Letter Sequence Other |
---|
CAC:MF5372, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4B (Approved, Closed) CAC:MF5373, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4B (Approved, Closed) EPID:L-2014-LLA-0002, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4B (Approved, Closed) |
|
MONTHYEARML16036A3072016-02-18018 February 2016 Regulatory Audit Plan in Support of the License Amendment Requests to Implement Risk-Informed Technical Specifications Initiative 4b Project stage: Other ML16105A4592016-04-14014 April 2016 NRR E-mail Capture - Request for Additional Information Re. Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI ML16110A0042016-04-18018 April 2016 NRR E-mail Capture - Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI ML16154A3392016-06-0101 June 2016 NRR E-mail Capture - Request for Additional Information Re. Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI L-2016-116, Response to Request for Additional Information Regarding License Amendment Request 236, Revision to TS to Adopt Risk Informed Completion Time TSTF-505, Revision 1,Provide Risk-Informed Extended Completion Times.2016-06-16016 June 2016 Response to Request for Additional Information Regarding License Amendment Request 236, Revision to TS to Adopt Risk Informed Completion Time TSTF-505, Revision 1,Provide Risk-Informed Extended Completion Times. Project stage: Response to RAI ML16154A0122016-06-21021 June 2016 Summary of NRC Audit of Turkey Point Nuclear Generating Unit Nos. 3 and 4 for License Amendment Request No. 236 Project stage: Other L-2016-136, Second Response to Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide...2016-08-11011 August 2016 Second Response to Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide... Project stage: Response to RAI L-2017-006, Supplement to License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b.2017-02-0909 February 2017 Supplement to License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b. Project stage: Supplement ML17090A1252017-03-30030 March 2017 NRR E-mail Capture - Request for Additional Information Re. Turkey Point TSTF-505 LAR 236 (CACs MF5455 and MF5456) Project stage: RAI L-2017-063, Response to Third Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide ...2017-04-27027 April 2017 Response to Third Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide ... Project stage: Request ML17213A2102017-06-27027 June 2017 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: Draft RAI ML17222A2312017-07-18018 July 2017 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: Draft RAI ML17222A0042017-08-0303 August 2017 NRR E-mail Capture - Additional Draft RAI Related to the Turkey Point TSTF-505 LAR Project stage: Draft RAI ML17223A0612017-08-10010 August 2017 NRR E-mail Capture - Request for Additional Information - Turkey Point 3 & 4 LAR-236 (CACs MF5455 & MF5456) Project stage: RAI L-2017-168, Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed..2017-10-30030 October 2017 Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.. Project stage: Request L-2018-006, Third Response to Request for Additional Information Regarding License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Risk Informed Extended Completion Times - RITSTF Initiative 4b2018-02-0101 February 2018 Third Response to Request for Additional Information Regarding License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Risk Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Response to RAI L-2018-001, Supplement to Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide..2018-02-15015 February 2018 Supplement to Response to Fourth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide.. Project stage: Supplement ML18061A0172018-03-0101 March 2018 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 256 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: RAI L-2014-000, Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed....2018-03-22022 March 2018 Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.... Project stage: Request L-2018-061, Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed....2018-03-22022 March 2018 Response to Fifth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.... Project stage: Request ML18138A0002018-04-19019 April 2018 NRR E-mail Capture - Draft Request for Additional Information - Turkey Point 3 and 4 LAR 236 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: Draft RAI ML18138A4652018-05-17017 May 2018 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4, Request for Additional Information Regarding License Amendment Request 236 (CAC Nos. MF5455 and MF5456; EPID