MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23122A2332023-06-26026 June 2023 Issuance of Amendment No. 223 Regarding Revision of Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23158A1332023-06-0808 June 2023 Notice of Enforcement Discretion (NOED) for Fermi Power Plant, Unit Two (EPID L-2023-LLD-0000) Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/ Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink ML23130A1032023-05-17017 May 2023 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 ML23114A1172023-05-0101 May 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23115A4152023-04-25025 April 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Fermi Power Plant, Unit 2 ML23124A2032023-04-10010 April 2023 DTE Electric Company Submittal of Fermi 3 Periodic Reports ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22325A2992023-02-24024 February 2023 Audit Plan in Support of Review of License Amendment Request to Revise Technical Specification Surveillance Requirements Relating to Emergency Diesel Generator Voltage and Frequency ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML23200A2162023-01-20020 January 2023 Outline Submittal Letter 2024-02-05
[Table view] Category:Startup Test Report
[Table view] |
Text
William T. O'Connor, Jr.
Vice President, Nuclear Generation Fermni 2 6400 North Dixie NepTort, Michigan 48166 Nlewy.,
Tel: 734-586-5201 Fax: 734-5864172 DTE Energy-7 NRC 05-0017 March 9, 2005 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Fermi 2 Cycle 11 Startup Report In accordance with Technical Requirements Manual Section 5.2.1, Detroit Edison is submitting the enclosed Fermi 2 Cycle 11 Startup Report.
The Technical Requirements Manual states that a summary report of plant startup and power escalation testing shall be submitted "following installation of fuel that has a different design." Fermi 2 loaded 192 GE14 fuel assemblies manufactured by Global Nuclear Fuel-Americas during the Tenth Refueling Outage.
The startup report addresses applicable tests identified in Section 14.1.4.8 of the Updated Final Safety Analysis Report and includes a description of the measured values of the operating conditions or characteristics obtained during the test program and a comparison of these values with design predictions and specifications.
Should you have any questions or require additional information, please contact Mr.
Paul R. Kiel, Principal Engineer, at (734) 586-1455.
Sincerely, Enclosure cc: E. R. Duncan N. K. Ray NRC Resident Office Regional Administrator, Region III (9,t
Enclosure to NRC-05-0017 March 9, 2005 Page 1 Summary This startup report is being submitted pursuant to Fermi 2 Technical Requirements Manual Section 5.2.1, which requires a report to be submitted whenever Fermi 2 installs a fuel of a different design or has been manufactured by a different fuel supplier. Cycle 11, which is currently in progress, is operating with 192 GE14 fuel assemblies manufactured by Global Nuclear Fuel-Americas. This is the same manufacturer of the GE 1I fuel that constitutes the remainder of the fuel in the core.
Although Global Nuclear Fuel-Americas considers GE14 to be an evolutionary fuel design, Fermi 2 is documenting the testing for the first reload of GE14 fuel assemblies. Only applicable tests from Chapter 14 of the Updated Final Safety Analysis Report are described herein. Fermi 2 completed the startup testing for Cycle 11 based on performance of Procedure 57.000.15, "Recirculation System Performance Data Collection and Speed Limiter Setpoint Determination," on December 18, 2004.
Fuel Loading The purpose of this test is to load fuel safely and efficiently to the full core size. The partially loaded core must be subcritical by at least 0.38 percent Ak/k with the analytically determined strongest rod fully withdrawn.
The beginning of cycle shutdown margin calculated by the Fermi 2 fuel vendor was reported at 1.17 percent Ak/k. Core shuffle was conducted in accordance with approved instructions. Equipment required to be operable to ensure that shutdown margin is maintained was verified by various performances of Procedure 24.000.03, "Mode 5 Shiftly, Daily, and Weekly Surveillances," before and during core alterations. Procedure 24.000.03 was last completed on November 20, 2004. Post core alteration core verification was completed on November 25, 2004 in accordance with Procedure 82.000.04, "Refueling and Post Core Alteration Verification." All fuel bundles were verified to be in their proper locations and properly oriented in the control cells.
Full Core Shutdown Margin The purpose of this test is to demonstrate that the reactor is subcritical throughout the first fuel cycle with any single control rod fully withdrawn.
This test is performed in the fully loaded core in the Xenon-free condition. The shutdown margin is measured by withdrawing the control rods until criticality is reached. If criticality is not reached with in-sequence control rods in the
Enclosure to NRC-05-0017 March 9, 2005 Page 2 configuration corresponding to the required shutdown margin reactivity, the shutdown margin is satisfied. Additional in-sequence control rods are then withdrawn until the reactor is critical. The difference between the measured Ktff and the calculated Kff for the in-sequence critical will be applied to the calculated shutdown margin to obtain the true shutdown margin. Technical Specification 3.1.1 requires that shutdown margin of the fully loaded core with the analytically determined strongest rod withdrawn must be at least 0.38 percent Ak/k plus an additional margin for exposure. Criticality should occur within 1.0 percent Ak/k of the predicted critical.
The shutdown margin measured on December 1, 2004 in accordance with Procedure 54.000.01, "Shutdown Margin Check," was 0.9521 percent. This was above the minimum required shutdown margin of 0.38 percent.
Control Rod Drive System The purposes of the Control Rod Drive (CRD) system test are to demonstrate that the CRD system operates properly over the full range of primary coolant temperatures and pressures from ambient to operating, and to determine the initial operating characteristics of the entire CRD system. These tests would not be affected by the addition of GE14 fuel.
Core Performance The core performance evaluation is employed to determine the principal thermal and hydraulic parameters associated with core behavior. The test evaluated core thermal power, core flow rate, and the core performance parameters of maximum linear heat generation rate (MLHGR), minimum critical power ratio (MCPR), and maximum average planar linear heat generation rate (MAPLHGR). The MLHGR during steady-state conditions shall not exceed the allowable heat flux as specified in the core operating limits report (COLR). The steady-state MCPR shall be maintained greater than, or equal to, the value specified in the COLR. The MAPLHGR shall not exceed the limits given in the COLR. Steady-state reactor power shall be limited to full rated maximum values on or below the design flow control line. Core flow will not exceed its rated value.
During power ascension after the Tenth Refueling Outage, core parameters were monitored frequently using the 3D Monicore system. Core performance was documented in Procedure 54.000.07, "Core Performance Parameter Check," and Procedure 24.000.02, "Shiftly, Daily, and Weekly Required Surveillances," on December 3, 2004. Offline comparisons of 3D Monicore output and Panacea output indicate the core is behaving as expected.