ML16321A465

From kanterella
Jump to navigation Jump to search
Palo VERDE-2016-10 Final Operating Test
ML16321A465
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 11/03/2016
From: Vincent Gaddy
Operations Branch IV
To:
Arizona Public Service Co
GADDY V
References
Download: ML16321A465 (274)


Text

Administrative Topics Outline Facility: PVNGS Date of Examination: 10/28/16 Examination Level RO Operating Test Number: 2016 NRC Administrative Topic Type Code* Describe Activity to be Performed (see Note)

JPM: Determine actual Pressurizer levels in MODE 5 and determine if reference leg backfills are required.

Conduct of Operations D, R K/A: 2.1.25 Ability to interpret reference materials, such as (A1) graphs, curves, tables, etc.

IR: 3.9 / 4.2 JPM: Determine the minimum required flash protection boundaries and EPE to rack out a breaker.

Conduct of Operations K/A: 2.1.26 Knowledge of industrial safety procedures (such M, R (A2) as rotating equipment, electrical, high temperature, high pressure, caustic, chlorine, oxygen, and hydrogen).

IR: 3.4 / 3.6 JPM: Determine if acceptance criteria is met for PPS instrumentation channel checks.

Equipment Control N, R (A3) K/A: 2.2.12 Knowledge of surveillance procedures.

IR: 3.7 / 4.1 JPM: Determine the valves which should be used for a clearance which will result in the lowest dose to the workers.

Radiation Control M, R K/A: 2.3.14 Knowledge of radiation or contamination hazards (A4) that may arise during normal, abnormal, or emergency conditions or activities.

IR: 3.4 / 3.8 Emergency Plan NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes) (1)

(N)ew or (M)odified from bank ( 1) (3)

(P)revious 2 exams ( 1; randomly selected) (0)

PVNGS 2016 NRC RO Admin JPM Outline ES-301-1 Rev 1

Administrative Topics Outline Task Summary A1 The applicant is provided with indicated Pressurizer level from three level instruments as well as current RCS temperature and pressure. The applicant will compare the data to graphs with a variety of data lines which they will use to interpolate the actual Pressurizer level per 40OP-9ZZ01, Cold Shutdown to Hot Standby Mode 5 to Mode 3. The applicant will then compare the three values to determine if reference leg backfills are required. This is a bank JPM.

A2 The applicant will use 01DP-0IS13, Palo Verde Electrical Safe Work Practices, to evaluate a series of matrices listing a variety of electrical evolutions and voltage ranges and their corresponding safety requirements. This is a modified JPM. The bank version of this JPM uses a 4.16kV breaker and this JPM was changed to a 480V breaker. Both the flash protection boundary and the minimum required EPE are different from the original JPM.

A3 The applicant is provided a list of indicated values for PPS related parameters which they will use to determine the maximum deviations between any two channels, and determine if the deviations are within the listed acceptance values per 40ST-9ZZM1, Operations Mode 1 Surveillances. This is a new JPM.

A4 The applicant is provided a drawing with sets of valves (both upstream and downstream) which could be used to isolate a valve that has a point source hot spot. The applicant will utilize the curie-meter rem rule and point source equations to determine total expected dose for each possible isolation and select the isolation resulting in the lowest dose. This is a modified bank JPM. JPM was modified by changing the distances of the potential isolations from the valve to be isolated resulting in a different answer than the original JPM.

PVNGS 2016 NRC RO Admin JPM Outline ES-301-1 Rev 1

Administrative Topics Outline Facility: PVNGS Date of Examination: 10/28/16 Examination Level SRO Operating Test Number: 2016 NRC Administrative Topic Type Code* Describe Activity to be Performed (see Note)

JPM: Determine the active/inactive status of 3 licensed operators.

Conduct of Operations N, R (A5) K/A: 2.1.1 Knowledge of conduct of operations requirements.

IR: 3.8 / 4.2 JPM: Determine the minimum required flash protection boundaries and EPE to rack out a breaker.

