk indicated by their MODE 1 and 2 PRA model is bounding with respect to the lower MODE conditions.

b. A RICT may only be utilized in MODE 1, 2 [, and 3, and MODE 4 while relying on steam generators for heat removal];
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.

Westinghouse STS 5.5-24 Rev. 5.0

TSTF-591, Rev. 0 Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)

e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval ].
e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval.
f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X]

before a newly developed method is used to calculate a RICT.]

[ 5.5.21 Spent Fuel Storage Rack Neutron Absorber Monitoring Program This Program provides controls for monitoring the condition of the neutron absorber used in the spent fuel pool storage racks to verify the Boron-10 areal density is consistent with the assumptions in the spent fuel pool criticality analysis. The program shall be in accordance with NEI 16-03-A, "Guidance for Monitoring of Fixed Neutron Absorbers in Spent Fuel Pools," Revision 0, May 2017 [, with the following exceptions:

1. . . . ].]

Westinghouse STS 5.5-25 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.7 Steam Generator Tube Inspection Report (continued)

2. The location, orientation (if linear), measured size (if available), and voltage response for each indication. For tube wear at support structures less than 20 percent through-wall, only the total number of indications needs to be reported;
3. A description of the condition monitoring assessment and results, including the margin to the tube integrity performance criteria and comparison with the margin predicted to exist at the inspection by the previous forward-looking tube integrity assessment;
4. The number of tubes plugged [or repaired] during the inspection outage; and

[5. The repair methods utilized and the number of tubes repaired by each repair method.]

d. An analysis summary of the tube integrity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results;
e. The number and percentage of tubes plugged [or repaired] to date, and the effective plugging percentage in each SG;
f. The results of any SG secondary side inspections; and

[g. Insert any plant-specific reporting requirements, if applicable.]

5.6.8 Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to using those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods;
b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and Westinghouse STS 5.6-5 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6

d. All changes to key assumptions related to newly developed methods or their implementation.

Westinghouse STS 5.6-6 Rev. 5.0

TSTF-591, Rev. 0 No changes. For Information Only. Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)


REVIEWER'S NOTE ----------------------------------

The Risk Informed Completion Time is only applicable in MODES supported by the licensee's PRA. Licensees applying the RICT Program to MODES other than MODES 1 and 2 must demonstrate that they have the capability to calculate a RICT in those MODES or that the risk indicated by their MODE 1 and 2 PRA model is bounding with respect to the lower MODE conditions.

b. A RICT may only be utilized in MODE 1, 2 [, and 3, and MODE 4 while relying on steam generators for heat removal];
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.

Combustion Engineering STS 5.5-24 Rev. 5.0

TSTF-591, Rev. 0 Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.20 Risk Informed Completion Time Program (continued)

e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval. ]
e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval.
f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X]

before a newly developed method is used to calculate a RICT.]

[ 5.5.21 Spent Fuel Storage Rack Neutron Absorber Monitoring Program This Program provides controls for monitoring the condition of the neutron absorber used in the spent fuel pool storage racks to verify the Boron-10 areal density is consistent with the assumptions in the spent fuel pool criticality analysis. The program shall be in accordance with NEI 16-03-A, "Guidance for Monitoring of Fixed Neutron Absorbers in Spent Fuel Pools," Revision 0, May 2017 [, with the following exceptions:

1. . . . ].]

Combustion Engineering STS 5.5-25 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.7 Steam Generator Tube Inspection Report (continued)

2. The location, orientation (if linear), measured size (if available), and voltage response for each indication. For tube wear at support structures less than 20 percent through-wall, only the total number of indications needs to be reported;
3. A description of the condition monitoring assessment and results, including the margin to the tube integrity performance criteria and comparison with the margin predicted to exist at the inspection by the previous forward-looking tube integrity assessment;
4. The number of tubes plugged [or repaired] during the inspection outage; and

[5. The repair methods utilized and the number of tubes repaired by each repair method.]

d. An analysis summary of the tube integrity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results;
e. The number and percentage of tubes plugged [or repaired] to date, and the effective plugging percentage in each SG;
f. The results of any SG secondary side inspections; and

[g. Insert any plant-specific reporting requirements, if applicable.]

5.6.8 Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods;
b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and Combustion Engineering STS 5.6-5 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6

d. All changes to key assumptions related to newly developed methods or their implementation.

Combustion Engineering STS 5.6-6 Rev. 5.0

TSTF-591, Rev. 0 No changes. For Information Only. Programs and Manuals 5.5 5.5 Programs and Manuals

[ 5.5.17 Risk Informed Completion Time Program This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, "Risk-Managed Technical Specifications (RMTS) Guidelines." The program shall include the following:

a. The RICT may not exceed 30 days;

REVIEWER'S NOTE ----------------------------------

The Risk Informed Completion Time is only applicable in MODES supported by the licensee's PRA. Licensees applying the RICT Program to MODES other than MODES 1 and 2 must demonstrate that they have the capability to calculate a RICT in those MODES or that the risk indicated by their MODE 1 and 2 PRA model is bounding with respect to the lower MODE conditions.

b. A RICT may only be utilized in MODE 1, 2 [, and 3, and MODE 4 while relying on steam generators for heat removal];
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.

General Electric BWR/4 STS 5.5-19 Rev. 5.0

TSTF-591, Rev. 0 Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.17 Risk Informed Completion Time Program (continued)

e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval. ]
e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval.
f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X]

before a newly developed method is used to calculate a RICT.]

[ 5.5.18 Spent Fuel Storage Rack Neutron Absorber Monitoring Program This Program provides controls for monitoring the condition of the neutron absorber used in the spent fuel pool storage racks to verify the Boron-10 areal density is consistent with the assumptions in the spent fuel pool criticality analysis. The program shall be in accordance with NEI 16-03-A, "Guidance for Monitoring of Fixed Neutron Absorbers in Spent Fuel Pools," Revision 0, May 2017 [, with the following exceptions:

1. . . . ].]

