Letter Sequence Supplement |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: L-2021-063, Subsequent License Renewal Application Notification, L-2021-192, Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report, L-2022-108, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response, L-2023-026, Subsequent License Renewal Application - Aging Management Requests for Additional Information Set 4, ML21215A316, ML21285A107, ML21351A238, ML21351A239, ML21351A241, ML21351A248, ML21354A837, ML21356A011, ML22010A094, ML22010A096, ML22010A097, ML22010A100, ML22012A263, ML22012A282, ML22012A391, ML22013A277, ML22013A282, ML22013A284, ML22013A288, ML22013A292, ML22013A293, ML22013A294, ML22013A295, ML22013A296, ML22013A297, ML22013A301, ML22013A302, ML22013A303, ML22013A304, ML22013A305, ML22013A307, ML22013A316, ML22013A317, ML22013A334, ML22188A086, ML23200A123
|
MONTHYEARL-2021-064, Request for Exemption from the Schedular Requirements of 10 CFR 54.17 (C)2021-03-17017 March 2021 Request for Exemption from the Schedular Requirements of 10 CFR 54.17 (C) Project stage: Request L-2021-063, Subsequent License Renewal Application Notification2021-03-17017 March 2021 Subsequent License Renewal Application Notification Project stage: Other ML21215A3192021-08-0303 August 2021 Appendix E - Applicants Environmental Report for St. Lucie Project stage: Request ML21215A3152021-08-0303 August 2021 Application for Subsequent Renewed Facility Operating Licenses Project stage: Request ML21215A3172021-08-0303 August 2021 Enclosure 2: Affidavits Supporting Withholding Proprietary Information from Public Disclosure Project stage: Request ML21215A3162021-08-0303 August 2021 Enclosure 1: Subsequent License Renewal Application Enclosures Summary Project stage: Other L-2021-181, Subsequent License Renewal Application - Environmental Report Supplement 12021-09-13013 September 2021 Subsequent License Renewal Application - Environmental Report Supplement 1 Project stage: Supplement ML21285A1072021-10-12012 October 2021 Subsequent Licensee Renewal Application, Revision 1 Project stage: Other L-2021-192, Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report2021-10-12012 October 2021 Subsequent Licensee Renewal Application, Revision 1, Appendix E, Applicant'S Environmental Report Project stage: Other L-2021-209, Refueling Outage SL1-30 Steam Generator Tube Inspection Report2021-11-0101 November 2021 Refueling Outage SL1-30 Steam Generator Tube Inspection Report Project stage: Request ML22013A2772021-11-21021 November 2021 2.4 Structural Scoping and Screening Breakout Questions Project stage: Other ML21351A2382021-12-17017 December 2021 Trp 148.1 St. Lucie SLRA - Breakout Questions for TLAA Section 4.7.1 Rev. 1 Project stage: Other ML21351A2392021-12-17017 December 2021 Trp 14 St. Lucie SLRA - Buried Pipe Breakout Questions - Allik.Docx Project stage: Other ML21351A2412021-12-17017 December 2021 Trp 15 St. Lucie SLRA - Internal Coatings Breakout Questions - Allik Project stage: Other ML21351A2482021-12-17017 December 2021 Trp 26 St. Lucie SLRA - Fire Protection Breakout Questions Project stage: Other ML21356A0112021-12-17017 December 2021 Trp 148.3 and 148.4 St Lucie SLRA Breakout Questions Project stage: Other ML21354A8372021-12-20020 December 2021 Trp 11 St. Lucie SLRA Breakout Questions Project stage: Other ML22013A2972021-12-21021 December 2021 Trp 77 St. Lucie SLRA - Breakout Questions Corrosion Structural Project stage: Other ML22013A3052021-12-21021 December 2021 Trp 143.4 St Lucie SLRA - Breakout Questions HELB Project stage: Other ML22013A2922021-12-21021 December 2021 Trp 41 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A3042021-12-21021 December 2021 Trp 143.3 St Lucie SLRA - Breakout Questions EAF Project stage: Other ML22013A3032021-12-21021 December 2021 Trp 143.2 St Lucie SLRA - Breakout Questions Non-Class 1 Fatigue Project stage: Other ML22013A3022021-12-21021 December 2021 Trp 143.1 St Lucie SLRA - Breakout Questions Class 1 Fatigue Project stage: Other ML22013A3012021-12-21021 