Conduct of Operations K/A: 2.1.26 Knowledge of industrial safety procedures (such M, R as rotating equipment, electrical, high temperature, high (A6) pressure, caustic, chlorine, oxygen, and hydrogen).

IR: 3.4 / 3.6 JPM: Determine LCOs entered and exited given a timeline of events.

Equipment Control D, R K/A: 2.2.40 Ability to apply Technical Specifications for a (A7) system IR: 3.4 / 4.7 JPM: Determine the maximum dose a pregnant AO may receive for the duration of pregnancy and any reporting requirements.

Radiation Control N, R K/A: 2.3.4 Knowledge of radiation exposure limits under (A8) normal or emergency conditions.

IR: 3.2 / 3.7 JPM: Determine EAL classification and fill out NAN Emergency Message Form.

Emergency Plan D, R K/A: 2.4.41 Knowledge of the emergency action level (A9) thresholds and classifications.

IR: 2.9 / 4.6 PVNGS 2016 NRC SRO Admin JPM Outline ES-301-1 Rev 2

Administrative Topics Outline Task Summary NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes) (2)

(N)ew or (M)odified from bank ( 1) (3)

(P)revious 2 exams ( 1; randomly selected) (0)

A5 The applicant is provided a list of all watches stood by three licensed operators during the previous quarter. The applicant must compare the watches stood by each individual to the requirements in 40DP-9OP02, Conduct of Shift Operations, and determine whether or not each of their licenses are active for the current quarter. This is a new JPM.

A6 The applicant will use 01DP-0IS13, Palo Verde Electrical Safe Work Practices, to evaluate a series of matrices listing a variety of electrical evolutions and voltage ranges and their corresponding safety requirements. This is a modified JPM. The bank version of this JPM uses a 4.16kV breaker and this JPM was changed to a 480V breaker. Both the flash protection boundary and the minimum required EPE are different from the original JPM.

A7 The applicant is provided a timeline of events during which various related pieces of plant equipment are declared inoperable and restored to operable status. The applicant must determine which LCO conditions are entered and exited, and at what times those conditions are entered or exited, based on the provided timeline. This is a bank JPM.

A8 The applicant is provided with a timeline of events and dose history for a pregnant AO. The applicant must determine the remaining allowable dose for the AO and reporting requirements resulting from the listed conditions per 75DP-9RP01, Radiation Exposure and Access Control.

This is a new JPM.

A9 The applicant is provided with plant conditions which require an EAL classification to be declared. They will utilize all associated E-Plan procedures to determine the correct EAL.

They will have 15 minutes to make the official declaration. When the event has been declared, they will fill out the NAN Emergency Message Form for the post-declaration notifications. They will have 13 minutes to complete the EP-0541 form (to allow time for the notifications to be made within the 15 minutes window). This is a time-critical, bank JPM.

PVNGS 2016 NRC SRO Admin JPM Outline ES-301-1 Rev 2

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 JPM INFORMATION 1270010401 - Operate the plant during a plant heatup from cold shutdown to hot TASK:

standby Calculated actual pressurizer levels for RCN-LI-103 (25.8-27.8%), RCA-LI-110X (30.3-32.3%), and RCB-LI-100Y (32.0-34.0%), and determined that filling TASK STANDARD:

instrument reference legs IS required due to greater than 3% deviation between RCN-LI-103 and RCB-LI-110Y.

K/A: G 2.1.25 RATING: RO: 3.9 SRO: 4.2 10CFR55: 45.12 POSITION(S): RO/SRO VALIDATION TIME: 15 minutes

REFERENCES:

40OP-9ZZ23, Outage GOP LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 7/8/2016 VALIDATED BY: Joseph Stevens DATE: 7/8/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A1 Rev 1

1. PROCEDURES/MATERIALS:

40OP-9ZZ23, Outage GOP:

o Appendix A, Pressurizer Indicated vs Actual Level for RCA-LI-110X and RCB-LI-110Y o Appendix B, Pressurizer Indicated vs Actual Level for RCN-LI-103 o Appendix W, Forming a Steam Bubble in Pressurizer, steps W.9.8 and W.9.9 This JPM was written using Revision 72 of 40OP-9ZZ23. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

The plant is in MODE 5, in the process of drawing a steam bubble in the pressurizer per 40OP-9ZZ23, Outage GOP.

