MONTHYEARML20217N4611999-10-22022 October 1999 Forwards Revised Pages 11,14 & 71 of Rept & Order Dtd 990608.Revs Are Textual Changes to Clarify & Confirm Action Taken by Nuclear Decommissioning Financing Committee ML20216F5061999-09-16016 September 1999 Forwards Monthly Rept on Status of 10CFR2.206 Petitions as of 990831.During August,Director'S Decision (DD-99-10) on Seabrook Issued & Petition Closed.Six Petitions Open,Five in NRR & One in Nmss.Attachment 2 Withheld ML20210K4141999-08-0404 August 1999 Forwards Signed Originals of DD Issued Under 10CFR2.206. Without Encl ML20210C1631999-07-19019 July 1999 Forwards Monthly Rept Which Gives Status of 10CFR2.206 Petitions as of 990630.Six Open NRR,1 OE & 2 NMSS Petitions Available.Attachment 2 Withheld ML20206U9631999-05-18018 May 1999 Notification of Significant Licensee Meeting 99-27 with Util on 990602 to Discuss Predecisional Enforcement Conference - NRC Investigation ML20206R1691999-05-0707 May 1999 Rev 1 to Notification of 990602 Significant Licensee Meeting with Listed Attendees in King of Prussia,Pa Re Predecisional Enforcement Conference Concerning NRC Investigation.Rev Sighted Date Change ML20207G5681999-03-0808 March 1999 Informs That Commission Memorandum & Order (CLI-99-06), Issued on 990305,appointed TS Moore as Presiding Officer for Seabrook License Transfer Proceeding.With Certificate of Svc.Served on 990309 ML20197H1211998-12-0808 December 1998 Forwards Exam Rept with as Given Written Exam for Test Administered at Facility on 981019-23 ML20195C7641998-11-13013 November 1998 Forwards Pages That Were Faxed to J Peschel on 981113 in Preparation for Telcon That Will Be Scheduled Wk of 981116. Info in Attached Pages Based on Info Obtained from Licensee & Includes Specific Subjects to Be Discussed with Licensee ML20153E4211998-09-24024 September 1998 Informs That Ofc of Secretary Experienced Problems with Listed e-mail Address.Alternate Mailbox Has Been Created in Effort to Maintain Electronic Mailbox for Parties Filing by e-mail.With Certificate of Svc.Served on 980924 ML20153G0231998-09-24024 September 1998 Informs That Office of Secretary Experienced Problems with Dedicated e-mail Address.In Effort to Maintain Electronic Mailbox for Parties Filing by e-mail,alternate Mailbox Created.With Certificate of Svc.Served on 980924 ML20239A3361998-09-0404 September 1998 Forwards Request for Hearing & Submitted by RA Backus on Behalf of Seacoast Anti-Pollution League & New England Coalition on Nuclear Pollution Re Proposed License Amend for Seabrook Unit 1 ML20249A6691998-06-15015 June 1998 Forwards Request for Hearing, & Submitted by RA Backus on Behalf of Seacoast Anti-Pollution League. Petition Was Filed in Response to Notice of Proposed Determination by Staff ML20217M7161998-04-0303 April 1998 Notification of 980219 Meeting W/North Atlantic Energy Svc Corp in Rockville,Md to Discuss Great Power Corp Response to RAI Re Decommissioning Funding Assurance ML20216G5891998-03-0606 March 1998 Notification of Significant Licensee Meeting 98-25 W/Util on 980324 Predecisional Enforcement Conference to Discuss Apparent Violation in Insp Rept 50-443/97-08 (EA-98-073) ML20198S4161998-02-26026 February 1998 Submits Impact of New Decommissioning Funding Rule on Great Bay.Staff Intends to Propose Some Addl Mechanisms That Appear to Offer Assurance Equivalent to What Existing Mechanisms Provide ML20203B9021998-02-0909 February 1998 Notification of 980219 Meeting W/North Atlantic Energy Service Corp in North Bethesda,Md to Discuss Proposed License Amends to Support Current Operating Cycle & Plans for Conversion to Improved Standard TSs ML20199E8881998-01-23023 January 1998 Notification of 980204 Mgt Meeting W/North Atlantic Energy Svc Corp in Rockville,Maryland to Discuss SALP for Period Covering 960505-971206 as Documented in SALP Rept 50-443/97-99 ML20198N0191998-01-0909 January 1998 Forwards Draft Rept, ,to Docket for Seabrook Station,Unit 1.Draft Rept Provides Licensee Preliminary Root Cause Analysis for Leaks in Piping of B Train of RHR System.Leakage Reported by Licensee on 971205 ML20203D2971997-12-0909 December 1997 Notification of 971216 Meeting W/Utils in Rockville,Md to Discuss Decommissioning Funding Assurance ML20211E7301997-09-23023 September 1997 Notification of 971028 Meeting W/North Atlantic Energy Service Corp in