Letter Sequence Acceptance Review |
---|
TAC:MD9433, Control Room Habitability, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation (Open) |
|
MONTHYEARML0827504932008-10-0707 October 2008 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation Project stage: Acceptance Review ML0906808132009-04-17017 April 2009 Request for Additional Information Regarding TSTF-508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation Project stage: RAI TSTF-10-18, Response to NRC Request for Additional Information on TSTF-508, Revision 1, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation2010-10-11011 October 2010 Response to NRC Request for Additional Information on TSTF-508, Revision 1, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation Project stage: Response to RAI ML1104205302011-02-0909 February 2011 ITSB Resolution of Excel Services Corporation Proposed TSTF-426 Wording Project stage: Other ML1105606302011-03-23023 March 2011 February 9, 2011, Summary of NRC Meeting with the Technical Specifications Task Force Discussed the Topics as Presented on the Agenda Project stage: Request ML1103803112011-03-23023 March 2011 2/9/11 Meeting Handout - NRC Staff'S Draft LCO 3.0.X Project stage: Request ML1108908172011-04-12012 April 2011 Request for Additional Information Regarding TSTF-508, Revision 1, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation Project stage: RAI 2010-10-11
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML23205A2142023-08-10010 August 2023 Acceptance for Review Regarding Traveler TSTF-596, Revision 0, Expand the Applicability of the Surveillance Frequency Control Program (SFCP) ML23157A2062023-07-0505 July 2023 Acceptance for Review and Revised Schedule Regarding Traveler TSTF-576, Revise Safety/Relief Valve Requirements ML23145A2822023-06-0202 June 2023 Acceptance for Review Regarding Traveler TSTF-585, Provide an Alternative to the LCO 3.0.3 One Hour Preparation Time ML22256A2122022-09-28028 September 2022 Acceptance for Review Regarding Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22181A7442022-06-30030 June 2022 Acceptance for Review Regarding Traveler TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation ML22062B3362022-03-0808 March 2022 Acceptance Review of Traveler TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML20037A1292020-02-13013 February 2020 Acceptance for Review Regarding Traveler TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19211D1192019-08-22022 August 2019 Acceptance Review for Traveler TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19211D2842019-08-20020 August 2019 Acceptance Review for Traveler TSTF-554, Revise Reactor Coolant Leakage Requirements ML18057A1622018-03-26026 March 2018 Acceptance for Review Regarding Traveler TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, ML18057A1602018-03-26026 March 2018 Acceptance for Review Regarding Traveler TSTF-569, Revise Response Time Testing Definition, ML18057A1632018-03-0808 March 2018 Acceptance for Review Regarding Traveler TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML18057A1592018-03-0808 March 2018 Acceptance for Review Regarding Traveler TSTF-557, Spent Fuel Storage Rack Neutron Absorber Monitoring Program ML17325B6722017-11-28028 November 2017 Acceptance for Review Regarding Traveler TSTF-564, Safety Limit MCPR ML17236A1352017-08-29029 August 2017 Acceptance for Review Regarding Traveler TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases ML16194A0102016-08-11011 August 2016 Acceptance for Review Regarding Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement ML14223A7822014-08-14014 August 2014 Acceptance for Review Regarding Traveler TSTF-547, Revision 0, Clarification of Rod Position Requirements ML12163A1592012-06-13013 June 2012 TSTF-454, Extend PCIV Completion Times (NEDC-33046), Acceptance Letter ML12158A5472012-06-13013 June 2012 TSTF-523 Acceptance Letter and RAIs ML1128007042011-10-19019 October 2011 Acceptance for Review of Traveler TSTF-535, Revision 0, Revise Shutdown Margin Definition to Address Advanced Fuel Designs ML1111703472011-05-0606 May 2011 Acceptance for Review of Traveler TSTF-490, Revision 1, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML0827504932008-10-0707 October 2008 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML0715600542007-06-0707 June 2007 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 425, Revision 1, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5. 2023-08-10
[Table view] |
Text
October 7, 2008 Technical Specifications Task Force (TSTF) 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
ACCEPTANCE FOR REVIEW AND ESTABLISHMENT OF MILESTONE SCHEDULE FOR TSTF TRAVELER 508, REVISION 0, REVISE CONTROL ROOM HABITABILITY ACTIONS TO ADDRESS LESSONS LEARNED FROM TSTF-448 IMPLEMENTATION (TAC NO. MD9433)
Dear Members of the TSTF,
By letter dated July 3, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML081850420), the Technical Specifications Task Force (TSTF) requested that the Nuclear Regulatory Commission (NRC) review and approve TSTF Traveler 508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation under the Consolidated Line Item Improvement Process (CLIIP).
