ML13295A218

From kanterella
Revision as of 10:58, 5 December 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Summary of Public Meeting with Beaver Valley,
ML13295A218
Person / Time
Site: Beaver Valley
Issue date: 10/22/2013
From: Hunegs G
NRC/RGN-I/DRP/PB6
To:
HUNEGS, GORDON
References
Download: ML13295A218 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 Renaissance Boulevard, Suite 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 October 22, 2013 MEETING

SUMMARY

LICENSEE: FirstEnergy Nuclear Operating Company (FENOC)

FACILITY: Beaver Valley Power Station Davis-Besse Nuclear Power Station Perry Nuclear Power Plant

SUBJECT:

FENOC Public Meeting Summary On September 24, from 8:30 a.m. to 11:30 a.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public meeting at the Embassy Suites - Pittsburgh Airport in Coraopolis, PA.

The public was invited to observe the meeting that discussed FENOC fleet-wide performance with FENOC management. After the business portion of the meeting, the public had an opportunity to discuss FENOCs performance and the role of the NRC in ensuring safe operation at Beaver Valley, Davis-Besse and Perry Nuclear Power Plants.

The meeting notice was issued on September 9, 2013, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13252A171. ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The meeting began with brief introductions then FENOC management discussed fleet-wide and individual plant performance for 2013. FENOC management also discussed their fleet-wide approach to sustaining performance improvements as well as improving site performance at the Beaver Valley, Davis-Besse and Perry Nuclear Power Plants. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and FENOC representatives.

The meeting provided a forum to discuss common performance themes at the FENOC plants with the NRC. The meeting concluded with a discussion of plans to continue these meetings involving the NRC regions and program offices and all plants in the FENOC fleet on an annual basis.

/RA/

______________________

Gordon K. Hunegs, Chief Reactor Projects Branch 6 Division of Reactor Projects

Enclosure:

FENOC Slides, ML13294A597

ML13295A218 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME BBickett/ BB GHunegs/ GKH DATE 10/22/13 10/22/13