Rockville,Md to Discuss Approach for Extending Surveillances to 24-month Intervals ML20217B0471997-09-11011 September 1997 Notification of 970924 Meeting W/Eastern Utility Associates & North Atlantic Energy Service Corp in Rockville,Md to Discuss Proposed Electric Generating Asset Divestiture Plan ML20141D8191997-06-26026 June 1997 Forward 970624 Memo from P Milano to C Hehl Re Response to TIA Concerning Vantage 5H ZIRLO Fuel Problems at Plant,To Be Placed on Docket 50-443 & Made Publicly Available ML20141C9921997-06-24024 June 1997 Responds to 970605 TIA Re VANTAGE-5H ZIRLO Fuel Problems at Seabrook.Staff Has Not Identified Any Restart Concerns Re Reloading of VANTAGE-5H ZIRLO Fuel Used During Cycle 5 & W/Fresh VANTAGE-5H ZIRLO Fuel for Cycle 6 at Plant ML20136C1031997-03-0606 March 1997 Forwards Correspondence Transmitted Via Internet to J Zwolinski from P Blanch During 970102-31.Requests Correspondence Be Placed in PDR ML20134H7931996-11-0606 November 1996 Partially Deleted Memo Re 950502 Meeting W/Northeast Utilities Re Listed Topics ML20129K2561996-11-0505 November 1996 Notification of Significant Licensee Meeting 96-109 W/Listed Attendees on 961202-03 in Philadelphia,Pa to Provide Training,Resolve Interagency Exercise Scheduling Conflicts & Discuss Current Issues in Emergency Preparedness ML20134D7161996-10-24024 October 1996 Requests That Encl Internet Mail Received from PM Blanch,Dtd Through 960930,be Placed in Pdr.No Distribution Outside of PDR Necessary ML20129C0271996-10-11011 October 1996 Notification of 961030 Public Meeting of Nuclear Decommissioning Committee ML20129E2011996-09-25025 September 1996 Notification of 960930 Meeting W/Util in Rockville,Md to Discuss Status of Great Bay Power Corp as Electric Util ML20147J3281996-07-10010 July 1996 Discusses Staff Response to SRM M960612, Briefing on Part 100 Final Rule on Reactor Site Criteria. Staff Believes That Draft Final Rule Language May Be Misinterpreted as Implicity Overruling in Conflict W/Seabrook Decision ML20129D1831996-07-10010 July 1996 Informs of 960716 Visit W/B Patricelli,Cm Cleveland & Gw Davis of Northeast Utilities,Inc Re Introductions & Discussions of Millstone Point & Haddam Neck Issues ML20134B6681995-10-13013 October 1995 Forwards Briefing Package on Status of Listed Plant Units,As Background for Visit by Northeast Utils on 951018-19 ML20087B8531995-07-25025 July 1995 Forwards State of Nh Nuclear Decommissioning Finance Committee Third Supplemental Order Approving Revised Funding Schedule by North Atlantic Energy Svc Corp ML20134B5861995-06-0101 June 1995 Forwards Briefing Package on Status of Plants as Background for Util Visit on 950608 ML20134B5721995-04-26026 April 1995 Forwards Briefing Package on Status of Listed Plants,As Background for Visit by Util on 950502.Supporting Documentation Encl ML20078S9391994-12-23023 December 1994 Forwards State of Nh Nuclear Decommissioning Finance Committee (Ndfc) Ndfc 93-1, Brief of Nh Public Utilities Commission Staff NUREG-1299, Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl1994-06-29029 June 1994 Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl ML20134B4931994-02-16016 February 1994 Forwards Updated Briefing Package for Visit by Util Officials W/Nrc Chairman,Commission,Edo,Director OI & Director Oe.Requests Replacement of Encls 1 & 2 in 940215 Package,Retaining Supporting Attachment 1 Documentation ML20059J8371994-01-0606 January 1994 Notification of Significant Licensee Meeting 94-05 W/Util Emergency Preparedness Mgt Working Group on 940210 ML20058L9281993-12-15015 December 1993 Notification of 931221 Meeting W/North Atlantic Energy Svc Corp,Yaec & Intl Tech Svcs,Inc in Rockville,Md to Discuss Application of YAEC-1856P Methodology to Plant ML20058C9681993-11-19019 November 1993 Notification of Significant Licensee Meeting 93-147 W/Util on 931208 Re SALP Mgt Meeting for Period of 920301-930828 ML20059J2321993-11-0505 November 1993 Forwards Safety Evaluation Accepting LAR 92-14,submitted Via for TS Changes to Allow Independent Fixed Incore Detector Sys at Facility to Be Used for Periodic in-core Power Distribution TS SRs ML20128K8601993-02-0202 February 1993 Notification of Significant Licensee Meeting 93-13 W/Util on 930210 to Discuss General Engineering Programs ML20126K1461993-01-0505 January 1993 Notification of 930106 Meeting W/Util