ML20126C084

From kanterella
Revision as of 10:14, 12 July 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Insp Repts 50-373/92-23 & 50-374/92-23 on 921102-1204. Violations Noted.Major Areas Inspected:Licensee Response to GL 89-10, Safety-Related MOV Testing & Surveillance
ML20126C084
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 12/16/1992
From: Gainty C, Jeffrey Jacobson, Replogle G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20126C076 List:
References
50-373-92-23, 50-374-92-23, NUDOCS 9212220346
Download: ML20126C084 (17)


See also: IR 05000373/1992023

Text

_ _ . _ _ _ _ _ . . _ . . . _ . . _ .

- _ _ _ _ _ . _ . _ _ _ _ _ _ __ .-. _ _ _ _ _ _ . _ _ . _ . _ . _ _ -_ . _ _ .

.

b

!

U. S. ITUCLEAR REGULATORY COMMISSIO!! '

REGIOli III

Reports 110. 50-373/9202 3 (DRS) ; 110. 50-374/92023(DRS)

Docket 14os. 50-373; 50-374 Licenses lio. IIPF-11; ll o . ll P F - 1 8

Licensee: Commonwealth Edicon Company

Opus West III

1400 Opus Place

Downers Grove, IL 60515

Facility llame: LaSalle County lluclear Station

Units 1 and 2

Inspection At: LaSalle Site, Marreilles, Illinois

Inspection Conducte : llovember 2 Decemoer 14, 1992

'

Inspect d ~

4A /2.- ( 6 - 5 L

g

_

C. .. Waint;" Date

'

h/hb&us~

G. D. Rep o 7 le #

n- a -s u

Date

Approved Ofi~~~ / L - /6-1%

1

J. d/ [dobs a n, ChiefMh- Date

Ma cria s Processes Section

J.nnpection Summary

Inspection enI1 ducted 11ovember 2 through December 14, 1992-

(Reports 110. 50-373/92023(DRS); 110. ' 50-374 /92 02 3 (DRS) ) ..

Areas Inqpectedi Announced safety inspection of the licensee's

response to Generic Letter (GL) 89-10, " Safety-Related Motor-

7 Operated Valve (MOV) Testing and Surveillance" (2515/109).

'

Besult;ri The licensee has developed a program which is generally

-consistent with the guidance of GL 89-10. The inspection

disclosed two violations, (Paragraph 2.b.(3)):and three

i

unresolved items (Paragraphs 2.b.(3), 2.b.(4) and 2.b.(5). _

i

l

9212220346 921216 r

! 'PDR ADOCK0500g3

G ,

-. . , - - . -. - .. .- - - . - . . - _ - . . - - - - . . - - . . . .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Inspection Summary 2

The licensee demonstrated strengths in the following areas.

  • The licensee conducted testing of DC motors and proved that

the torque output of the motors was predictable below the

70% voltage rating that was recommended by the vendor.

Although the testing was conducted at significant expense,

the licensee freely shared the information with the rest of

the industry.

The licensee demonstrated weaknesses in the following areas:

Engineering did not demonstrate a thorough understanding of

the equations used to evaluate MOVs and inappropriately used

Limitorque's " stall torque" equation to evaluate MOV

capability, which resulted in a violation of NRC

requirements.

The methods used to evaluate dt.ta from design basis testing

did not ensure that MOVs could perform their safety

functions under design basis conditions. Additionally, when

instruments indicated that actual locked rotor current

values were greater than assumed, appropriate steps to

evaluate the data were not taken.

%

  • Additional steps to address negative thrust windows, as

specified in the program document and White Paper 107, were

not taken until concerns were raised by the NRC inspectors.

a Due to the lack of a procedure or adequate training for

, ~

mechanice on valve stem lubrication, the stem lubrication

was not consistently performed.

Torque switches were set in the opening direction, without

proper evaluation, at the same value as that calculated for

the closing direction. This issue had been identified

during previous NRC inspections of CECO facilities.

_ _ _ _ _ _ _ . . .

- - - - ---._--.-- - .. . - . - .- -

_ _ . . .

TABLE OF CQNTDITS

1

Page l

,

1

1. Persons Contacted.................................... 1 l

j 2. Inspection of the Program Developed in Response to  !

