|
---|
Category:Letter
MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a IR 05000528/20243012024-06-17017 June 2024 NRC Examination Report 05000528/2024301; 05000529/2024301; 05000530/2024301 ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 2024-09-27
[Table view] Category:License-Operator
MONTHYEARML24253A1932024-05-21021 May 2024 PV-2024-04 Exam Security Agreement (Final) ML24170B0072024-05-0909 May 2024 11-PV-2024-04 Public Forms ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23151A6492023-05-11011 May 2023 11-PV-2023-05 Public Forms ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML22196A3782022-07-15015 July 2022 Notification of NRC Initial Operator Licensing Examination 05000528/2023301; 05000529/2023301; 05000530/2023301 ML22143A9892022-05-19019 May 2022 PV-2022-05-Post Exam Comments ML22178A1772022-04-12012 April 2022 PV-2022-05-Public Forms ML23193A8502022-04-12012 April 2022 PV-2022-05-Form 2.3-1 Examination Outline Quality Checklist ML22070A1382022-03-10010 March 2022 Response to Regulatory Issue Summary (RIS) 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21160A0832021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 IR 05000528/20213012021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 ML21147A5442021-05-0606 May 2021 04 Post Examination Analysis ML21147A5452021-05-0606 May 2021 04 Public Forms ML21106A3042021-04-16016 April 2021 Response to Regulatory Issue Summary (RIS) 2021-01, Preparation and Scheduling of Operator Licensing Examinations ML21106A2842021-04-14014 April 2021 Generic Fundamentals Examination Results March 2021 ML21020A0962020-12-10010 December 2020 11 Final Outlines ML21020A0932020-12-10010 December 2020 11 Draft Written Examination Comments ML21020A0982020-12-10010 December 2020 2020-11 Draft Operating Test Comments ML21020A0922020-12-10010 December 2020 11 Draft Outlines ML21020A0902020-12-10010 December 2020 11 Draft Operating Test ML21020A1032020-12-10010 December 2020 11 Post Examination Analysis ML21020A0952020-12-10010 December 2020 11 Final Operating Test ML21020A0942020-12-10010 December 2020 11 Draft Written Examination ML21020A0912020-12-10010 December 2020 11 Draft Outline Comments ML21020A1042020-12-10010 December 2020 11 Public Forms ML21020A0972020-12-10010 December 2020 11 Final Written Examination ML20325A3682020-11-20020 November 2020 NRC Initial Operator Licensing Examination Approval 05000528/2020301; 05000529/2020301; 05000530/2020301 ML20199M3832020-07-17017 July 2020 Response to Regulatory Issue Summary (RIS) 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20003E2762019-10-11011 October 2019 PV-2019-10 Post Exam Comments and Analysis ML19273C8072019-09-30030 September 2019 NRC Initial Operator Licensing Exam Approval Letter 05000528/529/530/2019301 ML19135A3352019-05-15015 May 2019 Response to Regulatory Issue Summary (RIS) 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML20042C1192019-03-12012 March 2019 PV-2019-10 Public Forms ML19045A3732019-02-12012 February 2019 March 2019 GFE Cover Letter Riv ML19011A3712019-01-10010 January 2019 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2019 ML18284A4942018-09-25025 September 2018 NRC Retake Initial Operator Licensing Examination Approval 05000528/2018302, 05000529/2018302 and 05000530/2018302 ML18184A3552018-06-29029 June 2018 Response to Regulatory Issue Summary (RIS) 2018-02, Preparation and Scheduling of Operator Licensing Examinations - Update ML18122A3722018-05-0101 May 2018 Response to Regulatory Issue Summary (RIS) 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18086B0842018-02-16016 February 2018 Facility Cover Letter - Riv - March 2018 - GFE ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17124A2082017-05-0404 May 2017 Response to Regulatory Issue Summary (RIS) 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17013A5482017-01-13013 January 2017 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2017 ML16321A4652016-11-0303 November 2016 Palo VERDE-2016-10 Final Operating Test ML16321A4692016-11-0303 November 2016 2016-10-DRAFT Outline Comments Rev 2 with PVNGS Response ML16321A4722016-11-0303 November 2016 10 Draft Written Exam Pedigree ML16321A4632016-11-0303 November 2016 Palo VERDE-2016-10 Final Written Exam ML16321A4682016-11-0303 November 2016 2016-10 Draft Outlines 2024-05-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24253A1932024-05-21021 May 2024 PV-2024-04 Exam Security Agreement (Final) ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24170B0072024-05-0909 May 2024 11-PV-2024-04 Public Forms ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23151A6492023-05-11011 May 2023 11-PV-2023-05 Public Forms ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML22196A3782022-07-15015 July 2022 Notification of NRC Initial Operator Licensing Examination 05000528/2023301; 05000529/2023301; 05000530/2023301 ML22143A9892022-05-19019 May 2022 PV-2022-05-Post Exam Comments ML22178A1772022-04-12012 April 2022 PV-2022-05-Public Forms ML23193A8502022-04-12012 April 2022 PV-2022-05-Form 2.3-1 Examination Outline Quality Checklist ML22070A1382022-03-10010 March 2022 Response to Regulatory Issue Summary (RIS) 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20213012021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 ML21160A0832021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 ML21147A5452021-05-0606 May 2021 04 Public Forms ML21147A5442021-05-0606 May 2021 04 Post Examination Analysis ML21106A3042021-04-16016 April 2021 Response to Regulatory Issue Summary (RIS) 2021-01, Preparation