in Rockville,Md to Discuss Transfer of Control of Interest of Eua Power in Plant ML20126J6211992-12-24024 December 1992 Forwards LER 88-009-01 Issued on 921113,discussing Increased Thrust Bearing Loading for RHR Pumps When Pumps Run at Reduced Flows.Concern Raised That Inservice Testing May Not Detect Problem Soon Enough to Avoid Failure ML20125B4461992-11-30030 November 1992 Notification of 921203 Licensee Meeting in King of Prussia, PA to Discuss Auxiliary Operator re-licensing Plans ML20128C2131992-11-16016 November 1992 Notification of Postponement of 921124 Meeting W/Util in King of Prussia,Pa to Discuss Process for Reissuing Reactor Operator Licenses Terminated After Auxiliary Operator Performance Review ML20128C0271992-11-13013 November 1992 Notification of Significant Licensee Meeting 92-168 W/Util on 921124 to Discuss Process for Reissuing RO Licenses That Have Been Terminated After an AO Performance Review ML20097B5821992-05-27027 May 1992 Recommends That Methodology Specified in Order 20,475 Be Revised to Require Util to Include in Base Rates,Amounts Required by Nuclear Decommission Financing Committee 17th Supplemental Order 1999-09-16
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20217N4611999-10-22022 October 1999 Forwards Revised Pages 11,14 & 71 of Rept & Order Dtd 990608.Revs Are Textual Changes to Clarify & Confirm Action Taken by Nuclear Decommissioning Financing Committee ML20217J8951999-10-21021 October 1999 Staff Requirements Memo Re Affirmation Session on 991021, Rockville,Md (Open to Public Attendance) ML20216F5061999-09-16016 September 1999 Forwards Monthly Rept on Status of 10CFR2.206 Petitions as of 990831.During August,Director'S Decision (DD-99-10) on Seabrook Issued & Petition Closed.Six Petitions Open,Five in NRR & One in Nmss.Attachment 2 Withheld ML20210K4141999-08-0404 August 1999 Forwards Signed Originals of DD Issued Under 10CFR2.206. Without Encl ML20210C1631999-07-19019 July 1999 Forwards Monthly Rept Which Gives Status of 10CFR2.206 Petitions as of 990630.Six Open NRR,1 OE & 2 NMSS Petitions Available.Attachment 2 Withheld ML20206U9631999-05-18018 May 1999 Notification of Significant Licensee Meeting 99-27 with Util on 990602 to Discuss Predecisional Enforcement Conference - NRC Investigation ML20206R1691999-05-0707 May 1999 Rev 1 to Notification of 990602 Significant Licensee Meeting with Listed Attendees in King of Prussia,Pa Re Predecisional Enforcement Conference Concerning NRC Investigation.Rev Sighted Date Change ML20207G5681999-03-0808 March 1999 Informs That Commission Memorandum & Order (CLI-99-06), Issued on 990305,appointed TS Moore as Presiding Officer for Seabrook License Transfer Proceeding.With Certificate of Svc.Served on 990309 ML20207F5021999-03-0505 March 1999 Staff Requirements Memo Re 990305 Affirmation Session, Rockville,Md (Open to Public Attendance).Commission Approved Memo & Order Which Granted Util Intervention Petition & Request for Hearing ML20197H1211998-12-0808 December 1998 Forwards Exam Rept with as Given Written Exam for Test Administered at Facility on 981019-23 ML20195C7641998-11-13013 November 1998 Forwards Pages That Were Faxed to J Peschel on 981113 in Preparation for Telcon That Will Be Scheduled Wk of 981116. Info in Attached Pages Based on Info Obtained from Licensee & Includes Specific Subjects to Be Discussed with Licensee ML20153E4211998-09-24024 September 1998 Informs That Ofc of Secretary Experienced Problems with Listed e-mail Address.Alternate Mailbox Has Been Created in Effort to Maintain Electronic Mailbox for Parties Filing by e-mail.With Certificate of Svc.Served on 980924 ML20153G0231998-09-24024 September 1998 Informs That Office of Secretary Experienced Problems with Dedicated e-mail Address.In Effort to Maintain Electronic Mailbox for Parties Filing by e-mail,alternate Mailbox Created.With Certificate of Svc.Served on 980924 ML20239A3361998-09-0404 September 1998 Forwards Request for Hearing & Submitted by RA Backus on Behalf of Seacoast Anti-Pollution League & New England Coalition on Nuclear Pollution Re Proposed License Amend for Seabrook Unit 1 ML20249A6691998-06-15015 June 1998 Forwards Request for Hearing, & Submitted by RA Backus on Behalf of Seacoast Anti-Pollution League. Petition Was Filed in Response to Notice of Proposed Determination by Staff ML20217M7161998-04-0303 