Generic Letter 89-10............................... 1 1

a. Supplement 3 to GL 89-10........................ 1

b. Generic Letter 89-10 Program Review............. 1

(1) Scope of the Generic Letter Program........ 2 .

(2) Design Basis Reviews....................... 2  !

'

(3) MOV Switch Settings........................ 3 i

-

(4) Design Basis Differential Pressure and

Flow Testing............................. 6  !

(5) Periodic Verification of MOV Capability.... 8

(6) MOV Tailures, Corrective Actions and

i

l

Trending................................. 9

4

(7) Schedule................................... 10

(8) Liberty Technologies 10 CFR Part 21

Review................................... 10

c. Associated Programmatic Reviews................. 10

(1) Design Control for Thermal overload __ 3

-

-

10

'

Protection...............................

,

(2) MOV Setpoint Control....................... 11 .

(3) Maintenance................................ 11 LI

-

(4) Training................................... 12  ;

(5) Operating Experience and Vendor

flotification............................. 13 -

(6) Diagnostics................................ 13

(7) Walkdown................................... 14

'

3 .- Licensee Self-Assessment............................. 14

4. Unresolved Items..................................... 14

5. Exit Meeting......................................... 14

-i

, .~ - - . . , .,,,-------..-,_,_-,---~,-,.-.~,+_-_...,---c,-...-a.-,rn,..--,.- . , , - , . . . . - . - , . ..n ,

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

T& TAILS

1. EcIsons C.ontacted

Colno_rtwgalth Edison Comrany_ICEco)

G. Diederich, Station Manager

  • #1. Adams, ENC-Regulatory Assurance
  • W. Huntington, Technical Superintendent
    1. L. Melander, LaSalle Technical Staff
  • #11. Mulderink, BWR MOV Coordinator
    1. B. Rybak, ENC-Mechanical and Structural Design

Superintendent

/J. Schmeltz, Production Superintendent ~

  1. B. Smith, MOV Coordinator
    1. R. Ungeran, MOV Program Administrator
    1. R. Williams, Regulatory Assurance, NRC Coordinator

U. S. Nuclear Regula_ tory Commlssion (NRC)

  1. D. Ilills, Senior Resident Inspector
  1. C. Phillips, Resident Inspector
  1. Denotes those attending the exit meeting on November 20,

1992.

  • Denotes those participating in the telephone exit

December 1, 1992.

2. Infipect.l_oD of the Prograp_ Developed in Response Mo Generic

Letter 89-1Q

a. Eupplement 3 to Generic Letter 89-10 _

In a letter to the NRC dated September 5, 1991, the

licensee stated that 4 MOVs within the scope of

Supplement 3 to GL 89-10 were deficient and that

moditications were planned to resolve the deficiencies.

The NRC inspectors reviewed the progress of the

modifications and found that the necessary work was

being completed on schedule.

b. Generic Letter 89-10 Proaram Review

The NRC reviewed Commonwealth Edison's commitments to

Generic Letter 89-10, submitted to the NPC by letter

dated September 28, 1990. Additional commitments

regarding the program were submitted to the NRC by

letter dated May 11, 1992. The CECO corporate level GL 89-10 program and Nuclear Operations Directive NOD-

MA.1, " Guidelines for Motor Operated Valve (MOV)

1

l

_ - - _ _ - - _ -__-__-_--- ___ ___

. _ - _ _ _ - - . _ _ . . _ _ - .

Testing, Maintenance and Evaluation," Revision 2 were

implemented at LaSalle by procedure LAP-300-31, " Motor

Operated Valve Program." The licensee had developed a

program that was generally consistent with the GL and

this is discussed in more detail below.

(1) Scope _pf the Generic Letter Procram

The inspectors reviewed system drawings for

reactor water cleanup, residual heat removal, high

pressure core spray, and low pressure core spray

as a sample check for the completeness of the

scope of the program. There were 301 MOVs

included in the program at LaSalle Station. At

the time of the inspection, the licensee was in -

the process of removing six MOVs from the program

with appropriate justification. The inspectors

determined that the scope of the licensee's

program was consistent with the guidance of GL 89-

10.

