MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23332A1772023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 ML23270B8882023-10-23023 October 2023 Regulatory Audit Summary Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structure, Systems, and Components for Nuclear Power Reactors EPID L-2022-LLA-0182 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A1102023-10-0202 October 2023 License Amendment Request Revision 2 for the Technical Specifications Conversion to NUREG-1432, Revision 5 L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 ML23219A0042023-09-0101 September 2023 Transmittal Letter - Safety Evaluation Related to the SLRA of St. Lucie Plant, Units 1and 2, Revision 1 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23212B2652023-07-27027 July 2023 Operator Licensing Written Examination Approval 05000335/2023301 and 05000389/2023301 L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches ML23200A1232023-07-21021 July 2023 Transmittal Letter for the St. Lucie SLRA Review L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) ML23184A0352023-06-30030 June 2023 Notification of St. Lucie Units 1 & 2 Focused Engineering Inspection (FEI) 05000335/2023010 and 05000389/2023010 and Initial Information Request L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report 2024-01-08
[Table view] Category:Schedule and Calendars
[Table view] |
Text
September 24, 2021 Mr. Robert Coffey Vice President, Nuclear &
Chief Nuclear Officer Florida Power & Light Company 700 Universe Boulevard Mail Stop: EX/JB Juno Beach, FL 33408
SUBJECT:
ST. LUCIE PLANT, UNITS 1 AND 2 - DETERMINATION OF ACCEPTABILITY AND SUFFICIENCY FOR DOCKETING, PROPOSED REVIEW SCHEDULE, AND OPPORTUNITY FOR A HEARING REGARDING THE FLORIDA POWER AND LIGHTS APPLICATION FOR SUBSEQUENT LICENSE RENEWAL
Dear Mr. Coffey:
By letter dated August 3, 2021 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML21215A314), Florida Power and Light (FPL) submitted an application for the subsequent license renewal of Renewed Facility Operating License Nos. DPR-67 and NPF-16 for the St. Lucie Plant (SLP), Units 1 and 2 to the U.S. Nuclear Regulatory Commission (NRC).
By letter dated August 10, 2021 (ADAMS Accession No. ML21217A195), and Federal Register Notice (FRN) (86 FR 45768) dated August 16, 2021, the NRC noted the receipt and availability of this application.
The acceptance review is intended to identify whether the application is reasonably complete and conforms to the timing and information requirements in applicable regulations. The NRC staff reviewed your application following the guidance in NUREG-2192, Revision 0, Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants, and NUREG-1555, Supplement 1, Revision 1, Standard Review Plans for Environmental Reviews for Nuclear Power Plants, to determine if the application is sufficient and acceptable for docketing in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Sections 2.101, Filing of application, 51.45, Environmental report, 51.53(c),
Postconstruction environmental reports, 54.19, Contents of application--general information, 54.21, Contents of application--technical information, 54.22, Contents of application--technical specifications, and 54.23, Contents of application--environmental information.
The NRC staff conducted three pre-submittal meetings, one for the environmental review and two for the safety review, as documented in letters dated May 20, 2021 (ADAMS Accession No. ML21173A292), April 4, 2021 (ADAMS Accession No. ML21127A218), and June 3, 2021, (ADAMS Accession No. ML21176A055).
R. Coffey For the environmental review, the NRC staff noted that the application did not provide an analysis of impacts of the proposed action on the West Indian manatee (Trichechas manatus) nor sufficient analysis of the effects of the proposed action on essential fish habitat (EFH). After the NRC staff identified certain application deficiencies in a conference call with the applicant, by letter dated September 13, 2021 (ADAMS Accession No. ML21256A199), FPL supplemented its application to provide this information. The staff is currently reviewing this information and will issue RAIs if further information is needed.
As stated in the email sent to William Maher on September 17, 2021 (ADAMS Accession No. ML21266A041), the NRC staff has concluded that the application is acceptable for the staffs detailed review. Given the lesser scope and depth of the acceptance review as compared to a detailed technical review, the staffs determination does not preclude requests for additional information or topic specific audits. During the staffs detailed technical review, there may be instances identified in which issues that impact the NRC staffs ability to complete the detailed technical review are identified. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
This letter also forwards the staffs projected review schedule for the SLP subsequent license renewal application (Enclosure 1). The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 51, Environmental Protection Regulations for Renewal of Operating Licenses for Nuclear Power Functions, and Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants. Based on the information provided in your submittal and discussions during the pre-application meetings, the NRC staff has estimated that review of this subsequent license renewal application will take approximately 23,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> to complete. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated via separate correspondence. Milestones for hearing activities that may be needed are not included in the enclosed schedule or the estimated hours because these dates, if needed, would be established by the Commission or the Atomic Safety and Licensing Board and new resource considerations would need to be developed.