April 1998 Notification of 980219 Meeting W/North Atlantic Energy Svc Corp in Rockville,Md to Discuss Great Power Corp Response to RAI Re Decommissioning Funding Assurance ML20216G5891998-03-0606 March 1998 Notification of Significant Licensee Meeting 98-25 W/Util on 980324 Predecisional Enforcement Conference to Discuss Apparent Violation in Insp Rept 50-443/97-08 (EA-98-073) ML20198S4161998-02-26026 February 1998 Submits Impact of New Decommissioning Funding Rule on Great Bay.Staff Intends to Propose Some Addl Mechanisms That Appear to Offer Assurance Equivalent to What Existing Mechanisms Provide ML20203B9021998-02-0909 February 1998 Notification of 980219 Meeting W/North Atlantic Energy Service Corp in North Bethesda,Md to Discuss Proposed License Amends to Support Current Operating Cycle & Plans for Conversion to Improved Standard TSs ML20199E8881998-01-23023 January 1998 Notification of 980204 Mgt Meeting W/North Atlantic Energy Svc Corp in Rockville,Maryland to Discuss SALP for Period Covering 960505-971206 as Documented in SALP Rept 50-443/97-99 ML20198N0191998-01-0909 January 1998 Forwards Draft Rept, ,to Docket for Seabrook Station,Unit 1.Draft Rept Provides Licensee Preliminary Root Cause Analysis for Leaks in Piping of B Train of RHR System.Leakage Reported by Licensee on 971205 ML20203D2971997-12-0909 December 1997 Notification of 971216 Meeting W/Utils in Rockville,Md to Discuss Decommissioning Funding Assurance ML20211E7301997-09-23023 September 1997 Notification of 971028 Meeting W/North Atlantic Energy Service Corp in Rockville,Md to Discuss Approach for Extending Surveillances to 24-month Intervals ML20217B0471997-09-11011 September 1997 Notification of 970924 Meeting W/Eastern Utility Associates & North Atlantic Energy Service Corp in Rockville,Md to Discuss Proposed Electric Generating Asset Divestiture Plan ML20141D8191997-06-26026 June 1997 Forward 970624 Memo from P Milano to C Hehl Re Response to TIA Concerning Vantage 5H ZIRLO Fuel Problems at Plant,To Be Placed on Docket 50-443 & Made Publicly Available ML20141C9921997-06-24024 June 1997 Responds to 970605 TIA Re VANTAGE-5H ZIRLO Fuel Problems at Seabrook.Staff Has Not Identified Any Restart Concerns Re Reloading of VANTAGE-5H ZIRLO Fuel Used During Cycle 5 & W/Fresh VANTAGE-5H ZIRLO Fuel for Cycle 6 at Plant ML20136C1031997-03-0606 March 1997 Forwards Correspondence Transmitted Via Internet to J Zwolinski from P Blanch During 970102-31.Requests Correspondence Be Placed in PDR ML20134H7931996-11-0606 November 1996 Partially Deleted Memo Re 950502 Meeting W/Northeast Utilities Re Listed Topics ML20129K2561996-11-0505 November 1996 Notification of Significant Licensee Meeting 96-109 W/Listed Attendees on 961202-03 in Philadelphia,Pa to Provide Training,Resolve Interagency Exercise Scheduling Conflicts & Discuss Current Issues in Emergency Preparedness ML20134D7161996-10-24024 October 1996 Requests That Encl Internet Mail Received from PM Blanch,Dtd Through 960930,be Placed in Pdr.No Distribution Outside of PDR Necessary ML20129C0271996-10-11011 October 1996 Notification of 961030 Public Meeting of Nuclear Decommissioning Committee ML20129E2011996-09-25025 September 1996 Notification of 960930 Meeting W/Util in Rockville,Md to Discuss Status of Great Bay Power Corp as Electric Util ML20147J3281996-07-10010 July 1996 Discusses Staff Response to SRM M960612, Briefing on Part 100 Final Rule on Reactor Site Criteria. Staff Believes That Draft Final Rule Language May Be Misinterpreted as Implicity Overruling in Conflict W/Seabrook Decision ML20129D1831996-07-10010 July 1996 Informs of 960716 Visit W/B Patricelli,Cm Cleveland & Gw Davis of Northeast Utilities,Inc Re Introductions & Discussions of Millstone Point & Haddam Neck Issues ML20134B6681995-10-13013 October 1995 Forwards Briefing Package on Status of Listed Plant Units,As Background for Visit by Northeast Utils on 951018-19 ML20087B8531995-07-25025 July 1995 Forwards State of Nh Nuclear Decommissioning Finance Committee Third Supplemental Order Approving Revised Funding Schedule by North Atlantic Energy Svc Corp ML20134B5861995-06-0101 June 1995 Forwards Briefing Package on Status of Plants as Background for Util Visit on 950608 ML20134B5721995-04-26026 April 1995 Forwards Briefing Package on Status of Listed Plants,As Background for