(2) Qenjan Basis Reviews

(a) Differential Pressure (do) Requirementn

The NRC inspectors reviewed design basis dp

requirements for a sample of MOVs. No

problems were noted.

(b) Reduced Voltace Capability

Some of the design basis documents

incorrectly specified the use of the diesel

generator voltage instead of the worst case _

grid voltage (as specified in the GL) as a

starting point in the calculations. However,

further investigation revealed that the

proper worst case grid voltage was actually

used in the calculations. Changes to the

design basis documents to correct the

inaccurate information may be appropriate.

During design basis testing, the actual motor

current measured, for some MOVs, exceeded the

nameplate locked rotor current and appeared

to indicate that the locked rotor current was

higher than originally assumed. However, the

licensee had not taken steps to evaluate new

information with respect to the degraded

voltage calculations. The inspectors

2

. . - -

considered the failure to evaluate pertinent

data from testing in the MOV evaluations to

be a weakness.

The program did not consider the effects of

high ambient temperatures on the performance

of MOV motors. However, Limitorque was

performing testing and analysis to address

this issue. The licensee planned to

incorporate the information from the testing

into the program when it becomes available.

The licensee conducted testing of DC motors

and demonstrated that the torque output of

the motors was predictable below the 70%

voltage rating that was recommended by the

vendor. Although the testing was conducted

at significant expense, the licensee freely

shared the information with the rest of the

industry. The licensee's efforts in the area

of DC motor testing was considered to be a

strength.

(3) MOV Switch Settinas

MOVs that appeared to be undersized using the

standard industry equation for sizing were

reevaluated using Limitorque's " stall torque"

equation to determine operability. The inspectors

considered the use of the stall torque equation,

for this applicatien, to be inappropriate.

Limitorque's intended use of the equation was to

evaluate the potential for damage to valves and/or

actuators using conservative factors that bounded

the capability of the actuator. The equation

included conservatism to account for the inertial

energy imparted to the unit when the valve disc

was mechanically stopped by slamming it into the

seat and does not represent potential MOV

capability. The licensee did not have appropriate

technical justification for deviating from the

standard industry equation. The inappropriate use

of the stall torque equation is an example of a 10

CFR 50, Appendix B, Criterion III violation (50-

373/92023-01(DRS); 50-374/920'3-01(DRS)).

On November 18, 1992, the NRC inspectors met with

representatives from the licensee's staff to

discuss the violation. At the meeting, the

licensee presented a telephone conversation record

(dated February 6, 1991) which was drafted on

Bechtel letterhead and was signed by a Bechtel

3

- _ - _ _ _ _ _ _ _ - _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ - - - _ - _ -_

~- --- --- -.- ._- - - . - - -..--- .-

l

i

I

representative and a Limitorque representative.

The record outlit.ed the factors that could be used

to determine MOV capability for " blowdown valves"

(addressed in Supplement 3 to GL 84-10) and was

presented as justification for deviating frvm the

standard industry equation for sizing. The

approach closely approximated Limitorque's stall

torque equation, but made no mention of the

application factor (normally assumed to be 9 in .

the standard sizing equation and 1.0 in the stall

torque equation). The licensee's use of an

application factor of 1.0 yielded an even less ,

conservative result than would have been obtained I

by following the guidance specified in the Dechtel  ;

document. The inspectors were concerned with the 4

- specifics of the document because they appeared to

conflict with documented guidance which-Limitorque

published in Maintenance Updates 89-1 (issued in  ;

1989) and 92-1 (issued February,-1992).

Furthermore, the Electrical Power Research

Institute's " Application Guide for Motor-Operated

Valves in Nuclear Power Plants," (dated _ March

'

1990) specifically recommended against using stall

efficiency to evaluate MOV capability.

-t

On November 19,-1992, the NRC inspectors contacted

a Limitorque representative in an attempt to

resolve-the above noted discrepancy. The

Limitorque representative informed the inspectors-

that the individual that signed the Bechtel

document was once a sales representative for ,

Limitorque but was not authorized to sign

technical concurrence documents.- Furthermore, the

information contained in the document did not  ;

represent Limitorque's technical position, nor did

it reflect Limitorque's position at the' time the  ;

document was issued. The_ representative also

indicated that he had previous discussions with

CECO on this issue and advised the utility that

Limitorque recommended against that the use of the-

stall torque' equation for determining operability..