Pressurizer pressure is 50 psia Pressurizer temperature is 200°F RCN-LI-103 indicates 26%

RCA-LI-110X indicates 40%

RCB-LI-110Y indicates 43%

INITIATING CUE:

The CRS directs you to determine ACTUAL pressurizer level for RCN-LI-103, RCA-LI-110X, and RCB-LI-110Y, and determine whether or not filling reference legs to Pressurizer level instrumentation will be required, per 40OP-9ZZ23, Outage GOP, Appendix W, Forming a Steam Bubble in Pressurizer, steps W.9.8 and W.9.9.

Document answers on the provided answer sheet.

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 JPM START TIME:

Step: 1

  • Check RCA-LI-110X actual level indicates within 3% of each other using ANY of Proc Step: W.9.8 the following:

Appendix A - Pressurizer Indicated vs Acutal Level For RCA-LI-110X and RCB-LI-110Y Appendix B - Pressurizer Indicated vs Acutal Level For RCN-LI-103 Standard: Determined RCA-LI-110X actual level to be 31.3% (acceptable range is 30.3% to 32.3%)

Answer explanation:

RCA-LI-110X:

y = y0 + (y1 - y0)((x-x0)/(x1-x0))

y = 30% + (34% - 30%)((200°F - 70°F)/(467°F - 70°F))

y = 31.3%

Comments (required for UNSAT):

SAT UNSAT Step: 3

  • Check RCB-LI-110Y actual level indicates within 3% of each other using ANY of Proc Step: W.9.8 the following:

Appendix A - Pressurizer Indicated vs Acutal Level For RCA-LI-110X and RCB-LI-110Y Appendix B - Pressurizer Indicated vs Acutal Level For RCN-LI-103 Standard: Determined RCB-LI-110Y to be 33.0% (acceptable range is 32.0% to 34.0%)

Answer explanation:

RCB-LI-110Y:

y = y0 + (y1 - y0)((x-x0)/(x1-x0))

y = 31.5% + (36% - 31.5%)((200°F - 70°F)/(467°F - 70°F))

y = 33.0%

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 JPM Step: 3

  • Check RCN-LI-103 actual level indicates within 3% of each other using ANY of Proc Step: W.9.8 the following:

Appendix A - Pressurizer Indicated vs Acutal Level For RCA-LI-110X and RCB-LI-110Y Appendix B - Pressurizer Indicated vs Acutal Level For RCN-LI-103 Standard: Determined actual level for RCN-LI-103 to be 26.8% (acceptable range is 25.8 to 27.8%)

Answer explanation:

RCN-LI-103:

y = y0 + (y1 - y0)((x-x0)/(x1-x0))

y = 26% + (28% - 26%)((200°F - 60°F)/(401°F - 60°F) y = 26.8%

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 Step: 4

  • IF ANY of the following Pressurizer level instruments deviated greater than 3%

Proc Step: W.9.9 between each other:

RCA-LI-110X RCB-LI-110Y RCN-LI-103 THEN direct I&C to fill reference legs to Pressurizer level instrumentation.

Standard: Determined the maximum deviation to be greater than 3% and that filling reference legs IS required.

Answer explanation:

RCN-LI-103 highest acceptable answer is 27.8% and lowest acceptable answer from RCB=LI-110Y is 32.0%.

32.0% - 27.8% = 4.2%, which is greater than 3%, therefore filling reference legs IS required.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 00 6/22/05 6 Initial issue 01 12/5/08 3, 6 Updated to Rev 37 of 40OP-9ZZ01, revised evaluator cues and initiating cue, updated JPM to current format template.

02 11/21/13 3, 6 Updated to Rev 43 of 40OP-9ZZ01, updated JPM to current template.

03 5/26/15 6 Revised JPM to include answer explanations, updated to current template, shortened to only require calculating each actual level one time instead of twice per instrument.