Visit by Util on 950502.Supporting Documentation Encl ML20078S9391994-12-23023 December 1994 Forwards State of Nh Nuclear Decommissioning Finance Committee (Ndfc) Ndfc 93-1, Brief of Nh Public Utilities Commission Staff NUREG-1299, Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl1994-06-29029 June 1994 Forwards Continuation of Curtiss Papers to Be Filed Under Commission Correspondence in Pdr.Advanced Copy Sent to Pdr. List of Documents Included in Four Boxes Encl ML20134B4931994-02-16016 February 1994 Forwards Updated Briefing Package for Visit by Util Officials W/Nrc Chairman,Commission,Edo,Director OI & Director Oe.Requests Replacement of Encls 1 & 2 in 940215 Package,Retaining Supporting Attachment 1 Documentation ML20059J8371994-01-0606 January 1994 Notification of Significant Licensee Meeting 94-05 W/Util Emergency Preparedness Mgt Working Group on 940210 ML20058L9281993-12-15015 December 1993 Notification of 931221 Meeting W/North Atlantic Energy Svc Corp,Yaec & Intl Tech Svcs,Inc in Rockville,Md to Discuss Application of YAEC-1856P Methodology to Plant ML20058C9681993-11-19019 November 1993 Notification of Significant Licensee Meeting 93-147 W/Util on 931208 Re SALP Mgt Meeting for Period of 920301-930828 ML20059J2321993-11-0505 November 1993 Forwards Safety Evaluation Accepting LAR 92-14,submitted Via for TS Changes to Allow Independent Fixed Incore Detector Sys at Facility to Be Used for Periodic in-core Power Distribution TS SRs ML20128K8601993-02-0202 February 1993 Notification of Significant Licensee Meeting 93-13 W/Util on 930210 to Discuss General Engineering Programs ML20126K1461993-01-0505 January 1993 Notification of 930106 Meeting W/Util in Rockville,Md to Discuss Transfer of Control of Interest of Eua Power in Plant ML20126J6211992-12-24024 December 1992 Forwards LER 88-009-01 Issued on 921113,discussing Increased Thrust Bearing Loading for RHR Pumps When Pumps Run at Reduced Flows.Concern Raised That Inservice Testing May Not Detect Problem Soon Enough to Avoid Failure ML20125B4461992-11-30030 November 1992 Notification of 921203 Licensee Meeting in King of Prussia, PA to Discuss Auxiliary Operator re-licensing Plans ML20128C2131992-11-16016 November 1992 Notification of Postponement of 921124 Meeting W/Util in King of Prussia,Pa to Discuss Process for Reissuing Reactor Operator Licenses Terminated After Auxiliary Operator Performance Review 1999-09-16
[Table view] |
Text
.
t Y
l OCT 2 01975 Docket Nos. 50-443/444 E. Markee, Leader, Meteorology Section, Site Analysis Branch, TR SEABROOK 1 AND 2 EFFLUENT RELEASE POINT DATA I
We have reviewed the Supplement to the Seabrook Enviro:nnental Report dated October 8, 1975 and have determined that the data given in Enclosure A is appropriate for use in your antlysis. The release points are also noted on the attached plot plan. Questions concern-ing these data should be addressed to W. Hewitt, cognizant engineer assigned to this facility.
Original signed byl W. C. Eurke, Leader Applications Section Effluent Treatment Systems Branch favision of Technical Review
Enclosure:
As stated 1 1
- cc: J. Collins W. Gansnill W. Hewitt bec: Docket Files 4 -- ~ - M ETSB Reading File !
h I .
L i l l
8707220104 870717 PDR FDIA PDR p l
- GDREN87-51 o, c., TR
- ETSB TR:dSB
' , , , , , , , , , WHe N ( dune
,,,,,, 10/20/75 10/)b/75 _,,. _
W u. e. oovaammsut ensatino o, recs: sava.see.see Forse ABC.)18 (Rev. 9.$)) AECM 0240 i
)
4
+ i OCT 2 0 E75 SEABROOK RL1 '.SE POINT DA7' Enclosure _A
- 1. All relecscs except turbine building releases occur through plant vent. Plant vent follows contour of containment building up the I i
side to the top of the dome. At the top of the dome it has an {
elbow looking up. The inside dimensions of the plant vents are as follotes: Unit 1 - 6 ft x 9 ft Unit 2 - 5 ft x 7 ft 6 in Elevation of Release Point is 208 ft above MSL Nornal Fic'a Rate--Unit 1 - 232,000 cft Unit 2 - 122,000 cfm Relcase Temperature is 100*F on a design summer day and 50*F on l a design winter day
, Exit Velocity--Unit 1 - 4,500 fpm Unit 2 - 3,300 fpm
- 2. Turbine Building - 10 roof vents flow rate - 54,000 cfm/ vent velocity - 2,600 fpm elevation - 129 ft 6 in above ground 1cyc]
dimensicus - circular, 62 in diameter reaperature. 50*F - 175'T 4
g*# %
UNITto STATES NUCLEAR REGULATORY COMMISSION
[ i# i j WASHINGTON, D. C. 20555
's !