and Scheduling of Operator Licensing Examinations ML21020A0962020-12-10010 December 2020 11 Final Outlines ML21020A0982020-12-10010 December 2020 2020-11 Draft Operating Test Comments ML21020A1032020-12-10010 December 2020 11 Post Examination Analysis ML21020A0972020-12-10010 December 2020 11 Final Written Examination ML21020A0952020-12-10010 December 2020 11 Final Operating Test ML21020A0942020-12-10010 December 2020 11 Draft Written Examination ML21020A0932020-12-10010 December 2020 11 Draft Written Examination Comments ML21020A0912020-12-10010 December 2020 11 Draft Outline Comments ML21020A0922020-12-10010 December 2020 11 Draft Outlines ML21020A0902020-12-10010 December 2020 11 Draft Operating Test ML21020A1042020-12-10010 December 2020 11 Public Forms ML20325A3682020-11-20020 November 2020 NRC Initial Operator Licensing Examination Approval 05000528/2020301; 05000529/2020301; 05000530/2020301 ML20199M3832020-07-17017 July 2020 Response to Regulatory Issue Summary (RIS) 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20003E2762019-10-11011 October 2019 PV-2019-10 Post Exam Comments and Analysis ML19273C8072019-09-30030 September 2019 NRC Initial Operator Licensing Exam Approval Letter 05000528/529/530/2019301 ML19135A3352019-05-15015 May 2019 Response to Regulatory Issue Summary (RIS) 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML20042C1192019-03-12012 March 2019 PV-2019-10 Public Forms ML18284A4942018-09-25025 September 2018 NRC Retake Initial Operator Licensing Examination Approval 05000528/2018302, 05000529/2018302 and 05000530/2018302 ML18184A3552018-06-29029 June 2018 Response to Regulatory Issue Summary (RIS) 2018-02, Preparation and Scheduling of Operator Licensing Examinations - Update ML18122A3722018-05-0101 May 2018 Response to Regulatory Issue Summary (RIS) 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17124A2082017-05-0404 May 2017 Response to Regulatory Issue Summary (RIS) 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML16321A4682016-11-0303 November 2016 2016-10 Draft Outlines ML16321A4652016-11-0303 November 2016 Palo VERDE-2016-10 Final Operating Test ML16321A4632016-11-0303 November 2016 Palo VERDE-2016-10 Final Written Exam ML16340B6372016-11-0303 November 2016 Palo VERDE-2016-10 Public Forms ML16321A4662016-11-0303 November 2016 Palo VERDE-2016-10 Post-Exam Comments ML16321A4692016-11-0303 November 2016 2016-10-DRAFT Outline Comments Rev 2 with PVNGS Response ML16321A4882016-11-0303 November 2016 Palo VERDE-2016-10 Final Outlines ML16321A4832016-11-0303 November 2016 Palo VERDE-2016-10 Draft Operating Test ML16321A4722016-11-0303 November 2016 10 Draft Written Exam Pedigree ML16321A4792016-11-0303 November 2016 2016-10 Draft Written Exam Comments 2024-05-09
[Table view] |
Text
PVNGS 2008 License Examination Post-examination Assessment Written Examination Question Assessment 50% or more of the candidates answered these questions incorrectly.
Question # Success Rate Description SRO Q-5 33% Question asked which at EOP should be entered for the given conditions. Answer key and worksheet listed A (Reactor Trip) as the correct answer, after review it has been determined that B (LOAF) should be the correct answer.
Modified the question, worksheet and answer key to reflect this change.
This change has been submitted in the Post Exam submittal.
SRO Q-7 44% Question asked for 2 preferred methods of contamination control during a SGTR/LOOP event. All candidates who missed the question chose distracter B which included increasing the cooldown rate to 100 degrees per hour. The SGTR procedure limits the CD rate to 30 degrees during a LOOP due to ensure asymmetric cooldown.
The question is valid as written.
SRO Q-13 44% Question asked what signal would stop the SG overfill event and which EOP should be entered.
All picked correct signal MSIS but some chose Reactor Trip vs. Excessive Steam Demand. The excessive cooldown required ESD to be entered.
The question is valid as written.
SRO Q-21 33% Question asked Operability status of ECCS (HPSI pumps) with the A DG OOS and a subsequent loss of the B HPSI pump room essential cooler.
The correct answer on the worksheets and answer key was both HPSI pumps Inoperable. All those who missed chose distracter C which stated that A HPSI was operable if the PBA-S03 was powered by offsite power, this can be considered correct since TS allows a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> period before A HPSI must be declared Inoperable. A & C are both considered correct answers.
This change has been submitted in the Post Exam submittal.
1
PVNGS 2008 License Examination Post-examination Assessment RO Q-34 32% Question asked for the response of the Reactor Drain Tank as saturation conditions are reached in the Pressurizer when forming a bubble. The correct answer was smaller pressure increases accompanied by larger level increases, most examinees picked distracter D greater pressure increase accompanied by smaller level increases.
In review the question should have been worded more clearly.
The question is valid as written.
All examination questions missed by any candidate have been reviewed and there are no other issues identified with any other questions.
Written Exam Results SROs SRO RO Combined Reactor Operators Sensitive Kharrl 76 90 86 Sensitive Information Huck 86 Information Smith 80 95 91 Gallegos 85 Martinez 92 93 92 Schingeck 91 Piepiora 76 85 82 Bury 83 Clark 84 93 90 Trejo 97 Liston 76 86 83 Ploegman 90 Whitson 84 90 88 Hopkins 94 Schank 72 93 87 Rosenbaum 86 Fouse 72 89 84 Ratliff 86 Kura 98 2