04 7/8/16 3 40OP-9ZZ01 was cancelled, changed JPM to match steps in 40OP-9ZZ23.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A1 Rev 1 EXAMINEE INITIAL CONDITIONS:

The plant is in MODE 5, in the process of drawing a steam bubble in the pressurizer per 40OP-9ZZ23, Outage GOP.

Pressurizer pressure is 50 psia Pressurizer temperature is 200°F RCN-LI-103 indicates 26%

RCA-LI-110X indicates 40%

RCB-LI-110Y indicates 43%

INITIATING CUE:

The CRS directs you to determine ACTUAL pressurizer level for RCN-LI-103, RCA-LI-110X, and RCB-LI-110Y, and determine whether or not filling reference legs to Pressurizer level instrumentation will be required, per 40OP-9ZZ23, Outage GOP, Appendix W, Forming a Steam Bubble in Pressurizer, steps W.9.8 and W.9.9.

Document answers on the provided answer sheet.

Answers:

RCN-LI-103 actual level: _________________

RCA-LI-110X actual level: ________________

RCB-LI-110Y actual level: ________________

Instrument reference leg filling IS / IS NOT required. (circle one)

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 JPM INFORMATION TASK: 1290520004 - Rack in/rack out a 480 volt load center breaker Determined the minimum required Flash Protection Boundary is 10 feet and the TASK STANDARD: minimum required PPE/EPE: hearing protection, arc face shield with balaclava, RF gloves, FR shirt, FR pants, and FR coveralls.

K/A: G 2.1.26 RATING: RO: 3.4 SRO: 3.6 10CFR55: 45.12 POSITION(S): AO/RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/19/16 VALIDATED BY: Joseph Stevens DATE: 7/5/16 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 PROCEDURES/MATERIALS:

01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices o Section 4.10, PPE and EPE o Section 4.11, Barrier, Guards, and Posting Practices o Appendix A, Safe Working Distances o Appendix B, PPE/EPE Matrix 40OP-9PG01, 480V Class 1E Switchgear o Appendix B, Breaker Racking Instructions, Section B.1, Racking Out Breakers This JPM was written using Revision 12 of 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices and Revision 22 of 40OP-9PG01, 480V Class 1E Switchgear.

This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

The unit is hanging a clearance on the A Charging Pump, CHA-P01.

You have been directed to rack out the breaker for the A Charging Pump, PGA-L31C4, per 40OP-9PG01, 480V Class 1E Switchgear, Appendix B - Breaker Racking Instructions.

INITIATING CUE:

Identify the required Flash Protection Boundary and the MINIMUM Personal Protective Equipment / Electrical Protection Equipment (in addition to the PPE always required inside the unit) for this evolution per 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices.

Document your answers in the space provided below.

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 JPM START TIME:

JPM Step: 1

  • Determine the minimum Flash Protection Boundary per Appendix A.

Proc Step: N/A Standard: Determined the Flash Protection Boundary for this work is 10 feet.

Examiner Note: Examinee may also note that the walls, floor and ceiling of the switchgear room can be used as a part of the flash protection boundary, however the JPM step only requires identifying 10 feet as the boundary. The flash protection boundary is listed in 01DP-0IS13, PVNGS Electrical Safe Work Practices, Appendix A, page 3 of 4, for Door/Cover Closed & Secured for a 480V load center.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • Determine the MINIMUM PPE/EPE for the evolution.

Proc Step:

Standard: Determined that (in addition to the always required PPE) that the following PPE/EPE is required:

Hearing Protection Arc Face Shield with Balaclava FR Gloves FR Shirt FR Pants FR Coveralls Examiner Note: The listed PPE/EPE is from 01DP-0IS13, PVNGS Electrical Safe Work Practices, Appendix B, page 7 of 11, 301-600V Load Centers, Racking Breaker with Door Closed.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 01 03/09/05 3 Changed EPE requirements and Flash protection boundary.

02 01/27/2009 6 Changed format.

03 07/29/2015 3, 6 Changed glove requirements to FR and new format.

