|
---|
Category:Meeting Summary
MONTHYEARML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24257A0582024-09-26026 September 2024 Summary of August 1, 2024, Hybrid Public Meeting on the Potential Palisades Nuclear Plant Restart ML24212A0592024-08-0606 August 2024 May 15, 2024, Summary of Meeting with Holtec Decommissioning International,Llc Regarding LAR to Approve Biasi Critical Heat Flux Correlation for Use with Main Steam Line Break Analysis to Support Potential Reauthorization of Power Operation ML24166A2912024-06-25025 June 2024 April 29, 2024, Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a Quality Assurance Program Manual to Support Potential Reauthorization of Power Operations at Palisades Nuclear Plant ML24141A0632024-05-23023 May 2024 Summary of April 17, 2024, Hybrid Public Outreach Meeting ML24089A2472024-04-0808 April 2024 March 18, 2024, Summary of Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Proposed Emergency Plan for Resumption of Power Operations at the Palisades Nuclear Plant ML24051A0942024-02-27027 February 2024 Summary of February 6, 2024, Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Technical Specifications Administrative Controls and Quality Assurance Program ML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21012A0382021-01-14014 January 2021 December 8, 2020, Summary of Public Teleconference with Entergy Nuclear Operations Inc. Regarding Pre-submittal of a License Transfer Application to Holtec International for Palisades Nuclear Plant ML20309A2372020-11-0606 November 2020 Summary of Public Teleconference with Entergy Nuclear Operations, Inc. to Discuss Future Request for One-Time Exemption from Certain Requirements of 10 CFR 50, Appendix E, Section Iv.F. at Palisades Nuclear Plant (EPID L-2020-LRM-0091 ML20304A1442020-11-0202 November 2020 Summary of September 21, 2020, Public Teleconference with Entergy Nuclear Operations Inc. Regarding a Proposed Alternative for Repair of Reactor Vessel Head Penetrations for Palisades Nuclear Plant ML20280A6952020-10-13013 October 2020 Letter - Palisades Nuclear Plant- Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant EPID L-2020-LRO-0051 ML20280A6962020-10-13013 October 2020 20200912 NRC Mid Outage Q and a for Phone Call for Palisades 1R27 (Revised) ML20280A6972020-10-13013 October 2020 20200910 NRC Mid Outage Q and a for Phone Call for Palisades 1R27-Entergy Responses ML20231A2202020-08-17017 August 2020 Summary of Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML19296D0632019-11-0101 November 2019 August 2019 Palisades NEIMA 108 Public Meeting Summary ML19136A2552019-05-16016 May 2019 Summary of the Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML18351A2382018-12-18018 December 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant ML18340A0072018-12-0606 December 2018 Summary of Call with Entergy Nuclear Operations, Inc. - Verbal Authorization of Request for Alternative for the Repair of Reactor Vessel Closure Head Penetrations ML18268A2802018-09-26026 September 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18008A2302018-01-10010 January 2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant ML17335A0262017-12-0505 December 2017 Summary of November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Confomances ML17338B0502017-12-0505 December 2017 Summary of November 28, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding a Potential Request Associated with an Alternative to the Reexamination Frequency for a Relevant Condition ML17227A2742017-08-14014 August 2017 Summary of the July 26, 2017, Public Meeting Regarding Palisades Nuclear Plant ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17164A3112017-06-27027 June 2017 Summary of 06/12/2017, Pre-Submittal Meeting with Entergy Nuclear Operations, Inc. to Discuss Palisades Nuclear Plant Post Shutdown Emergency Plan and Administrative Technical Specification License Amendment Request ML17160A1812017-06-14014 June 2017 Summary of Conference Call with Palisades Nuclear Plant Regarding the Spring 2017 Steam Generator Inspections ML17080A1492017-03-23023 March 2017 Summary of March 20, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Cyber Security Plan Implementation Schedule ML16344A0862016-12-20020 December 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding National Fire Protection Association Standard 805 ML16277A6772016-10-11011 October 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Proposed Closure Plant for Generic Safety Issue 191, Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance ML16182A5142016-06-30030 June 2016 Summary of the June 23, 2016, Public Meeting Regarding Palisades Nuclear Plant ML16127A1722016-05-0505 May 2016 6/23/16 