The inspectors considered the Bechtel document to_ ,

be inappropriate' justification for the-licensee's i

position. Furthermore, the information given to

the NRC was not accurate because it was' presented

jn a manner-which implied-that it was-Limitorque's

technical position. The presentation of

inaccurate information-to.the NRC inspectors was

- considered to be-a violation of 10 CFR 50.9-(50-

373/92023-02(DRS); 50-374/92023-02(DRS)).

- t

s

'r

e w wn--,r,w *e--e, b vm.-, de- re,- -v-- ewr. .e -

.-m v,- -w ,ww.e., rm -w < wt-t-+.- se a* --=,-v E-, - e m* 9 --v y- -t

- - - . - - . - - - - - . _ - - - .. . - . - .- . - . . -

,

6

i

!

The results from the dp testing at LaSalle

appeared to indicate higher stem friction factors,  !

higher valve factors and greeter effects from load J

sensitive behavior for some MOVs than was

4

originally assumed. The licensee had compiled .!

,

test data from all six Ceco sites and estimated

that an average valve factor was between 0.4 and

0.5. It is the intent of GL 89-10 that test data

be evaluated for applicability to the overall Mov

program.  ;

The " Generic Letter 89-10 Program Document,"

(Revision 1, dated October 15, 1991) and " White

Paper 107" (Revision 0, dated January 24, 1991)

indicated that add.itional. steps would be taken to

address MOVs which had negative thrust windows

(the maximum thrust capability or structural limit

was below the minimum required thrust for

operation). However, several MOVs had negative

windows (at the end of the maintenance cycle, a

degraded condition) but additional steps to '

address the deficiencies had not:-been taken. As a

result of the concerns expressed by tho'HRC _ ,

inspectors, the licensee increased the lubrication

frequencies on the subject MOVs.- At the new

maintenance frequency the windows were no longer

negative. The. failure to-address the negative

thrust windows as specified in the above noted

documents was considered to be a weakness.

Close torque switches were set to values

I consistent with design basis thrust requirements

, for closing. Open torque switches were set to

match-the close torque. switch settings, although,

in some instances tue required opening thrust was '

much greater than the required closing thrust. 'As

such, the open torque switch setting may be

inadequate because of the potential to set the  :

switches too low.. In responne'to the NRC concern,

the licensee reviewed all the existing open torque

switch settings at LaSalle to ensure.that.

operability concerns did not exist.. This issue

was previously raised at other Ceco facilities. '

Because this inspection at LaSalle showedfthat the ,

licensce's practice had not-changed, the -

inspectors considered the failure to-previously:

evaluate this issue to be a weakness.

.

!

Upon completing its evaluation of the backlog of

MOV test data, CECO will-be expected to

, incorporate the results of the. assessment of the

test data into:its MOV. sizing and switch setting.

l

5

i

'

Mm d , - m , < , -. y . vre n-% w #w .we .-v..., r. h . .. . . , - - . , , . . . +r.. -m,-+ .- . x w r . M. ,m # w-<n. v w ,. , , , ,-m r- m

. . _ . . _ . - _._. _ _ _ . _ _ _ . _ _ _ _ _ . _ - - . _ _ _ . _ _ _ _ _

'i

+

,

r

methodology in accordance with GL 89-10 guidance. ,

For example, the thrust windows for the tested i

MOVs will need to be corrected where the thrust

requirements were found to be greater than >

predicted. For those MOVs that will not be tested -

under dynamic conditions, test results from valves

similar in type and service, must be considered in  ;

the evaluation of valve-capability.  !