04 4/19/2016 6 Modified JPM from racking a 4.16kV breaker to racking a 480V breaker.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A2 Rev 1 EXAMINEE INITIAL CONDITIONS:

The unit is hanging a clearance on the A Charging Pump, CHA-P01.

You have been directed to rack out the breaker for the A Charging Pump, PGA-L31C4, per 40OP-9PG01, 480V Class 1E Switchgear, Appendix B - Breaker Racking Instructions.

INITIATING CUE:

Identify the required Flash Protection Boundary and the MINIMUM Personal Protective Equipment / Electrical Protection Equipment (in addition to the PPE always required inside the unit) for this evolution per 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices.

Document your answers in the space provided below.

Flash Protection Boundary: _______________________________________

PPE/EPE Required: _____________________________________________

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM INFORMATION TASK: 1280020001 - Perform Mode 1 Surveillance Logs Correctly determined all MODE 1 Surveillance parameters maximum deviations and TASK STANDARD: determined ONLY parameters SG2 WR Level and RWT Level did not meet acceptance criteria.

K/A: G 2.2.12 RATING: RO: 3.7 SRO: 4.1 10CFR55: 45.13 POSITION(S): RO/SRO VALIDATION TIME: 15 minutes

REFERENCES:

40ST-9ZZM1, Operations Mode 1 Surveillance Logs LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/20/2016 VALIDATED BY: Joseph Stevens DATE: 7/5/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 PROCEDURES/MATERIALS:

40ST-9ZZM1, Operations Mode 1 Surveillance Logs, Section 6.1.5 and Appendix B This JPM was written using Revision 68 of 40ST-9ZZM1, Operations Mode 1 Surveillance Logs.

This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 is operating at 100% power.

INITIATING CUE:

The CRS directs you to perform 40ST-9ZZM1, Operations Mode 1 Surveillance Logs, Section 6.1.5, Plant Protection System (PPS) Instrument Channel Checks, step 6.1.5.1, and complete the provided data sheet from Appendix B.

Another operator will perform the channel checks for Minimum Static DNBR using the CPC Cross Channel Report.

Use the provided sheet of current instrument readings to complete the surveillance.

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM START TIME:

JPM Step: 1

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

Refueling Water Tank Level Standard: Determined the maximum deviation to be 1.1% and determined this DOES NOT meet the acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: instrumentation and associated functions:

SG1 Primary Loop Flow Standard: 6.1.5.1 Determined the maximum deviation to be 2 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 3

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG2 Primary Loop Flow Standard: Determined the maximum deviation to be 3 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM Step: 4

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

Pressurizer Pressure Standard: Determined the maximum deviation to be 25 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

Pressurizer Pressure Standard: Determined the maximum deviation to be 10 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

Containment Pressure Standard: Determined the maximum deviation to be 0.25 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM Step: 7

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

Containment Pressure Standard: Determined the maximum deviation to be 0.5 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 8

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG1 Pressure Standard: Determined the maximum deviation to be 10 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 9

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG2 Pressure Standard: Determined the maximum deviation to be 10 psid and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM Step: 10

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG1 Wide Range Level Standard: Determined the maximum deviation to be 4% and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 11

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG2 Wide Range Level Standard: Determined the maximum deviation to be 6% and determined this DOES NOT meet acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 12

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG1 Narrow Range Level Standard: Determined the maximum deviation to be 2% and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 JPM Step: 13

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

SG2 Narrow Range Level Standard: Determined the maximum deviation to be 2% and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 14

  • Perform a channel check of the following Plant Protection System (PPS)

Proc Step: 6.1.5.1 instrumentation and associated functions:

LPD Margin Standard: Determined the maximum deviation to be 0.3 kw/ft and determined this meets acceptance criteria.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 4/20/2016 6 JPM created.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A3 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 is operating at 100% power.

INITIATING CUE:

The CRS directs you to perform 40ST-9ZZM1, Operations Mode 1 Surveillance Logs, Section 6.1.5, Plant Protection System (PPS) Instrument Channel Checks, step 6.1.5.1, and complete the provided data sheet from Appendix B.