%, * * . . . /
JAN 121979
/
MEMORANDUM FOR: Harold R. Denton, Director, Office of Nuclear Reactor Regulation THRU: Domenic B. Vassallo, Assistant Director for Light Wate Reactors, Division of Project Management i FRON: Emanuel Licitra, Project Manager, Light Water Reactors Branch No. 3, Division of Project Management f i
SUBJECT:
SUPNARY OF MEETING HELD WITH POST-CP APPLICANTS TO DISCUSS OL REVIEW MATTERS At the request of Mr. Harold Denton, Director, NRR, a meeting was held on December 13, 1978 in Bethesda, Maryland with representatives of the utilities, listed in Enclosure 1, with pending OL applications. The purpose of the meeting was to discuss (1) staff policies regarding the review of the pending OL applications, and (2) the criteria for es'Jblishing priorities for the review of those applications. The areas of discussion are identified in Enclosure 2. Enclosure 3 provides a list of the attendees.
Introduction Mr. Denton stated that we recently held meetings with appljcants, for whom we are currently reviewing CP or OL applications, to discuss review schedule matters and staff resources. At those meetings, we had discussed the scope of OL review matters, including the resolution of recurring issues, and the method for establishing review priorities. Since the matters discussed at those meetings are applicable to the review of pending OL applications, Mr. Denton indicated that he thought it appropriate to also discuss those matters with the post-CP applicants.
Review Scope We stated that we currently use the Standard Review Plan in our review of l applications. Since issuance of the Standard Review Plan, staff manpower requirements have increased due to its use. Experience gained from currently operating reactors have also increased staff manpower requirements for case reviews. For example, in 1975, DSS needed about 500 man days to review an OL application but now takes about 1700 man days. Evaluation of novel features, such as a computer protection system, further increase staff ,
manpower requirements. l W' 8$ ,
M S O-J
.)
l l
l Harold R. Denton JAN 121979 l t
l Our review of OL applications will include an eval.ation of Standard Review Plan deviations. Since most, if not all, plants c.rrently in the post-CP (
stage were originally reviewed prior to issuance c' the Standard Review Plan, certain aspects of these applications may ha,e been accepted on some other defined basis. Therefore, where deviations with the Standard Review Plan exist, the staff will be required to identify the basis for acceptar.ce in the SER. 3 j
During the course of our OL reviews, we will also consider Category 2, 3 and 4 items. Category 2 and 3 items pertain to new regulatory guides or branch technical positions, or changes to existing guides and positions, which the Regulatory Requirements Review Comittee (RRRC) has approved i j
for backfit on all plants (Category 3) or backfit en a case by case basis <
(Category 2). Category 4 items pertain to matters which have not been processed through the RRRC but have been approved ty Mr. Denton for ,
application on a case by case basis. Copies of the current Category 2, 3 and 4 items have been transmitted to the post-CP applicants so that they l may be considered in the preparation of their FSAR's. Mr. Denton pointed l out that future considerations by the RRRC on new pides and positions '
will include a period for public comment before any final decisions are made. )
1 An additional review requirement has been imposed by an Appeal Board decision regarding generic issues ( ALAB-444). That decisior states that with regard to unresolved generic issues, the staff should provide the basis for continuing !
licensing and plant operations while the generic issue is being resolved.
Therefore, this matter will also be considered in car review of OL applications.
l Mr. Denton stated that we have proposed a list of la items to the Comission that are currently considered " unresolved safety issues." These issues are a subset of the generic issues which are encompassed Dy the ALAB-444 decision.
We stated that, because of the above considerations, the staff review of an OL application currently takes about 24 months to csnplete. In order to minimize staff manpower requirements, we attempt te perform a common review for similar plants or plant features, where approprf ate. In this regard, Mr. Denton stated that the post-CP applicants should maintain an awareness of how we are resolving issues for plants currently un:er review which are similar to their plants.