L-2014-0002) Project stage: RAI ML18141A8222018-05-21021 May 2018 NRR E-mail Capture - St. Lucie Plant, Unit Nos. 1 and 2 - Audit Plan and Setup of Online Reference Portal (CAC Nos. MF5372 and MF5373; EPID L-2014-LLA-0001) Project stage: Other L-2018-111, Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2018-06-0707 June 2018 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Supplement L-2018-118, Response to Sixth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed..2018-06-12012 June 2018 Response to Sixth Request for Additional Information Regarding License Amendment Request 236, Revision to the Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed.. Project stage: Request ML18151A4342018-06-14014 June 2018 Summary of NRC Audit Regarding License Amendment Request to Adopt Risk-Informed Completion Times in Technical Specifications (CAC Nos. MF5372 and MF5373; EPID L-2014-LLA-0002) Project stage: Other ML18179A4332018-07-23023 July 2018 Summary of Regulatory Audit from 5/22 to 6/7/18, Implement Technical Specification Task Force Traveler TSTF-505, Rev, 1, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b Project stage: Other L-2018-150, Third Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.2018-09-18018 September 2018 Third Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. Project stage: Supplement ML18291A7492018-10-0404 October 2018 Submittal of Amendment 29 to Updated Final Safety Analysis Report and License Renewal 10CFR54.37(b) Report Project stage: Request ML18303A2432018-10-26026 October 2018 NRR E-mail Capture - (External_Sender) NRC Notification of State of Florida Regarding Turkey Point 3 and 4 License Amendments - Regarding the Addition of Risk-Informed Completion Times Project stage: Other L-2018-215, Resubmittal of Fourth Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2018-11-30030 November 2018 Resubmittal of Fourth Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Supplement ML18270A4292018-12-0303 December 2018 Issuance of Amendments Nos. 284 and 278 Regarding Adoption of Risk-Informed Completion Times in Technical Specifications (CAC Nos. MF5455 and MF5456; EPID L-2014-LLA-0002) Project stage: Approval ML19113A0242019-04-22022 April 2019 NRC Notification of State of Florida Regarding St. Lucie License Amendments - Regarding the Addition of Risk-Informed Completion Times Project stage: Other ML19113A0992019-07-0202 July 2019 Issuance of Amendments Regarding Adoption of Risk-Informed Completion Times in Technical Specifications Project stage: Approval 2018-10-04
[Table View] |
|
---|
Category:Letter
MONTHYEARL-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums IR 05000335/20250102024-10-21021 October 2024 Notification of St. Lucie Plant Units 1 & 2 Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000335/2025010 and 05000389/2025010 ML24227A9702024-10-18018 October 2024 Letter to Kenneth Mack Dir, License and Reg Compliance, NextEra Energy, Inc Response to Request Re Engagement Re Sub License Renewal Environmental Review - St Lucie Nuclear Plant 1 and 2 L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) ML24255A3092024-09-30030 September 2024 SLRA - Revised SE Letter L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes 05000335/LER-2024-001, Unplanned Reactor Scram2024-09-25025 September 2024 Unplanned Reactor Scram IR 05000335/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000335/2024011 and 05000389/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 IR 05000335/20240052024-08-22022 August 2024 Updated Inspection Plan for St. Lucie, Units 1 & 2 - Report 05000335/2024005 and 05000389/2024005 L-2024-140, Cycle 28 Core Operating Limits Report2024-08-14014 August 2024 Cycle 28 Core Operating Limits Report L-2024-133, Snubber Program Plan Submittal2024-08-14014 August 2024 Snubber Program Plan Submittal L-2024-132, 2024 Population Update Analysis2024-08-13013 August 2024 2024 Population Update Analysis IR 05000335/20240022024-08-13013 August 2024 Integrated Inspection Report 05000335-2024002 and 05000389-2024002 L-2024-129, Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval2024-08-0707 August 2024 Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review 05000389/LER-2024-003, Unplanned Reactor Scram2024-08-0505 August 2024 Unplanned Reactor Scram L-2024-121, Subsequent License Renewal Commitment 30 Revision2024-07-30030 July 2024 Subsequent License Renewal Commitment 30 Revision L-2024-123, Submittal of In-Service Inspection Program Owners Activity Report (OAR-1)2024-07-29029 July 2024 Submittal of In-Service Inspection Program Owners Activity Report (OAR-1) L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000389/LER-2024-002-01, Safety Injection Tank Vent Through Wall Leakage2024-07-11011 July 2024 Safety Injection Tank Vent Through Wall Leakage L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review ML24172A1562024-06-27027 June 2024 Relief Request - PSL2-I5-RR-01 Proposed Alternative to Amse Code XI Code Examination Requirements - System Leakage Test of Reactor Pressure Vessel Bottom Head and Class 1 and 2 Piping in Covered Trenches L-2024-104, Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 102024-06-26026 June 2024 Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 L-2024-097, Technical Specification Special Report2024-06-20020 June 2024 Technical Specification Special Report L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-090, Revised Steam Generator Tube Inspection Reports2024-06-0404 June 2024 Revised Steam Generator Tube Inspection Reports IR 05000335/20244012024-06-0303 June 2024 Security Baseline Inspection Report 05000335/2024401 and 05000389/2024401 ML24135A0642024-05-17017 May 2024 Correction Letter - Amendment Nos. 253 and 208 Regarding Conversion to Improved Standard Technical Specifications L-2024-075, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-05-13013 May 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation IR 05000335/20240012024-05-10010 May 2024 Integrated Inspection Report 05000335/2024001 and 05000389/2024001 ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-053, License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis2024-04-30030 April 2024 License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis L-2024-070, Cycle 32 Core Operating Limits Report2024-04-29029 April 2024 Cycle 32 Core Operating Limits Report L-2024-071, Cycle 27 Core Operating Limits Report2024-04-29029 April 2024 Cycle 27 Core Operating Limits Report ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection L-2024-064, Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report2024-04-17017 April 2024 Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report L-2024-056, Annual Radiological Environmental Operating Report for Calendar Year 20232024-04-17017 April 2024 Annual Radiological Environmental Operating Report for Calendar Year 2023 L-2024-054, 2023 Annual Environmental Operating Report2024-04-0909 April 2024 2023 Annual Environmental Operating Report 2024-09-09
[Table view] Category:Schedule and Calendars
MONTHYEARL-2024-026, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-02-27027 February 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter ML22322A0372022-11-18018 November 2022 SLRA Intent to Change Schedule Letter ML21246A0912021-09-24024 September 2021 Letter - St. Lucie Plant, Units 1 and 2 - Determination of Acceptability, Proposed Review Schedule, and Opportunity for a Hearing Regarding the FPL SLRA ML18151A4342018-06-14014 June 2018 Summary of NRC Audit Regarding License Amendment Request to Adopt Risk-Informed Completion Times in Technical Specifications (CAC Nos. MF5372 and MF5373; EPID L-2014-LLA-0002) L-2014-166, NRC Regulatory Issue Summary 2014-05 Preparation and Scheduling of Operator Licensing Examinations2014-06-0606 June 2014 NRC Regulatory Issue Summary 2014-05 Preparation and Scheduling of Operator Licensing Examinations L-2013-214, NRC Regulatory Issue Summary 2013-06 Preparation and Scheduling of Operator Licensing Examinations2013-07-0505 July 2013 NRC Regulatory Issue Summary 2013-06 Preparation and Scheduling of Operator Licensing Examinations L-2011-229, NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations2011-07-0606 July 2011 NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examinations 2024-02-27
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 14, 2018 Mr. Mano Nazar President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company Mail Stop EX/JB 700 Universe Blvd .
Juno Beach, FL 33408
SUBJECT:
ST. LUCIE PLANT, UNIT NOS. 1 AND 2 -
SUMMARY
OF NRC AUDIT REGARDING LICENSE AMENDMENT REQUEST TO ADOPT RISK-INFORMED COMPLETION TIMES IN TECHNICAL SPECIFICATIONS (CAC NOS. MF5372 AND MF5373; EPID L-2014-LLA-0001)
Dear Mr. Nazar:
By application dated December 5, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14353A016), Florida Power & Light Company submitted a License Amendment Request (LAR) to revise the St. Lucie Plant, Unit Nos. 1 and 2 (St. Lucie)
Technical Specifications to adopt risk-informed completion times in accordance with the Technical Specifications Task Force (TSTF) Traveler-505, Revision 1, "Provide Risk-Informed Extended Completion Times - RITSTF [Risk Informed TSTF] Initiative 4b" (ADAMS Accession No. ML111650552).