The licensco stated that, in determining the-

acceptability of certain MOVs, it had relied on

the results from a study by Kalsi Engineering of

the capability of Limitorque actuators to i

withstand thrust greater than their published

ratings. The Kalsi study has been endorsed by  ;

Limitorque for thrust levels above the published- ,

ratings for its.SMB actuators for those licenscos  !

that have the report and have addressed its

caveats.. CECO however, did'not have a documented

evaluation addressing the. provisoes of the Kalsi

report. The lack of a documented evaluation of,

the provisons constitute an unresolved-item . ,

pending NRC review of the licensee's evaluation

(50-373/92023-03(DRS); 50-374/92023-03(DRS)). l

(4) Desian Basic Dif ferential Pressure and Flow - I+

Testina

Approximately 14 dp tests had boen-performed at *

the timeLof the inspection.- In general, the test

results indicate that several original assumptions

~

utilized for MOV operability evaluations wercinot i

conservative.- It is, however, recognized that  :

bounding all factors considered in the evaluation

of MOV performance may not be practicable or.

appropriate and-may lead to an unrealistic

compounding of conservatisms._ However, it is the

intent of GL 89-10 that values of individual

factors be evaluated such that when combined, they ,

provide reasonably conservative bounds on actuator

performance. Results from the testing are

summarized below.

'

(a) ' Stem friction factors varied between 0.08 and--

0.16-during design basis-testing (seven dp

tests) and-did not_ appear to1be. bounded by-

the 0.15-stem = friction factor 1that was

.

assumed for most-safety-related'MOVs'in a:

l -non-degraded condition. Furthermore, testing

L conducted at other-facilities, and at the '

'

Electrical = power Reserrch;1nstitute, i

_

indicated that same MOVs may;experier.ce' stem- -i

L 1

6

.

r

1

_

-

, , . - - - - , . . , --. - . . _ . , . - , , .- . - - . - . ~ . , _ ~, - -

. . _ . . . .- - _ -- - . --- . . ._. - - - - . ~ . _ _. . - . - . - - - - - _ -

4

friction factors significantly greater than

the 0.15 value that was originally assumed.

(b) Flex-wedge gate valve factors varied between

0.22 and 0.9 during design _ basis testing. Of

the nine valves tested, only one. valve (which

was tested at a very low dp) exhibited a

valve factor which was bounded by the 0.3

valve factor that was assumed for most gate

valves.

1

(c) Globe valves exhibited valve factors that j

varied between 0.02 and 2.08 during design I

basis testing. Of the five globe valves 1

tested, only one had a valve factor greater i

than 1.0. Since it is not theoretically

possible to have a globe valve with a valve

factor less than 1.0, the data may indicate

inaccuracles in the measurement of dp or some

other parameter. Generic difficulties in

measuring test parameters may affect the data ,

'

generated for all design basis tests.

Further investigation into this issue is

appropriate.<

(d)- The_ licensee had not accounted for-load

sensitive. behavior (rate-of-loading) in the ,

methods for setting torque switches. ,

However, load sensitive behavior was observed

during most of the design basis tests and-

varied between 2%'and 23%.

The inspectors reviewed the results and the

licensee's evaluation of the 14 design basis tests '

that had been completed at LaSalle.1 LTS-600-26 -r

requires that the acceptance criteria for-

differential pressure _ tests be satisfied before-

tested MOVs-are returned to service. The

acceptance criteriaoof LTS-600-26 evaluate the

capability of the tested.MOV to provide the

required thrust extrapolated to design-basis -

conditions for both opening and closing the; valve.

The inspectors identified several weaknesses in

the acceptance criteria. Specifically, the

acceptance criteria did not include consideration _7

of diagnostic equipment inaccuracy'orl torque-

switch repeatability-in: evaluating the capabil-ity

- of-the MOV-(for example, motor actuator

capability). .The~ acceptance. criteria-also did not  ;

consider torque requirements: or load sensitive  :

behavior to ensure motor autuator capability under '

'

degraded voltage conditions. Finally, the ,

7

. - - . .~ :.- = . - . - - - . . - - . . _ , - . - . -

, . - - . - - - ,2. ~ ,- . : - - ,.

acceptance criteria did not justify the omission

of extrapolation of the opening thrust requirement

from test conditions to design-basis conditions

(an example was the acceptance criteria evaluation

for 2WR040). The inspectors did not identify any

operability concerns for the tested MOVs resulting

from these specific weaknesses in the acceptance

criteria at this time. The licensee was currently

in the process of revising its acceptance criteria

in response to a violation of 10 CFR 50 Appendix B

Criterion V identified at Dresden. This is an

area that will be reviewed during the part 2

inspections.

