ML20244D120

From kanterella
Jump to navigation Jump to search
Submits Daily Highlights.State of Nh Supreme Court Ruling Upheld Financing Package for Util.Plans Established to Initiate Hiring Addl Craft Personnel Beginning 841203
ML20244D120
Person / Time
Site: Seabrook, 05000000
Issue date: 12/06/1984
From: Nerses V
Office of Nuclear Reactor Regulation
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20235T530 List: ... further results
References
FOIA-87-51 NUDOCS 8412170388
Download: ML20244D120 (1)


Text

_ _____ - _ - _-

l c

1 l

i f4'

"~ ' ', '

MEMORANDUM FOR:

H. Denton, NPR E. G. Case, NRR j

i G. Edison, TOSB, NRR D. Eisenhut, DL F. Miraglia, DL T. Novak, DL H. Thompson, DHFS R. Vollmer, DE R. Bernero, DSI T. Speis, DST R. Snyder, TMIPO, NRR G. Holahan, ORAR

0. Crutchfield DL l

THRU:

George W. Knighton, Branch Chief Licensing Branch No. 3, DL i

FROM:

Victor Nerses, Project Manager Licensing Branch No. 3, DL

SUBJECT:

DAILY HIGHLIGHT SEABROOK STATION l

Recently, several things have taken place to allow the Seabrook Station to increase construction:

1.

The New Hampshire Supreme Court ruling uphcid approval of a $425 million financing package for Public Service of tW Hampshire.

2.

The joint owners authorized spendina on the project be increased from

$4 million/wk to $5 million/wk.

~

3.

Plans have been established to initiate hiring r. ore crafts starting Monday, December 3, 1984.

The applicant expects to have hired between 800 to 1,000 additional craft L

workers by the end of February 1985 to bring the total work force to approximately 3,800 which is about full strength for Unit 1.

Unit 2 is still mothballed.

4 l

Victor Nerses, Project Manager Licensing Branch No. 3 Division of Licensing i