Mr. Denton stated that industry car help minimize canpower review requirements by facing up to review issues sooner and by utility management focussing attention on these issues. He added that, with the existence of the Standard Review Plan, the identification of Category 2, 3 and 4 items, and the public awareness of matters to be considered by the RRRC, cur requirements for acceptance are all out in the open. In this regard, Mr. Dentor stated that we would not resort to " arm twisting" to resolve issues and that we would be prepared to go forward to the ACRS or to hearings with differences of opinion if the staff and an applicant cannot reach agreement on an issue.
Harold R. Denton JAN 121979 In response to a question, we stated that if an applicant requests an appeal meeting regarding differences of opinion between the staff and the applicant, the appeal process should start from the lower levels and proceed up to the next level until the issue is resolved. Appeals of Category 2, 3 or 4 items should go directly to Mr. Denton's level since the Director of NRR has already approved these items for consideration in the review process.
Another suggestion for minimizing schedule delays was to have applicants present novel ideas as soon as possible. We also suggested that industry l should think of and recommend other ways to streamline the review process.
In this regard, General Electric plans to meet with us shortly to present their views on the subject.
Submittal of OL Applicants and Establishment of Review Schedule We stated that an applicant should submit its OL application about 30 months i before the projected fuel load date. This submittal time will accommodate a 24 month staff review period, but time only for a limited hearing, if required.
In order to provide the staff with realistic fuel load dates for manpower planning purposes, we utilize the NRC's Caseload Forecast Panel. This panel has established a model which is useful in estimating the fuel load date based on past experience. In order to allocate available staff resources, the panel's forecasted date is also utilized in establishing priorities for the review of OL applications. In establishing review priorities within NRR, operating reactors receive top priority, followed by OL applications and then CP applications.
Where the Caseload Forecast Panel's forecasted fuel load date differs significantly from an applicant's forecasted date (usually because an applicant will use the earliest achievable date), an attempt is made to reconcile i the difference via a site visit prior to OL tendering. In any case, the initial review schedule will be established on the basis of at least meeting the Caseload Forecast Panel fuel load date.
In response to a question, we stated that adjustments to the review schedule (and priorities) can be made, if necessary, but not before the Q-1 phase of review has been completed. Also, the Caseload Forecast Panel will reassess its forecasted fuel load dates on a regular basis, based on changes in the status and pace of construction. The next reassessment is planned for around March of 1979.
l .
Harold R. Denton M 12 M Other Discussion Items Dr. Mattson stated that one of the major recurring issues during an OL review has been the issue regarding environmental qualification of electrical equipment. He is concerned that industry's perforr.ance to date in resolving this matter has been unsatisfactory. This is an issue that an applicant clearly should have control over. An applicant should not depend on the NRR audit of the qualifications as a substitute for the applicant's QA function.
Dr. Mattson recomended a more conserted effort on the part of the utilities to resolve this matter. He cautioned against "re-inventing the wheel" on every case. Once it is determined that an item of equipment u environmentally qualified for one plant, it is quite likely that the results may be applicable to other similar plants.
Mr. Denton discussed the accelerated review which is being performed for Palo Verde 4 & 5 in accordance with the recommendations of NUREG-0292. The review process includes dedicated reviewers and public meetings near the site area. Public meetings have also been held for the Fort St. Vrain and Duane Arnold plants. Additional public meetings for other plants are tentatively planned on a monthly basis (i.e., each month hold a public meeting for a different plant).
Mr. Denton pointed out that, with regard to Category 2, 3 and 4 items for Palo Verde 4 & 5, the applicant has indicated that it will also implement these items on Palo Verde 1, 2 & 3. He stated that the Palo Verde applicant estimates that the total cost of implerrenting applicable Category 2, 3 and 4 items on Palo V,erde 1, 2 & 3 is about $25 million for all three units and that most of this' expense is due to the requirements for industrial security, fire protection and venting cf the main steamline compartment.
Mr. Denton stated that the Commissioners set their regulations to be minimum standards which should be met. Exemptions from these regulations will be considered if the health and safety of the public is not affected.
If such exemptions are required, they should be identified early since they require Mr. Denton's approval and, possibly, Commission approval.
Mr. Denton pointed out that the Comission receives various petitions from ,
the public proposing actions for the Commission to take (either on a generic l basis or on an individual license application). Such petitions are acted on expeditiously. Any petitions filed by industry (regarding proposed Comission action or changes in regulation) would receive similar prompt attention.
In response to a question, Dr. Mattson stated that if an applicant finds that it is not getting timely attention from members of DSS, the applicant should bring the situation to his attention.
]
Harold R. Denton -5 - I 2 I979 Other matters dicsussed included:
(1) Topical Reports - Applicants should focus on any referenced topical reports in an FSAR which we have not yet approved. These topical reports will require utility attention to assure that the vendors resolve any problems with the reports in a time frame that is compatible with the schedule for completion of the FSAR review.
(2 ) Pretendering Meetings - We stated that we would be receptive to pretendering meetings with an applicant for the purpose of providing guidance in specific areas to assist in the preparation of an FSAR.