On February 22 and 23, 2016 , the U.S. Nuclear Regulatory Commission (NRC) staff and its contractors from the Pacific Northwest National Laboratory participated in a regulatory audit of St. Lucie at the NextEra Energy Offices in Juno Beach, Florida. The purpose of the audit was to understand what information the NRC staff needed to support its review of the LAR and to develop requests for additional information, as needed. provides the schedule of activities during the audit. Enclosure 2 provides the list of audit participants. Enclosure 3 contains a list of documents reviewed by the team .
M. Nazar. If you have any questions, please contact me at (301) 415-6459 or Michael.Wentzel@nrc.gov.
Sincerely, Michael J. Wentz I Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389
Enclosures:
- 1. Audit Schedule
- 2. Audit Participants
- 3. Audit Documents cc: Listserv
Schedule of Activities Monday, February 22, 2016 8:30 AM Introductions Presentation on Risk-Informed Completion Time (RICT) Program Overview
- Discussion of license amendment request and RICT Program
- Discussion on how external events are considered for the RICT
- Discussion on how risk management actions are determined and implemented 11:30 AM Lunch 12:30 PM Presentation on Probabilistic Risk Assessment (PRA) functional definition, development, and use (PRA Request for Additional Information (RAI) 9)
Discussion of other RAls - PRA, Instrumentation and Control, and Technical Specifications 4:00 PM End of the Day Briefings Tuesday, February 23, 2016 8:30 AM Presentation on Configuration Risk Management Program (CRMP) demonstration (including presentation of user interface for evaluations)
- Discussion of reviews and acceptance testing of the CRMP model
- Discussion on how the CRMP is maintained consistent with baseline PRA model Discussion of other RAls - PRA, Instrumentation and Control, and Technical Specifications 11:30 AM Lunch 12:30 PM Presentation on Walkthrough sample RICT calculations
- Discussion of reviews and acceptance testing of the CRMP model
\
- Discussion on how cumulative risk will be evaluated and tracked 4:00 PM End of the Day Briefings Enclosure 1
List of Participants U.S. Nuclear Regulatory Commission Team
- Stacey Rosenberg, Branch Chief
- Margaret Chernoff, Technical Reviewer*
- Phone participant Pacific Northwest National Laboratory Team
- Garill Coles, Risk Analyst
- Steve Short, Risk Analyst Florida Power & Light Company/NextEra Energy Company
- William Cross Florida Power & Light Company/NextEra Energy Company Contractor
- Andrew Howe, JBC Nuclear, Inc., Consultant Enclosure 2
List of Documents Reviewed
- 1. Hurricane Procedure
- 2. Configuration Management
- 3. Risk-Informed Completion Time (RICT) Calculations
- 4. Configuration Risk Management Program Procedure
- 5. Protected Train Procedure
- 6. NextEra Energy Audit Kick-Off Presentation (Presentation)
- 7. St. Lucie Risk-Managed Technical Specifications Overview (Presentation)
- 8. Overview of NextEra. Energy License Amendment Request (Presentation)
- 9. Electric Power Research Institute Phoenix Risk Monitor Implementation Overview (Presentation)
- 10. St. Lucie Sample RICT Calculations (Presentation)
Enclosure 3
M. Nazar.
SUBJECT:
ST. LUCIE PLANT, UNIT NOS. 1 AND 2 -
SUMMARY
OF NRC AUDIT REGARDING LICENSE AMENDMENT REQUEST TO ADOPT RISK-INFORMED COMPLETION TIMES IN TECHNICAL SPECIFICATIONS (CAC NOS. MF5372 AND MF5373; EPID L-2014-LLA-0001)
DATEDJUNE 14, 2018 DISTRIBUTION:
PUBLIC RidsRgn2MailCenter PM File Copy LFields, NRR RidsACRS MailCTR JEvans, NRR RidsNrrDorlLpl2-2 SDinsmore, NRR RidsNrrDraApla NCarte, NRR RidsNrrDssStsb MChernoff, NRR RidsNrrDeEicb PBuckberg, NRR RidsNrrLABClayton AKlett, NRR RidsNrrPMStLucie ADAMS Accession No.:
- b memorandum NAME MWentzel SRosenberg BVenkataraman MWentzel DATE 05/25/16 f;J I I~ /18 Ul I /~ /18 OFFICIAL RECORD ONLY