Acceptance for Review Regarding Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements
ML22256A212
Person / Time
Site: Technical Specifications Task Force
Issue date: 09/28/2022
From: Michelle Honcharik
NRC/NRR/DSS/STSB
To:
Technical Specifications Task Force
Honcharik M NRR/DSS 301-415-8553
References
EPID L-2022-PMP-0011
Download: ML22256A212 (3)


Text

September 28, 2022

Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852

SUBJECT:

ACCEPTANCE FOR REVIEW REGARDING TRAVELER TSTF-592, REVISION 0, "REVISE AUTOMATIC DEPRESSURIZATION SYSTEM (ADS) INSTRUMENTATION REQUIREMENTS" (EPID L-2022-PMP- 0011)

Dear Members of the Technical Specifications Task Force:

By letter dated July 19, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22200A080 ), you submitted a request to the U.S. Nuclear Regulatory Commission (NRC) to incorporate Traveler TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements, into the standard technical specifications.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that Travelers are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours have been billed accordingly. The NRC staff estimates that the review will require approximately 355 staff hours including project management time.

The NRC staff has completed a preliminary review of your submission and determined it is sufficiently complete and appropriate to initiate a more comprehensive review. The review will generally follow the schedule below.

MILESTONE SCHEDULE DATE Issue Request for Additional Information December 16, 2022 Issue Draft Safety Evaluation August 31, 2023 Issue Final Safety Evaluation December 22, 2023

If you have any questions, please contact me at (301) 415-1774 or via e-mail to Michelle.Honcharik@nrc.gov.

Sincerely,

Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation

Project No. 753 cc: See next page

cc:

Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E-mail: brian.mann@excelservices.com

Drew Richards STP Nuclear Operating Company 12090 FM 521 Mail Code: N5016 Wadsworth, TX 77483 Email: amrichards@stpegs.com

Kevin Lueshen Constellation Energy Generation 4300 Winfield Road Warrenville IL 60555 Email: kevin.lueshen@constellation.com

Jordan L. Vaughan Duke Energy EC07C / P.O. Box 1006 Charlotte, NC 28202 Email: jordan.vaughan@duke-energy.com

Ryan M. Joyce Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-274-EC Birmingham, AL 35243 Email: rmjoyce@southernco.com

Wesley Sparkman Southern Nuclear Operating Company 3535 Colonnade Parkway / Bin N-226-EC Birmingham, AL 35242 Email: wasparkm@southernco.com

SUBJECT:

ACCEPTANCE FOR REVIEW REGARDING TRAVELER TSTF-592, REVISION 0, "REVISE AUTOMATIC DEPRESSURIZATION SYSTEM (ADS) INSTRUMENTATION REQUIREMENTS" (EPID L-2022-PMP- 0011)

DATED: SEPTEMBER 28, 2022

DISTRIBUTION:

PUBLIC RidsResOd Resource RidsNrrOd Resource M.Honcharik, NRR RidsNrrDprPrab Resource C.Ashley, NRR RidsOgcMailCenter Resource H.Vu, NRR RidsOpaMail Resource N.Karipineni, NRR RidsACRS_MailCTR Resource RidsNrrDeEicb Resource RidsNrrDssStsb Resource RidsNrrDssSnpb Resource

ADAMS Accession No.: ML22256A212 NRR-106 OFFICE NRR/DSS/STSB NRR/DSS/STSB NAME VCusumano CAshley for MHoncharik DATE 09/28/2022 09/28/2022 OFFICIAL RECORD COPY