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Palisades Nuclear Plant Performance for the 2015 Calendar Year ML16035A4252016-03-0101 March 2016 Summary of January 25, 2016, Pre-Application Teleconference Meeting with Entergy Nuclear Operations to Discuss a Forthcoming License Amendment Request Regarding Steam Generator Cold Leg Alternate Repair Criteria at Palisades Nuclear Plant ( ML15294A2972015-10-27027 October 2015 Steam Generator Tube Inspection Discussion During Palisades 2015 (RF24) Outage (Preliminary Information) ML15294A2922015-10-27027 October 2015 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2015 Steam Generator Inspections ML15272A0652015-09-30030 September 2015 Summary of Telephone Conference on September 28, 2015, Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15261A0392015-09-21021 September 2015 September 17, 2015, Summary of Telephone Conference Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15119A0442015-05-0606 May 2015 Summary of April 14, 2015, Meeting with Entergy Nuclear Operations, Inc. on Plans for Volumetric Examinations of Primary Coolant System Alloy 600 Welds ML15118A0352015-04-27027 April 2015 Meeting Summary with Public to Discuss the 2014 Annual Assessment Results for Palisades Nuclear Plant 2024-09-26
[Table view] |
Text
September 29, 2005 LICENSEE: Nuclear Management Company, LLC FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF MEETING HELD ON SEPTEMBER 2, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF AND NUCLEAR MANAGEMENT COMPANY, LLC (NMC) REPRESENTATIVES TO DISCUSS THE RESULTS OF THE PALISADES NUCLEAR PLANT (PNP) AGING MANAGEMENT PROGRAM (AMP) AND AGING MANAGEMENT REVIEW (AMR) AUDITS On September 2, 2005, the NRC staff met with members of the NMC, LLC (the applicant) in a public meeting to discuss the results of the Palisades Nuclear Plant (PNP) Aging Management Program (AMP) and Aging Management Review (AMR) audits. The application was submitted by letter dated March 22, 2005. The list of attendees is provided in Enclosure 1.
The License Renewal and Environmental Impacts Program, Section B project team conducted a public exit meeting in South Haven, Michigan, to discuss the results of its audit of the PNP license renewal application (LRA). The team audited approximately 83 percent of the AMP and 99 percent of the AMR contained in the PNP LRA. Approximately, 20 members of the public attended the meeting. The public participants raised numerous concerns outside the scope of the audit activities, including (1) spent nuclear fuel dry cask storage, (2) site emergency planning, (3) economic damage, and (4) the potential consequences due to a terrorist attack.
The staff responded to numerous questions and directed the public to other sources of information located on the NRCs Web site. However, many of the issues raised are the subject of proposed contentions contained in a request by intervenors for a hearing on the PNP LRA which are currently under review by the Atomic Safety and Licensing Board Panel (ASLBP). Therefore; the staff was limited in its response and only addressed the LRA process for public participation and other areas outside the scope of the intervenors petition when responding to questions from the public.
/RA/
Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-255
Enclosure:
As stated cc w/encl: See next page
September 29, 2005 LICENSEE: Nuclear Management Company, LLC FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF MEETING HELD ON SEPTEMBER 2, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF AND NUCLEAR MANAGEMENT COMPANY, LLC (NMC) REPRESENTATIVES TO DISCUSS THE RESULTS OF THE PALISADES NUCLEAR PLANT (PNP) AGING MANAGEMENT PROGRAM (AMP) AND AGING MANAGEMENT REVIEW (AMR) AUDITS On September 2, 2005, the NRC staff met with members of the NMC, LLC (the applicant) in a public meeting to discuss the results of the Palisades Nuclear Plant (PNP) Aging Management Program (AMP) and Aging Management Review (AMR) audits. The application was submitted by letter dated March 22, 2005. The list of attendees is provided in Enclosure 1.
The License Renewal and Environmental Impacts Program, Section B project team conducted a public exit meeting in South Haven, Michigan, to discuss the results of its audit of the PNP license renewal application (LRA). The team audited approximately 83 percent of the AMP and 99 percent of the AMR contained in the PNP LRA. Approximately, 20 members of the public attended the meeting. The public participants raised numerous concerns outside the scope of the audit activities, including (1) spent nuclear fuel dry cask storage, (2) site emergency planning, (3) economic damage, and (4) the potential consequences due to a terrorist attack.
