Clarifies License Amend Request Re Conformance of Administrative Controls Section 6 to Guidance of STS
ML20137T193
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 04/10/1997
From: Sorensen J
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20137T196 List:
References
NUDOCS 9704160018
Download: ML20137T193 (2)


Text

.

Northern states Power Company 1717 Wakonade Dr. E.

Welch, MN 55089 Telephone 612-388-1121 1

April 10,1997 i 10 CFR Pad 50

, Section 50.90 U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Supplement 2 to License Amendment Request Dated December 14,1995 Conformance of Administrative Controls Section 6 to the Guidance of Standard Technical Specifications l

l This letter is submitted to further clarify the subject license amendment request l based on discussions with the NRC staff. Specific Technical Specification page  ;

changes are presented in Attachments 1 and 2 to this letter. Attachment 1 contains Technical Specification pages TS.6.0-3 from the previous supplement, dated November 25,1996, and page TS.6.0-5 from Exhibit C of the subject License Amendment Request marked up to implement the modifications proposed by this supplement. Attachment 2 contains Technical Specification pages revised to their final form to reflect the changes proposed by both supplements. Specific changes to the Technical Specifications Chapter 6 proposed by this supplement are discussed below.

l Proposed page TS.6.0-3: overtime controls.  !

An additional paragraph from the Prairie Island current Technical Specifications is included in the requirements for limiting the working hours of the plant staff. This additional paragraph specifies the controls on deviations from the procedural guidelines.

I 150 97o426oote 97o42o /

PDR P

ADOCK 05000282 I4 @

PDR .;

I!$.!lfb!lIl}fI,I}fl,l}lEll

. USNRC 4/10/97 Pag 3 2 of 2 Also, two minor typographical errors on this page as previously submitted have been corrected.

Proposed page TS.6.0-5: incorporation of NUREG-0737.

In conformance with the guidance of NUREG-1431, the requirements for emergency operating procedures includes the base document NUREG-0737.

A revised Safety Evaluation, Significant Hazards Determination and Environmental Assessment have not been submitted with the changes proposed by this letter since these evaluations, as originally presented in the December 14,1995 submittal, continue to bound the proposed license amendment as modified by this supplement.

All recently issued License Amendments which would impact the subject License Amendment Request and its supplements were addressed in the November 25, 1996 supplement.

If you have any questions related to this information in support of the subject license amendment request, please contact myself or Dale Vincent at 612-388-6758.

Joel P. Sorensen Plant Manager, Prairie Island Nuclear Generating Plant Attachment 1: Marked Up Technical Specification Pages from Supplement dated November 25,1996, Attachment 2 and License Amendment Request Dated December 14,1994, Exhibit C Attachment 2: Revised Technical Specification Pages c: Regional Administrator-lil, NRC NRR Project Manager, NRC Senior Resident inspector, NRC State of Minnesota Attn: Kris Sanda J E Silberg