MONTHYEARIR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 2024-09-09
[Table view] Category:Startup Test Report
[Table view] |
Text
William T. O'Connor, Jr.
Vice President, Nuclear Generation Fermni 2 6400 North Dixie NepTort, Michigan 48166 Nlewy.,
Tel: 734-586-5201 Fax: 734-5864172 DTE Energy-7 NRC 05-0017 March 9, 2005 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Fermi 2 Cycle 11 Startup Report In accordance with Technical Requirements Manual Section 5.2.1, Detroit Edison is submitting the enclosed Fermi 2 Cycle 11 Startup Report.
The Technical Requirements Manual states that a summary report of plant startup and power escalation testing shall be submitted "following installation of fuel that has a different design." Fermi 2 loaded 192 GE14 fuel assemblies manufactured by Global Nuclear Fuel-Americas during the Tenth Refueling Outage.
The startup report addresses applicable tests identified in Section 14.1.4.8 of the Updated Final Safety Analysis Report and includes a description of the measured values of the operating conditions or characteristics obtained during the test program and a comparison of these values with design predictions and specifications.
Should you have any questions or require additional information, please contact Mr.
Paul R. Kiel, Principal Engineer, at (734) 586-1455.
Sincerely, Enclosure cc: E. R. Duncan N. K. Ray NRC Resident Office Regional Administrator, Region III (9,t
Enclosure to NRC-05-0017 March 9, 2005 Page 1 Summary This startup report is being submitted pursuant to Fermi 2 Technical Requirements Manual Section 5.2.1, which requires a report to be submitted whenever Fermi 2 installs a fuel of a different design or has been manufactured by a different fuel supplier. Cycle 11, which is currently in progress, is operating with 192 GE14 fuel assemblies manufactured by Global Nuclear Fuel-Americas. This is the same manufacturer of the GE 1I fuel that constitutes the remainder of the fuel in the core.
Although Global Nuclear Fuel-Americas considers GE14 to be an evolutionary fuel design, Fermi 2 is documenting the testing for the first reload of GE14 fuel assemblies. Only applicable tests from Chapter 14 of the Updated Final Safety Analysis Report are described herein. Fermi 2 completed the startup testing for Cycle 11 based on performance of Procedure 57.000.15, "Recirculation System Performance Data Collection and Speed Limiter Setpoint Determination," on December 18, 2004.
Fuel Loading The purpose of this test is to load fuel safely and efficiently to the full core size. The partially loaded core must be subcritical by at least 0.38 percent Ak/k with the analytically determined strongest rod fully withdrawn.
The beginning of cycle shutdown margin calculated by the Fermi 2 fuel vendor was reported at 1.17 percent Ak/k. Core shuffle was conducted in accordance with approved instructions. Equipment required to be operable to ensure that shutdown margin is maintained was verified by various performances of Procedure 24.000.03, "Mode 5 Shiftly, Daily, and Weekly Surveillances," before and during core alterations. Procedure 24.000.03 was last completed on November 20, 2004. Post core alteration core verification was completed on November 25, 2004 in accordance with Procedure 82.000.04, "Refueling and Post Core Alteration Verification." All fuel bundles were verified to be in their proper locations and properly oriented in the control cells.
Full Core Shutdown Margin The purpose of this test is to demonstrate that the reactor is subcritical throughout the first fuel cycle with any single control rod fully withdrawn.
This test is performed in the fully loaded core in the Xenon-free condition. The shutdown margin is measured by withdrawing the control rods until criticality is reached. If criticality is not reached with in-sequence control rods in the
Enclosure to NRC-05-0017 March 9, 2005 Page 2 configuration corresponding to the required shutdown margin reactivity, the shutdown margin is satisfied. Additional in-sequence control rods are then withdrawn until the reactor is critical. The difference between the measured Ktff and the calculated Kff for the in-sequence critical will be applied to the calculated shutdown margin to obtain the true shutdown margin. Technical Specification 3.1.1 requires that shutdown margin of the fully loaded core with the analytically determined strongest rod withdrawn must be at least 0.38 percent Ak/k plus an additional margin for exposure. Criticality should occur within 1.0 percent Ak/k of the predicted critical.
The shutdown margin measured on December 1, 2004 in accordance with Procedure 54.000.01, "Shutdown Margin Check," was 0.9521 percent. This was above the minimum required shutdown margin of 0.38 percent.
Control Rod Drive System The purposes of the Control Rod Drive (CRD) system test are to demonstrate that the CRD system operates properly over the full range of primary coolant temperatures and pressures from ambient to operating, and to determine the initial operating characteristics of the entire CRD system. These tests would not be affected by the addition of GE14 fuel.
Core Performance The core performance evaluation is employed to determine the principal thermal and hydraulic parameters associated with core behavior. The test evaluated core thermal power, core flow rate, and the core performance parameters of maximum linear heat generation rate (MLHGR), minimum critical power ratio (MCPR), and maximum average planar linear heat generation rate (MAPLHGR). The MLHGR during steady-state conditions shall not exceed the allowable heat flux as specified in the core operating limits report (COLR). The steady-state MCPR shall be maintained greater than, or equal to, the value specified in the COLR. The MAPLHGR shall not exceed the limits given in the COLR. Steady-state reactor power shall be limited to full rated maximum values on or below the design flow control line. Core flow will not exceed its rated value.
During power ascension after the Tenth Refueling Outage, core parameters were monitored frequently using the 3D Monicore system. Core performance was documented in Procedure 54.000.07, "Core Performance Parameter Check," and Procedure 24.000.02, "Shiftly, Daily, and Weekly Required Surveillances," on December 3, 2004. Offline comparisons of 3D Monicore output and Panacea output indicate the core is behaving as expected.