Inspection/Activity Plan, 09/01/2008 - 12/31/2009, Report 22
ML082461022
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/02/2008
From:
Division Reactor Projects II
To:
Shared Package
ML082461019 List:
References
Download: ML082461022 (2)


Text

Page 1 of 2 Turkey Point 09/02/2008 17:37:30 Inspection / Activity Plan Report 22 09/01/2008 - 12/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB1-CDBI - COMPONENT DESIGN BASIS INSPECTION 8 3, 4 IP 7111121 Component Design Bases Inspection 09/08/2008 09/12/2008 Baseline Inspections 3, 4 IP 7111121 Component Design Bases Inspection 09/22/2008 09/26/2008 Baseline Inspections 3, 4 IP 7111121 Component Design Bases Inspection 10/06/2008 10/10/2008 Baseline Inspections OL EXAM - INITIAL EXAM PREP 3 3 V23299 TURKEY POINT/FEBRUARY 2009 EXAM AT POWER FACILITIES 02/02/2009 02/06/2009 Not Applicable PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 3, 4 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 02/16/2009 02/20/2009 Baseline Inspections 3, 4 IP 7111401 Exercise Evaluation 02/16/2009 02/20/2009 EP Baseline Inspection 3, 4 IP 7111404 Emergency Action Level and Emergency Plan Changes 02/16/2009 02/20/2009 EP Baseline Inspection 3, 4 IP 71151-EP01 Drill/Exercise Performance 02/16/2009 02/20/2009 Baseline Inspections 3, 4 IP 71151-EP02 ERO Drill Participation 02/16/2009 02/20/2009 Baseline Inspections 3, 4 IP 71151-EP03 Alert & Notification System 02/16/2009 02/20/2009 Baseline Inspections OL EXAM - INITIAL EXAM 3 3 V23299 TURKEY POINT/FEBRUARY 2009 EXAM AT POWER FACILITIES 02/23/2009 03/06/2009 Not Applicable EB3ISI - UNIT 3 INSERVICE INSPECTION 1 3 IP 7111108P Inservice Inspection Activities - PWR 03/09/2009 03/13/2009 Baseline Inspections OL EXAM - INITIAL EXAM PREP 3 3 V23313 TURKEY POINT/AUGUST 2009 EXAM AT POWER FACILITIES 07/27/2009 07/31/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 1 3 3 V23313 TURKEY POINT/AUGUST 2009 EXAM AT POWER FACILITIES 08/17/2009 08/21/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 2 3 3 V23313 TURKEY POINT/AUGUST 2009 EXAM AT POWER FACILITIES 08/31/2009 09/04/2009 Not Applicable OL EXAM - INITIAL EXAM - WEEK 3 3 3 V23313 TURKEY POINT/AUGUST 2009 EXAM AT POWER FACILITIES 09/14/2009 09/18/2009 Not Applicable PSB1-RP - RP OCCUPATIONAL PREINSPECTION VISIT 1 3, 4 IP 7112101 Access Control to Radiologically Significant Areas 09/21/2009 09/25/2009 Baseline Inspections PSB1-RP - RP OCCUPATIONAL INSPECTION WK1 (OUTAGE) 2 3, 4 IP 7112101 Access Control to Radiologically Significant Areas 10/26/2009 10/30/2009 Baseline Inspections 3, 4 IP 7112102 ALARA Planning and Controls 10/26/2009 10/30/2009 Baseline Inspections 3, 4 IP 7112202 Radioactive Material Processing and Transportation 10/26/2009 10/30/2009 Baseline Inspections 3, 4 IP 71151-OR01 Occupational Exposure Control Effectiveness 10/26/2009 10/30/2009 Baseline Inspections 3, 4 IP 71151-PR01 RETS/ODCM Radiological Effluent 10/26/2009 10/30/2009 Baseline Inspections EB3ISI - UNIT 4 INSERVICE INSPECTION 1 4 IP 7111108P Inservice Inspection Activities - PWR 11/02/2009 11/06/2009 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Turkey Point 09/02/2008 17:37:30 Inspection / Activity Plan Report 22 09/01/2008 - 12/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP OCCUPATIONAL INSPECTION WK2 (OUTAGE) 2 3, 4 IP 7112101 Access Control to Radiologically Significant Areas 11/16/2009 11/20/2009 Baseline Inspections 3, 4 IP 7112102 ALARA Planning and Controls 11/16/2009 11/20/2009 Baseline Inspections 3, 4 IP 7112202 Radioactive Material Processing and Transportation 11/16/2009 11/20/2009 Baseline Inspections INSP - MODIFICATIONS/50.59 INSPECTION 4 3, 4 IP 7111117 Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 11/30/2009 12/04/2009 Baseline Inspections 3, 4 IP 7111117 Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 12/07/2009 12/11/2009 Baseline Inspections This report does not include INPO and OUTAGE activities.