The plan also relies on your responses to the staff's requests for additional information, if needed, being of high quality and provided in a timely manner. A timely response is defined as 30 days from the date of the request, or within such other time as may be specified in the request in accordance with 10 CFR 2.108, Denial of application for failure to supply information. You should also be prepared to provide high quality support in a timely and organized manner during technical audits determined necessary by the staff. Delays in staffs receipt of necessary information could result in changes to the plan in evaluating and processing your application, up to and including the denial of your application in accordance with the regulations or a significant delay in the schedule based on the overall workload for the staff involved in the review. We request that you inform the NRC staff in writing as early as possible should potential delays arise in your support of the schedule. The staffs goal is to complete the review in 21 months provided that FPL addresses the staffs information needs in a timely manner. The 21-month schedule, which was mutually agreed upon during a discussion with your staff on September 16, 2021, is longer than the schedule for previous subsequent license renewal applications. In Fiscal Year 2021, the NRC has received a higher number of applications than anticipated and budgeted for this year and next, resulting in resource constraints at the NRC. Although the schedule is slightly longer, the staff remains committed to completing the review within the typical resource allocations for prior renewals. The NRC will
R. Coffey continue to evaluate opportunities to streamline this schedule wherever possible and appropriate.
Finally, we have also enclosed a copy of the notice related to your application that is being sent to the Office of the Federal Register for publication (Enclosure 2). This notice announces the opportunity to request a hearing and to file a petition for leave to intervene.
If you have any questions on this matter, please contact Lois James, Project Manager, for the safety review of the SLP subsequent license renewal application at Lois.James@nrc.gov, or Lance Rakovan, Project Manager, for the environmenal review at Lance.Rakovan@nrc.gov.
Sincerely,
/RA/
Robert K. Caldwell, Acting Director Division of New and Renewed Licenses Docket Nos: 50-335 and 50-389
Enclosures:
- 1. Review Schedule
- 2. Copy of Federal Register Notice cc w/encls: Listserv
ML21246A090 (Package)
ML21246A091 (Letter)
ML21246A092 (FRN) *eConcurrence via E-mail NRR-106 OFFICE PM/NLRP/DNRL LA/NRLB/DNRL PM/NLRP/DNRL PM/ERLRB/REFS NAME HRodriguez SGreen LJames LRakovan DATE 09/02/21 09/03/21 09/07/21 09/07/21 OFFICE OGC (NLO) BC/ERLRB/REFS BC/NLRP/DNRL D/DNRL (acting)
NAME MYoung RElliott LGibson BCaldwell DATE 09/14/21 09/20/21 09/21/21 09/24/21 SAINT LUCIE PLANT, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 08/2021 08/03/2021 Publish Federal Register Notice (FRN) - SLRA Availability 08/2021 08/10/2021 Publish FRN - Docketing Acceptance/Rejection and Opportunity 09/2021 for Hearing Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 10/2021 Public Meeting - Overview of Subsequent License Renewal 10/2021 Process and Environmental Scoping Environmental Scoping Period Ends 11/2021 Deadline for Filing Hearing Requests and Petitions for Intervention 11/2021 Issue Draft Supplemental Environmental Impact Statement (SEIS) 10/2022 Public Meeting - Draft SEIS Meeting, If Needed 11/2022 End of DSEIS Comment Period 11/2022 Issue Safety Evaluation Report (SER) 12/2022 ACRS Full Committee Meeting 02/2023 Issue Final SEIS 05/2023 U.S. Environmental Protection Agency FRN 06/2023 Published - Availability of Final SEIS Decision - Director, NRR 07/2023 Enclosure 1
Copy of the Draft Federal Register Notice of Saint Lucie Plant, Units 1 and 2 - Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Florida Power and Light Companys Application for Subsequent License Renewal ADAMS Accession No. ML21246A092 Enclosure 2