ML16194A010

From kanterella
Jump to navigation Jump to search

Acceptance for Review Regarding Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement
ML16194A010
Person / Time
Site: Technical Specifications Task Force
Issue date: 08/11/2016
From: Michelle Honcharik
Licensing Processes Branch (DPR)
To:
Technical Specifications Task Force
Honcharik M
References
TAC MF7622, TSTF-546
Download: ML16194A010 (3)


Text

August 12, 2016 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852

SUBJECT:

ACCEPTANCE FOR REVIEW REGARDING TRAVELER TSTF-546, REVISION 0, "REVISE APRM CHANNEL ADJUSTMENT SURVEILLANCE REQUIREMENT" (TAC NO. MF7622)

Dear Members of the Technical Specifications Task Force:

By letter dated April 21, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16112A208), you submitted to the U.S. Nuclear Regulatory Commission (NRC) for review and approval Traveler TSTF-546, Revision 0, Revise APRM

[Average Power Range Monitor] Channel Adjustment Surveillance Requirement.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that Travelers are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours have been billed accordingly.

The NRC staff has completed a preliminary review of your submission and determined it is sufficiently complete and appropriate to initiate a more comprehensive review. The review of Traveler TSTF-546 will generally follow the schedule below.

MILESTONE SCHEDULE DATE Issue Request for Additional Information September 30, 2016 Issue Draft Safety Evaluation June 7, 2017 Issue Final Safety Evaluation September 21, 2017 If you have any questions, please contact me at (301) 415-1774 or via e-mail to Michelle.Honcharik@nrc.gov.

Sincerely,

/RA/

Michelle C. Honcharik, Senior Project Manager Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753

ML16194A010; *concurred via e-mail NRR-106 OFFICE DPR/PLPB DPR/PLPB* DSS/SRXB* DE/EICB*

NAME MHoncharik DHarrison EOesterle (DWoodyatt) MWaters DATE 7/26/2016 7/21/16 7/15/16 7/29/16 OFFICE DSS/STSB* DPR/PLPB DPR/PLPB NAME AKlein KHsueh MHoncharik DATE 8/2/2016 08/11/2016 08/11/2016 Technical Specifications Task Force Project No. 753 cc:

Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E-mail: brian.mann@excelservices.com James R. Morris Diablo Canyon Power Plant Building 104/5/21A P.O. Box 56 Avila Beach, CA 93424 E-mail: JY1E@pge.com Lisa L. Williams Energy Northwest Columbia Generating Station PO Box 968 Mail Drop PE20 Richland, WA 99352-0968 E-mail: llwilliams@energy-northwest.com Otto W. Gustafson Entergy Nuclear Operations, Inc.

Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E-mail: ogustaf@entergy.com Michael K. Leisure Duke Energy 526 S. Church Street Mail Code EC2ZF Charlotte, NC 28202 E-mail: mike.leisure@duke-energy.com Kelli A. Roberts Southern Nuclear Operating Company 42 Inverness Center Parkway BIN B237 Birmingham, AL. 35242-4809 E-mail: kroberts@southernco.com