December 2021 TRP60 St. Lucie SLRA - Breakout Questions Fatigue Monitoring Project stage: Other ML22013A2962021-12-21021 December 2021 Trp 74 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A2952021-12-21021 December 2021 Trp 47 St. Lucie SLRA - Breakout Questions Project stage: Other ML22013A2942021-12-21021 December 2021 Trp 46 St. Lucie SLRA - Breakout Questions Structures Monitoring Project stage: Other ML22013A2882021-12-21021 December 2021 Trp 23 & 147.8 St. Lucie SLRA - Breakout Questions Cranes AMP-TLAA Project stage: Other ML22013A2842021-12-21021 December 2021 Trp 18 St. Lucie SLRA - Breakout Questions Bolting Integrity Project stage: Other ML22013A2822021-12-21021 December 2021 SLRA - Breakoutt Questions Corrosion OE Project stage: Other ML22013A2932021-12-21021 December 2021 Trp 45 St. Lucie SLRA - Breakout Questions Masonry Walls Project stage: Other ML21356A5772021-12-22022 December 2021 Slar Breakout Questions - Fire Protection Scoping and Screening Project stage: Approval ML22010A0942022-01-0404 January 2022 Trp 29 St. Lucie SLRA - Tank Breakout Project stage: Other ML22010A0962022-01-0505 January 2022 Trp 010 St Lucie SLRA - Boricacidcorrbreakoutq - Makar Project stage: Other ML22010A1002022-01-0707 January 2022 Trp 033 Psl Selective Leaching Breakout Questions - Allik Project stage: Other ML22010A0972022-01-0707 January 2022 Trp 038 Psl Internal Surfaces Breakout Questions - Allik Project stage: Other ML22012A2822022-01-10010 January 2022 TRP142- St. Lucie SLRA Section 4.2 - Breakout Questions Project stage: Other ML22012A2632022-01-10010 January 2022 Trp 3 - St. Lucie Psl SLRA Breakout Question Reactor Head Closure Stud Bolting Project stage: Other ML22012A3912022-01-11011 January 2022 Scoping and Screening 2.3.3.2 & 2.3.3.4 St. Lucie SLRA - Breakout Questions Project stage: Other ML22130A6542022-01-11011 January 2022, 21 January 2022 SLRA - Audit Report - Audit Questions Transmitted to Florida Power & Light (FPL) Project stage: Request ML22013A3342022-01-11011 January 2022 TRP16 - St. Lucie SLRA Breakout Questions_Pwr Internals Project stage: Other ML22013A3072022-01-11011 January 2022 Trp 084 St Lucie SLRA - Ssnial Scclombreakoutq Project stage: Other ML22013A3172022-01-12012 January 2022 Trp 030 - St. Lucie SLRA Breakout Questions_Fuel Oil Project stage: Other ML22013A3162022-01-12012 January 2022 Trp 020 - St. Lucie SLRA Breakout Questions_Occw Project stage: Other L-2022-043, Subsequent License Renewal Application Revision 1 - Supplement 12022-04-0707 April 2022 Subsequent License Renewal Application Revision 1 - Supplement 1 Project stage: Supplement L-2022-044, Subsequent License Renewal Application Revision 1, Supplement 22022-04-13013 April 2022 Subsequent License Renewal Application Revision 1, Supplement 2 Project stage: Supplement L-2022-071, Subsequent License Renewal Application Revision 1 - Supplement 32022-05-19019 May 2022 Subsequent License Renewal Application Revision 1 - Supplement 3 Project stage: Supplement L-2022-075, Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 1A Response and Request for Confirmation of Information (RCI) Set 1 Response2022-06-13013 June 2022 Subsequent License Renewal Application-Aging Management Requests for Additional Information (RAI) Set 1A Response and Request for Confirmation of Information (RCI) Set 1 Response Project stage: Request ML22188A0862022-07-0707 July 2022 SLRA - Audit Report Project stage: Other L-2022-108, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response2022-07-11011 July 2022 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 2 Response Project stage: Other 2022-01-10
[Table View] |
Text
U.S. Nuclear Regulatory Commission Attn: Document Control Desk 11545 Rockville Pike One White Flint North Rockville, MD 20852-2746 St. Lucie Nuclear Plant Units 1 and 2 Dockets 50-335 and 50-389 Renewed Facility Operating Licenses DPR-67 and NPF-16 SUBSEQUENT LICENSE RENEWAL APPLICATION REVISION 1 - SUPPLEMENT 6
Reference:
L-2023-097 10 CFR 54.17 July 13, 2023
- 1.