(3) Standard Format - Revision 3 to the Standard Format for Safety Analysis Reports was recently issued and should be followed for SAR's submitted after one year of the Revision 3 issuance date.
However, changes are in substance, not format, compared to Revision 2 of the Standard Format.
(4 ) Blue Book - The blue book will be made public shortly. (It is l published every other month).
l ,
'i .
W
, Emanuel Licitra, Project Manager ;
l Light Water Reactors Branch No. 3 l Division of Project Management
Enclosures:
As Stated l
l L
1
. Enclosure 1 List of Attending Utilities Decemben 13, 1973 Meeting Carolina Power and Light (Harris 1-4)
Cleveland Electric Illuminating (Perry 1 and 2) {
Duquesne Light (Beaver Valley 2) J Florida Power and Light (St. Lucie 1 and 2) i Gulf States Utilities (River Bend 1 and 2) l Illinois Power (Clinton 1 and 2) ,
Jersey Central Power and Light (Forked River)
Kansas Gas and Electric (Wolf Creek)
Niagara Mohawk Power (Nine Mile Point 2)
Northeast Nuclear Energy (Millstone 3)
Northern Indiana Public Service (Bailly)
Northern States Power (Tyrone)
Philadelphia Electric (Limerick 1 and 2)
Public Service of Indiana (Marble Hill 1 and 2)
Public Service of New Hampshire (Seabrook 1 and 2)
Rochester Gas and Electric (Sterling)
Union Electric (Callaway 1 and 2)
Virginia Electric and Power (North' Anna 3 and 4) i i
l l
' ENCLOSURE 2 AGENDA MEETING WITH POST-CP APPLICANTS DECEMBER 13, 1978 OPENING REMARKS POLICIES AND PRACTICES ON CONDUCTING OPERATING LICENSE REVIEWS
- Standard Format and Content Guide - applicability of Rev. 2 and 3.
- Category I through 4 matters - handling of.
- Proposed approach to handling Regulatory Requirements Review Committee (RRRC) matters.
1
- Use of Standard Review Plan (SRP).
- Handling of SRP deviations - implementation of Office Letter No. 9.
- Generic items - handling of by staff and participation by applicants and industry in resolving.
- Referencing of Topical Reports. i
- Handling of applicant appeals of staff positions.
SCHEDULING
- Optimum time for docketing of OL application.
- Use of NRC Case Forecast Panel in establishing construction completion dates for developing OL review schedule.
- Development and use of staff review priority list.
APPLICANT COMMENTS
~
I ENCLOSURE 3 LIST OF ATTENDEES i
NRC REPRESENTATIVES NRR H. Denton )
R. Boyd - NRR, DPM
- NRR, DSS l R. Mattson R. DeYoung - NRR, DSE l - NRR, DPM D. Ross i
- 0. Vassallo - NRR. DPM NRR, DPM E. Licitra -
- NRR, DPM H. Berkow NRR, OPM B. Kirschner -
S. Kari - PLA P. Boehnert - ACRS Staff UTILITY REPRESENTATIVES Rochester Aas & Electric Corporation John Arthur -
Rochester Gas & Electric Corporation Paul Wilkens -
E. Ashby Baum - Virginia Electric & Power Company SNUPPS (Also representing Northern States Power Co.)
E. Beckett -
N. A. Petrick - SNUPPS Bruce Beckley - Public Service of New Hampshire i D. N. Merrill - Public Service of New Hampshire Northern Indiana Public Service Comoany E. M. Shorb -
Northern Indiana Public Service Company R. J. Bohn -
Gulf States Utilities Company J. E. Booker -
Northeast Utilities. Service Company W. G. Counsil -
Northeast Utilities Service Company J. P. Cagnetta -
Jim Coughlin - Public Service of Indiana D. R. Davidson - Cleveland Electric Illuminating Company Gary Groscup - Cleveland Electric Illuminating Company J. A. DeMastry - Florida Power & Light Company. ,
C. S. Kent - Florida Power & Light Company Orin F. Pearson - Florida Power & Light Company Robert C. Hagan - Kansas cas & Electric Company
- Kansas Gas A Electric Company :
Gene P. Rathban H. D. Honan - Philadelphia Electric Company R. H. Logue - Philadelphia Electric Company P. W. Howe
- Carolina Power & Light Company Carolina Power & Light Company M. A. McDuffie -
S. F. Manno - Niagara Mohawk Company C. V. Mangan - Niagara Mohawk Company E. J. Woolever - Ouquesne Liqht Company R. E. Martin - Ouquesne Light Company Ted J. Myers - GPU Service Corporation
- GPU Service Corporation Edward Wallace A. C. Passwater - Union Electric Company D. F. Schnell - Union Electric Company l
L