Another operator will perform the channel checks for Minimum Static DNBR using the CPC Cross Channel Report.

Use the provided sheet of current instrument readings to complete the surveillance.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 JPM INFORMATION TASK: 1290320301 - Hang a Clearance Determined the clearance requiring the lowest dose to hang is using HV-4, HV-7 TASK STANDARD:

and HV-8.

K/A: G 2.3.14 RATING: RO: 3.4 SRO: 3.8 10CFR55: 45.10 POSITION(S): AO/RO/SRO VALIDATION TIME: 15 minutes

REFERENCES:

75DP-0RP03, ALARA Program Overview LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/19/2016 VALIDATED BY: Joseph Stevens DATE: 7/5/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 PROCEDURES/MATERIALS:

Handout with valve diagram and associated equations required to determine dose rates at each valve (handout on last page of JPM).

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

There is a 5 Curie (Ci) point source in the body of HV-5.

HV-5 needs to have a clearance hung to facilitate replacement of HV-5.

HV-5 must be isolated on both the upstream and downstream sides.

INITIATING CUE:

The CRS directs you to determine which valves (see provided drawing) should be isolated to ensure the lowest dose to the individual hanging the clearance.

Document your answer on the space provided below.

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 JPM START TIME:

JPM Step: 1

  • Determine the dose rate at 1 meter from HV-5.

Standard: Determined the dose rate 1 meter from HV-5 is 5 rem/hr.

Answer Explanation:

1 Ci = 1 rem/hr @ 1 meter, therefore 5 Ci = 5 rem/hr @ 1 meter.

Comments (required for UNSAT):

SAT UNSAT Step: 2

  • Determine the dose rates at HV-4.

Standard: Determined the dose rates at HV-4 to be 313 mrem/hr.

Answer Explanation:

(Dose Rate 1)(Distance 1)2 = (Dose Rate 2)(Distance 2)2 (5 rem/hr)(1 meter)2 = (Dose Rate 2)(4 meters)2 Dose Rate 2 = (5 rem/hr)(1 meter2) / (16 meters2)

Dose Rate 2 = 313 mrem/hr Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 Step: 3

  • Determine the dose rates at HV-1, HV-2, and HV-3.

Standard: Determined the dose rates at HV-1, HV-2, and HV-3 to be 139 mrem/hr for a total effective dose rate of 417 mrem/hr.

Answer Explanation:

(Dose Rate 1)(Distance 1)2 = (Dose Rate 2)(Distance 2)2 (5 rem/hr)(1 meter)2 = (Dose Rate 2)(6 meters)2 Dose Rate 2 = (5 rem/hr)(1 meter2) / (36 meters2)

Dose Rate 2 = 139 mrem/hr Since 3 valves must be tagged, the effective dose rate is 417 mrem/hr Comments (required for UNSAT):

SAT UNSAT Step: 4

  • Determine the dose rates at HV-6.

Standard: Determined the dose rates at HV-6 to be 200 mrem/hr.

Answer Explanation:

(Dose Rate 1)(Distance 1)2 = (Dose Rate 2)(Distance 2)2 (5 rem/hr)(1 meter)2 = (Dose Rate 2)(5 meters)2 Dose Rate 2 = (5 rem/hr)(1 meter2) / (25 meters2)

Dose Rate 2 = 200 mrem/hr Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 Step: 5

  • Determine the dose rates at HV-7 and HV-8.

Standard: Determined the dose rates at HV-7 and HV-8 to be 156 mrem/hr.

Answer Explanation:

(Dose Rate 1)(Distance 1)2 = (Dose Rate 2)(Distance 2)2 (5 rem/hr)(1 meter)2 = (Dose Rate 2)(8 meters)2 Dose Rate 2 = (5 rem/hr)(1 meter2) / (64 meters2)

Dose Rate 2 = 78 mrem/hr Since 2 valves must be tagged, the effective dose rate is 156 mrem/hr.

Comments (required for UNSAT):

SAT UNSAT Step: 6

  • Determine the lowest dose clearance.