General Electric BWR/4 STS 5.5-20 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.4 RCS PRESSURE AND TEMPERATURE LIMITS REPORT (continued)

6. The minimum temperature requirements of Appendix G to 10 CFR Part 50 shall be incorporated into the pressure and temperature limit curves.
7. Licensees who have removed two or more capsules should compare for each surveillance material the measured increase in reference temperature (RTNDT) to the predicted increase in RTNDT; where the predicted increase in RTNDT is based on the mean shift in RTNDT plus the two standard deviation value (2) specified in Regulatory Guide 1.99, Revision 2. If the measured value exceeds the predicted value (increase RTNDT + 2), the licensee should provide a supplement to the PTLR to demonstrate how the results affect the approved methodology.

5.6.5 Post Accident Monitoring Report When a report is required by Condition B or F of LCO 3.3.[3.1], "Post Accident Monitoring (PAM) Instrumentation," a report shall be submitted within the following 14 days. The report shall outline the preplanned alternate method of monitoring, the cause of the inoperability, and the plans and schedule for restoring the instrumentation channels of the Function to OPERABLE status.


REVIEWER'S NOTE----------------------------------------

These reports may be required covering inspection, test, and maintenance activities. These reports are determined on an individual basis for each unit and their preparation and submittal are designated in the Technical Specifications.

5.6.6 Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods;
b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
d. All changes to key assumptions related to newly developed methods or their implementation.

General Electric BWR/4 STS 5.6-4 Rev. 5.0

TSTF-591, Rev. 0 No changes. For Information Only. Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.17 Risk Informed Completion Time Program (continued)


REVIEWER'S NOTE ----------------------------------

The Risk Informed Completion Time is only applicable in MODES supported by the licensee's PRA. Licensees applying the RICT Program to MODES other than MODES 1 and 2 must demonstrate that they have the capability to calculate a RICT in those MODES or that the risk indicated by their MODE 1 and 2 PRA model is bounding with respect to the lower MODE conditions.

b. A RICT may only be utilized in MODE 1, 2 [, and 3, and MODE 4 while relying on steam generators for heat removal];
c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
2. For emergent conditions, the revised RICT must be determined within the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall account for the increased possibility of common cause failure (CCF) by either:
1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, and, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.

General Electric BWR/6 STS 5.5-19 Rev. 5.0

TSTF-591, Rev. 0 Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.17 Risk Informed Completion Time Program (continued)

e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods used to support this license amendment, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval. ]
e. A RICT calculation must include the following hazard groups: [list specific hazards and the associated PRA models or alternate means of assessing the hazard for each applicable hazard group approved by NRC. For example, internal flood and internal events PRA model, internal fire PRA model, and seismic penalty factor]. Changes to these means of assessing the hazard groups require prior NRC approval.
f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
g. A report shall be submitted in accordance with Specification 5.6.[X]

before a newly developed method is used to calculate a RICT. ]

[ 5.5.18 Spent Fuel Storage Rack Neutron Absorber Monitoring Program This Program provides controls for monitoring the condition of the neutron absorber used in the spent fuel pool storage racks to verify the Boron-10 areal density is consistent with the assumptions in the spent fuel pool criticality analysis. The program shall be in accordance with NEI 16-03-A, "Guidance for Monitoring of Fixed Neutron Absorbers in Spent Fuel Pools," Revision 0, May 2017 [, with the following exceptions:

1. . . . ].]

General Electric BWR/6 STS 5.5-20 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6 5.6 Reporting Requirements 5.6.4 RCS PRESSURE AND TEMPERATURE LIMITS REPORT (continued)

6. The minimum temperature requirements of Appendix G to 10 CFR Part 50 shall be incorporated into the pressure and temperature limit curves.
7. Licensees who have removed two or more capsules should compare for each surveillance material the measured increase in reference temperature (RTNDT) to the predicted increase in RTNDT; where the predicted increase in RTNDT is based on the mean shift in RTNDT plus the two standard deviation value (2) specified in Regulatory Guide 1.99, Revision 2. If the measured value exceeds the predicted value (increase in RTNDT + 2), the licensee should provide a supplement to the PTLR to demonstrate how the results affect the approved methodology.

5.6.5 Post Accident Monitoring Report When a Special Report is required by Condition B or F of LCO 3.3.[3.1], "Post Accident Monitoring (PAM) Instrumentation," a report shall be submitted within the following 14 days. The report shall outline the preplanned alternate method of monitoring, the cause of the inoperability, and the plans and schedule for restoring the instrumentation channels of the Function to OPERABLE status.

5.6.6 [ Tendon Surveillance Report Any abnormal degradation of the containment structure detected during the tests required by the Pre-Stressed Concrete Containment Tendon Surveillance Program shall be reported to the NRC within 30 days. The report shall include a description of the tendon condition, the condition of the concrete (especially at tendon anchorages), the inspection procedures, the tolerances on cracking, and the corrective action taken. ]


REVIEWER'S NOTE----------------------------------------

These reports may be required covering inspection, test, and maintenance activities. These reports are determined on an individual basis for each unit and their preparation and submittal are designated in the Technical Specifications.

5.6.7 Risk Informed Completion Time (RICT) Program Upgrade Report A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:

a. The PRA models upgraded to include newly developed methods; General Electric BWR/6 STS 5.6-4 Rev. 5.0

TSTF-591, Rev. 0 Reporting Requirements 5.6

b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
d. All changes to key assumptions related to newly developed methods or their implementation.

General Electric BWR/6 STS 5.6-5 Rev. 5.0