Florida Power & Light Company (FPL) letter L-2021-192, Subsequent License Renewal Application - Revision 1, October 12, 2021 (ADAMS Package Accession No. ML21285A106)
- 2.
FPL letter L-2022-043, Subsequent License Renewal Application Revision 1 -
Supplement 1, April 7, 2022 (ADAMS Accession No. ML22097A202)
- 3.
FPL Letter L-2023-059, dated April 21, 2023 - Subsequent License Renewal Application -Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response (ADAMS Accession No. ML23111A129)
Florida Power & Light Company (FPL), owner and licensee for the St. Lucie Nuclear Plant (PSL) Units 1 and 2, has submitted a revised and supplemented subsequent license renewal application (SLRA) for the Facility Operating Licenses for PSL Units 1 and 2 (References 1-3). The Attachment to this letter provides a sixth supplement to the SLRA. The Attachment provides clarification of SLRA Unit 2 Commitments 23 as a final clean version of the commitment, incorporating all prior revisions from previous supplements and responses to RAls.
Should you have any questions regarding this submission, please contact Mr. Michael Davis, Fleet Licensing Projects Manager, at 319-851-7032.
Florida Power & Light Company 6501 S. Ocean Drive, Jensen Beach, FL 34957
St. Lucie Nuclear Plant Units 1 and 2 Dockets 50-335 and 50-389 I declare under penalty of perjury that the foregoing is true and correct.
Executed on the 13th day of July 2023.
Sincerely, Dianne Strand General Manager Regulatory Affairs Florida Power & Light Company Attachment Cc:
Regional Administrator, USNRC, Region II Senior Resident Inspector, USNRC, St. Lucie Plant Chief, USNRC, Division of New and Renewed Licenses L-2023-097 Page 2 of 2 Senior Project Manager, USNRC, Division of New and Renewed Licenses Chief, Bureau of Radiation Control, Florida Department of Health
St. Lucie Nuclear Plant Units 1 and 2 Dockets 50-335 and 50-389 SLRA Supplement 6 Attachment Clarification of PSL Unit 2 SLRA Commitment 23 (2 pages follow)
L-2023-097
St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 L-2023-097 Attachment 1 Page 1 of 2 Clarification of PSL Unit 2 Commitment No. 23 Affected SLRA Sections: Appendix A2, Section 19.4, Table 19-3, Commitment No. 23 Issues The response to Supplement 1, Attachment 7, page 18 of 33 (Ref. 1 ), made changes to the Implementation Schedule of Commitment No. 23. The response to RAI Set 4 Supplemental Response, Attachment 2, page 13 of 15 (Ref. 2), inadvertently omitted the Implementation Schedule changes previously made by Supplement 1, Attachment 7 (Ref. 1 ).
Resolutions For clarification, the final version of SLRA Appendix A2, Section 19.4, Table 19-3, Commitment No. 23, with all the appropriate revisions, is provided on the following page.
References
- 1. FPL Letter L-2022-043 dated April 7, 2022 - Subsequent License Renewal Application Revision 1 - Supplement 1 (ADAMS Accession No. ML22097A202)
- 2. FPL Letter L-2023-059 dated April 21, 2023 - Subsequent License Renewal Application
- Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response (ADAMS Accession No. ML23111A129)
No.
23 St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 L-2023-097 Attachment 1 Page 2 of 2 SLRA Appendix A2, Section 19.4, Table 19-3, page A2-89, is clarified as follows:
Table 19-3 List of Unit 2 SLR Commitments and Implementation Schedule Aging Management NUREG-2191 Commitment Program or Activity Section (Section)
One-Time Inspection XI.M32 a)
Implement the new PSL One-Time Inspection AMP. The new (19.2.2.20)
AMP will include volumetric examinations consistent with Table XI.M32-1 of NUREG-2191 XI.M32 One-Time Inspection program to examine the PSL Unit 2 EOG heat exchanger (radiator tubes) for the loss of material and cracking aging effects.
Implementation Schedule Program inspections begin 10 years before the SPEO.
Inspections that are to be completed prior to the SPEO are completed 6 months prior to the SPEO or no later than the last refueling outage prior to the SPEO.
Program and SLR enhancements are implemented 6 months prior to the SPEO, i.e.:
PSL2: 10/06/2042