NRC Technical staff have completed a preliminary review of your submission and have determined that it is an appropriate submission in that it contains adequate information in order to initiate a more comprehensive review. The enclosed review milestone schedule for the review of TSTF-508, Revision 0 has been established, and Technical Assignment Control (TAC) MD9433 has been assigned for this task. Current estimates are that it will take approximately 150 man-hours for the NRC to process TSTF-508, Revision 0.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that TSTF Travelers are subject to fees based on the full cost of the review. You did not request a fee exemption; therefore, staff hours will be billed as requested to the Westinghouse Owners Group.
Should circumstances lead to anticipated or actual schedule slippage, the causing party should promptly inform and coordinate with the other party to reach a new agreement and publish an appropriately revised schedule. This is of particular importance in connection with TSTF response to NRC staff requests for additional information (RAIs) as failure to provide a timely responsive reply, in accordance with the agreed schedule, or to successfully negotiate a revised schedule, may result in termination of the review process and closure of the TAC. Early completion of any activity will not necessitate schedule revision. Schedule revisions that change the projected Notice of Availability date by more than 2 weeks will be published by letter similar to this and will remain in effect unless superseded by another published schedule.
TSTF 2 Mr. Matthew Hamm (301-415-1472; Email: Matthew.Hamm@nrc.gov) has been assigned as the ITSB project lead. Please contact Mr. Hamm in coordinating activities specific to this review.
Sincerely,
/RA/by C. Schulten for/
Robert B. Elliott, Chief Technical Specifications Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: See next page
ML082750493 OFFICE ITSB:DIRS BC:ITSB:DIRS NAME MHamm RElliott/ CSculten for DATE 10/03/2008 10/7/2008
MILESTONE SCHEDULE FOR TSTF TRAVELER 508, REVISION 0, REVISE CONTROL ROOM HABITABILITY ACTIONS TO ADDRESS LESSONS LEARNED FROM TSTF-448 IMPLEMENTATION MILESTONE SCHEDULE DATE Application 7/3/2008 Request For Additional Information (RAIs) if needed 11/17/2008 RAI Response from TSTF 2/16/2009 Issue Notice For Comment on Model Safety 4/10/2009 Evaluation and Model Application Issue Notice of Availability for Model Safety 7/9/2009 Evaluation and Model Application Close Out TAC 7/9/2009 Enclosure
Technical Specifications Task Force Mailing List cc:
Techncial Specifications Task Force Donald R. Hoffman 11921 Rockville, Pike EXCEL Services Corporation Suite 100 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Rockville, MD 20852 tstf@excelservices.com donaldh@excelservices.com George G. Yates Brian Mann AmerenUE Callaway Plant EXCEL Services Corporation Junction Hwy. CC and Hwy. O 11921 Rockville Pike, Suite 100 Mail Code CA-460 Rockville, MD 20852 P.O. Box 620 brianm@excelservices.com Fulton, MO 65251 gyates@ameren.com John Messina First Energy Nuclear Operating Company 76 South Main Street Mail Sto: Akron-GO-14 Akron, OH 44308 jmessina@firstenergycorp.com David Bice Entergy N-GSB64 Russellville, AR 72802 dbice@entergy.com Reene= V. Gambrell Duke Energy Mailcode: ON03RC 7800 Rochester Highway Seneca, SC 29672 RVGambrell@duke-energy.com