LaSalle had performed some testing at less than -

80% of the design basis differential pressure for

the MOV, which does yield valuable information.

However, the inspectors found that LTS-600-26 did

not require the evaluation of test data if the

test was conducted at less than 80% of full dp.

The inspectors reminded the licensee that testing

MOVs at less than 80% of their design basis

differential pressure can indicate MOV operability

problems. For example, the test may reveal that

little margin exists between MOV capability and

thrust requirements at the test pressure such that

the operability of the MOV under design basis

conditions is questionable. The results of tests

at less than 80% of design basis differential

pressure can also be important in supporting the

basjs for any planned grouping of MOVs in

demonstrating their design basis capability. As

with any data that may reveal problems with _

cafety-related equipment, the licensee is required _

to assess the applicability of the test data and

to determine whether any operability concerns

exist based on that data. The licensee agreed

'

that such an evaluation should be conducted and

stated that the results of testo conducted below

80% of design basis differential pressure would be

evaluated before returning the MOV to service.

This is considered an unresolved item pending

review of the licensee's acceptance criteria for

tests that are performed at less than 80% of full

dp (50-373/92023-04(DRS); 50-374/92023-04(DRS)).

(5) Eeriodic_ Verification of MOV Cayability-

The licensee's plan for ensuring that adequate MOV

switch settings were established and maintained

throughout the life of the plant included static

diagnostic testing of MOVs of valves classified as

8

_____ .____ _ _ _ _ _ _ _

- _ - . . __ _ _ _ _ _ _

priority 1 on an interval that will be determined

once the initial stages of the GL 89-10 program

are completed. The period recommended by GL 89-10

was every third refueling outage. The inspectors

informed the licensee that static testing was not

currently a technically justified method of

periodic verification because of uncertainties in

the relative performance of MOVs under static and

design basis conditions. For valves classified as

priority 2, NOD-MA.1 specified that periodic

testing would not be required provided preventive

maintenance was performed. This is inconsistent

with the GL and the licensee's commitment, which

indicated plans to meet the intent of the GL.

This is an unresolved item pending review of the

licensee's justification for not periodically

testing priority 2 valves (50-373/92023-05(DRS);

50-374/92023-05(DRS)).

(6) ROV Failures, Corrective /Letions and Trellcling

The inspectors reviewed licensee actions for a

number of LER's, deviation reports, and other MOV

failures. In the cases reviewed, the root cause

determination and corrective actions were complete

and well documented. There were no specific

failures that appeared to indicate any program

weaknesses.

The trending program was recently improved to

include a number of parameters, including thrust

at torque switch trip, maximum thrust, and other

parameters that should become useful as more data

is collected. The trending for indication of when _

a refurbishment would be required was based mostly

on the results of grease inspections and no

periodic refurbishments were planned. This could

limit the effectiveness of the station personnel

to detect degradation prior to failure. Some

forms of wear may not be detectable until the

actuators are virtually inoperable. In such a

case, periodic visual inspections may provide a

measure of added assurance. A recent example

where a problem could have been identified prior

to failure by a periodic inspection was 1WR180

where the staking of the stem nut apparently

caused a crack in the drive sleeve and resulted in

failure of the valve to cycle.

9

. .

_.

(7) Schedule

The licensee committed to implementation of all GL 89-10 actions by tho end of the fifth refueling

outages, beginning with the 1991 outages. The

schedule was beyond the time frame recommended by

the GL and there were no plans to dynamically test

MOVs where at least 80% of design basis-dp and

flow could not be achieved. This position and the

implementation schedule for GL 89-10 will be

reviewed by NRR to determine acceptability. The

inspectors did note, however, that LaSalle had

developed an aggressive, but reasonable schedule

to dynamically test those valves considered

practicable to test by the end of the third -

refueling outage, which is more consistent with

the GL schedule than the corporate position.