The staff responded to numerous questions and directed the public to other sources of information located on the NRCs Web site. However, many of the issues raised are the subject of proposed contentions contained in a request by intervenors for a hearing on the PNP LRA which are currently under review by the Atomic Safety and Licensing Board Panel (ASLBP). Therefore; the staff was limited in its response and only addressed the LRA process for public participation and other areas outside the scope of the intervenors petition when responding to questions from the public.
/RA/
Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-255
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS accession no.: ML052730440 DOCUMENT NAME:E:\Filenet\ML052730440.wpd OFFICE: PM:RLEP LA:RLEP SC:RLEP NAME: MMorgan MJenkins SLee (KWeaver for)
DATE: 09/29/05 09/29/05 09/29/05 OFFICIAL RECORD COPY
Palisades Nuclear Plant cc:
Robert A. Fenech, Senior Vice President Michigan Department of Attorney General Nuclear, Fossil, and Hydro Operations Special Litigation Division Consumers Energy Company 525 West Ottawa St.
1945 Parnall Rd. Sixth Floor, G. Mennen Williams Building Jackson, MI 49201 Lansing, MI 48913 Arunas T. Udrys, Esquire Manager, Regulatory Affairs Consumers Energy Company Nuclear Management Company, LLC 1 Energy Plaza 27780 Blue Star Memorial Highway Jackson, MI 49201 Covert, MI 49043 Regional Administrator, Region III Director of Nuclear Assets U.S. Nuclear Regulatory Commission Consumers Energy Company 801 Warrenville Road Palisades Nuclear Plant Lisle, IL 60532-4351 27780 Blue Star Memorial Highway Covert, MI 49043 Supervisor Covert Township John Paul Cowan P.O. Box 35 Executive Vice President & Chief Nuclear Covert, MI 49043 Officer Nuclear Management Company, LLC Office of the Governor 700 First Street P.O. Box 30013 Hudson, WI 54016 Lansing, MI 48909 Jonathan Rogoff, Esquire U.S. Nuclear Regulatory Commission Vice President, Counsel & Secretary Resident Inspectors Office Nuclear Management Company, LLC Palisades Plant 700 First Street 27782 Blue Star Memorial Highway Hudson, WI 54016 Covert, MI 49043 Douglas E. Cooper Michigan Department of Environmental Senior Vice President - Group Operations Quality Palisades Nuclear Plant Waste and Hazardous Materials Division Nuclear Management Company, LLC Hazardous Waste and Radiological 27780 Blue Star Memorial Highway Protection Section Covert, MI 49043 Nuclear Facilities Unit Constitution Hall, Lower-Level North Paul A. Harden 525 West Allegan Street Site Vice President P.O. Box 30241 Palisades Nuclear Plant Lansing, MI 48909-7741 Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043
Palisades Nuclear Plant cc:
Robert A. Vincent Licensing Lead - License Renewal Project Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Darrel G. Turner License Renewal Project Manager Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Mr. Douglas F. Johnson Director, Plant Life Cycle Issues Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Secretary Federal Energy Regulatory Commission 888 First Street, NE, Room 1A Washington, DC 20426 Chairperson Michigan Public Service Commission PO Box 30221 Lansing, MI 48909-7721
DISTRIBUTION: Summary of public meeting held on 9/2/05 between NRC and NMC, Dated: September 29, 2005 ADAMS Accession No.: ML052730440 HARD COPY RLEP RF M. Morgan (PM)
E-MAIL:
RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li K. Winsberg (RidsOgcMailCenter)
R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff
P. Lougheed, RIII J. Ellegood, RIII M. Garza, RIII A. Stone, RIII M. Padovan L. Raghavan T. Mensah OPA
MEETING ATTENDANCE LIST SEPTEMBER 2, 2005 Names Affiliations Kurt Cozens U.S. Nuclear Regulatory Commission (NRC)
Michael Morgan NRC Jacob Zimmerman NRC Darrel Turner Nuclear Management Company, LLC (NMC)
Robert Vincent NMC Mark Savage NMC Dan Lemon NMC Miles Railey NMC Bill Bryant NMC John Kneeland NMC Larry Seamans NMC Mark Cimock NMC Douglas Johnson NMC Sara Seamans NMC Steve Wawro Consumers Energy Kathryn Barnes Public Corinne Cory Public Jim Roberts Public Chuck Jordan Public Gary Karch Public Beth Anderson Public Kenneth Richards Public LeRoy Wolins Public Sebastian Piccioca Public Jean McFadden Public Enclosure