(8) Liberty Technolonies 10 CFR Part 21 Review

During a meeting with the NRC staff in April 1992,

CECO committed to evaluate the data from tests of

motor-operated valves (MOVs) performed at its

facilities in response to GL 89-10.. In accordance

with 10 CFR Part 21, Liberty Technologies notified

the NRC staff and nuclear power plant licensees in

October 1992 of a generic.jssue regarding the .

accuracy of its VOTES diagnostic equipment used.in

measuring the thrust delivered by motor actuators

in opening and closing their valves. At the time

of the inspection at LaSalle, CECO had completed a

preliminary evaluation of the MOV test data

including an initial effort at addressing the

effect of the increased inaccuracy of the VOTES _ _

-

equipment. -In-an internal memorandum on October-

29, 1992, CECO stated that its consideration of

the increased inaccuracy of the~ VOTES cquipment

would be completed _within.six months of receipt

and validation of new VOTES software, expected in

December 1992.

c. Associated Proctammatic Reviews

The NRC inspectors reviewed other licensee programs

associated with MOVs. 1

(1) Desian Control for-Thermal Overload' Protection

.The NRC inspectors reviewed the licensee's methods

fornthe design control.of. thermal overloads. The

licensee's methods appeared to be acceptable.

10

i

- . . . . . . . . ,

- _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ _ . _ _ . _ _ _.

(2) MOV Setpoint Control

The NRC inspectors reviewed licensee documents and

discussed MOV setpoint control with personnel.

The licensee's MOV setpoint control program for

torque switches was based on thrust windows for

those valves that had been diagnostically tested.

For those valves that had not been diagnostically

tested, the torque switch setpoints were set

according to original manufacturer

recommendationu. The control of switch settings

appeared to be acceptable.

(3) dalatenanca

The licensee's nominal preventive maintenance (PM) -

frequency was 36 months, which exceeded the

manufacturer's (Limitorque) recommended frequency

for stem lubrication of 18 months. The exact

effects of the extended maintenance frequency are

not known, however, some additional degradation

and increased stem factors would be expected. The

licensee planned to perform some static as-found

diagnostic testing to justify their position and

had completed a few tests. Such justification

would be better supported by as-found design basis

testing since static diagnostic testing may not be

as valuable due to uncertainties in the

relationship between the performance of MOVs under

static and design basis conditions.

The NRC inspectors were concerned that data from

some as-found testing may not adequately reflect

the worst caso degradation that could be ~

experienced by MOVs in the plant. The inspectors

witnessed one as-found test on a reactor core

isolation cooling valve, which was located in the

drywell. Although the stem was last lubricated

approximately 18 months prior to the test, the

lubrication on the stem appeared to be in a

'

pristine condition, possibly due to the atmosphere

in the drywell. Data from this particular test

may not yield useful information related to the

effects of degraded stem lubrication on MOV

performance. Performing as-found testing on MOVs

known to be in the most degraded conditions,

possibly based on direct inspections, would

strengthen the program.

The lubrication of the valve stems was considered

to be a weakness. There was no formal procedure

to specify the details for lubrication of the

~

11

l

l

valve stem, which is a significant task in that

the friction at the stem to stem nut interface has

a direct effect on thrust output of the actuator.

In addition, training for the mechanics was

inconsistent in this area and resulted in

inconsistent results in the past. For examplo,

some mechanics would clean and lubricate only the

exposed portion of the stem and would not cycle

the valve. If the valve happened to be in the

open position at the time, the stem threads could

receive little maintenance. The 2.WR029 valve,

which was last lubricated in February 1992, had

caked-on lubricant on the valve stem, indicating

incomplete cleaning at the last lubrication.

Although there were no specific concerns with the

operability of 2WR029 due to the actual location -

of the cated-on lubricant, this was an example of

where procedures or additional training would

ensure consistency. Since the valves are already

lubricated on a 36 month frequency instead of the

recommended frequency of 18 months, the importance

of complete lubrication should be reinforced.

The NRC inspectors reviewed the licencoe's

position in the area of valve stem packing

adjustments. The practice was to perform a motor

current signature test after packing adjustments.

However, changes in power requirements associated

with packing loading may not be accurately

reflected in ac motor current analysis due to the

changing power factor. Large changes in thrust

requirements due to packing adjustments may result

in only small changes in motor current. The

licensee committed to evaluate data from testing ~

efforts and provide the status of the post

maintenance testing program for MOVs to the NRC at

the end of 1992.

(4) Tritining

The inspectors reviewed the training provided to

personnel performing work associated with the

implementation of the LaSalle MOV program. The

MOV training program at LaSalle was considered

acceptable. However, training for contractors

performing lubrication and refurbishment was

limited to what was covered by the procedures, and

in the case of stem lubrication as discussed

above, could be strengthened.

12

___ - __ _ _

.-__- __-- _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _

(5) pneirat_jagJ;perience and Vendor l{ptif 3 cation

The NRC inspectors found some weaknesses in the

area of processing and control of vendor

information from various sources. The licensee

had taken steps to ensure that certain

information, such as Part 21 information and NRC

Information Notices, was properly screened,

evaluated and maintained by appropriate

organizations and that appropriate actions were

planned. However, in the case of Limitorque

maintenance and technical updates, no formal

review that would ensure proper tracking and

screening, especially for possible procedure or

training updates was established.

The " stall efficiency" was used to evaluate MOV

capability (as part cf the stall thrust equation).

The NRC inspectors were especially concerned about

the use of the stall efficiency because at least

three industry documents (Limitorque Maintenance

Updates 89-1 and 92-1, and the Electrical Power

Research Institute's " Application Guida for Motor-

Operated Valves in Nuclear Power Plants," dated

March 1990) specifically recommended against using

stall efficiency to evaluate MOV capability. The

NRC inspectors assessed the licensee's program for

reviewing information from vendors and found that

all three documents had been reviewed by

appropriate members of the licensee's staff.

Deviations from vendor recommendations are

expected to be evaluated for technical

justification.

The LaSalle program for the processing and control

of operating experience and vendor notifications

was found to be in need of improvement, especially

for thorough review and use of Limitorque

maintenance and technical updates.

(6) Diagnostics

The licensee uses the Valve Operational Test

Equipment System (VOTES) to test MOVs under both

static and dynamic conditions. However, testing

plans did not always include the use of the VOTES

torque cartridge (VTC) to allow the measurement of

spring pack displacement. Deceuse of this, stem

friction factors may not be quantifiable at

different points of interest, such as flow cut-

off. The expanded use of the VTC would strengthen

the program.

13

- -_ -_ _ _ - - _ _ _ _ _ _ -___ _ _ - __ _ - _ -- _ _ -

.

(7) WAD:doWD

The inspectors performed a general inspection of

the plant as well as a detailed inspection of

several MOVs. In general, housekeeping appeared

to be satisfactory in most areas. The valve stems

that were accessible were well lubricated and most

valves appeared to be in good condition. However,

valve 2E51-F022 had the motor located at tne

bottom of the actuator, which may increase the

potential for damage due to grease leaking into

the motor. Additionally, grease (oil) was

observed Icaking past one of the housing gaskets.

3. LitoDsee fielf Assessment _

The licensee had performed self-assessments of the MOV

program au compared to the commitments of the CECO Response

to Generic Letter 89-10, dated Septencer 28, 1990, and to

the GL in general. In addition, the station had prepared an

action plan to addrece certain aspects of the MOV program.

Most of the items in the action plan were either completed

or were scheduled for January 1993. In general, the

licenseo showed a good effort in this area.

'

4. Unremo3 _eJLItems

Unresolved items are matters about which more information is

required in order to ascertain whether they are acceptable

items, items of noncompliance, or deviations. Unresolved

items disclosed during this inspection are discussed in

paragraphs 2.b.(3), 2.b.(4), and 2.b.(5) of this report.

5. Egjt Meetinus _

The inspectors met with licensee representatives (denoted in

Paragraph 1) at the conclusion of the inspection on

November 20, 1992. Supplementhl exits were held by

telephone conference on December 1 and 14, 1992. The

inspectors summarized the purpose and scope of the

inspection and the findings. The inspectors informed the

licensee of the two violations and two unresolved items

identified during this inspection. The inspectors also

discursed the likely informational content of the inspection

report with regard to documents or processes reviewed by the

inspectors during the inspection.

14

__ __- ___-_-_-- - _-__ _ -____- _ _-__ _ __- - - -- __ _