Standard: Determined the lowest dose clearance to be HV-4, HV-7 and HV-8.

Answer Explanation:

Total Dose Rate for HV-4 + HV-7 + HV-8 = 469 mr/hr Total Dose Rate for HV-4 + HV-6 = 513 mr/hr Total Dose Rate for HV-1 + HV-2 + HV-3 + HV-6 = 617 mr/hr Total Dose Rate for HV-1 + HV-2 + HV-3 + HV-7 + HV-8 = 573 mr/hr Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 2/24/2016 6 JPM created 1 4/19/2016 6 Numbers changed to modify the JPM.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A4 Rev 1 EXAMINEE INITIAL CONDITIONS:

There is a 5 Curie (Ci) point source in the body of HV-5.

HV-5 needs to have a clearance hung to facilitate replacement of HV-5.

HV-5 must be isolated on both the upstream and downstream sides.

INITIATING CUE:

The CRS directs you to determine which valves (see provided drawing) should be isolated to ensure the lowest dose to the individual hanging the clearance.

Document your answer on the space provided below.

Valves to be isolated: __________________________________

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 JPM INFORMATION TASK: 1290020301 - Conduct of Shift Operations Determined that Operator #1 DOES have an active license and Operators #2 and #3 TASK STANDARD:

DO NOT have active licenses as of April 1.

K/A: G 2.1.1 RATING: RO: 3.8 SRO: 4.2 10CFR55: 45.13 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40DP-9OP02, Conduct of Shift Operations LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/20/2016 VALIDATED BY: Joseph Stevens DATE: 7/5/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 PROCEDURES/MATERIALS:

40DP-9OP02, Conduct of Shift Operations, Section 4.2, Licensed Operator Watchstanding Proficiency.

This JPM was written using Revision 68 of 40DP-9OP02, Conduct of Shift Operations. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Today is April 1, 2016.

You are reviewing the license status of 3 licensed operators based on watches stood in the previous quarter.

Operator # 1 received his SRO license on June 10 of 2014.

Operator # 2 received her RO license on June 10 of 2014.

Operator # 3 received his RO license on November 15 of 2015.

All operators are current in LOCT.

INITIATING CUE:

Using the provided list of watches stood by each of the 3 operators in the previous quarter, determine whether or not each of their licenses is active or not as of April 1 per 40DP-9OP02, Conduct of Shift Operations.

Document your answers below by circling the status of each operator license as of April 1.

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 JPM START TIME:

JPM Step: 1

  • Determine if Operator # 1 license is active on April 1.

Proc Step: N/A Standard: Determined that Operator # 1s license IS active on April 1.

Answer Explanation:

An SRO license is considered active if they stand a minimum of five 12-hour shifts in the previous quarter. Per step 4.2.2 of 40DP-9OP02, Conduct of Shift Operations, at least one of those shifts must be in the CRS or SM position, however the other 4 shifts can be in a TS required RO position, therefore the SRO license remains active.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • Determine if Operator # 2s license is active on April 1.

Proc Step: N/A Standard: Determined that Operator # 2s license IS NOT active on April 1.

Answer Explanation:

An RO license is considered active if they stand a minimum of five 12-hour shifts in the RO or CO position in the previous quarter. While Operator # 2 completed 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> in the RO and CO position, partial shifts cannot be credited (per step 4.2.2 bullet 5), therefore, even though the 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> were met, the requirement for five 12-hour shifts was not, making the RO license inactive as of April 1.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 JPM Step: 3

  • Determine if Operator # 3s license is active on April 1.

Proc Step: N/A Standard: Determined that Operator # 3s license IS NOT active on April 1.

Answer Explanation:

Operator # 3 stood five 12-hour shifts, and at least one of those (4 actually) was in the RO position, however the allowance for SROs to stand an RO or lower for 4 of their 5 required shifts does not translate into an RO being able to credit a non-licensed position as one of the required five 12-hour shifts, therefore the RO license is inactive as of April 1.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 4/20/16 6 JPM created.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A5 Rev 1 EXAMINEE INITIAL CONDITIONS:

Today is April 1, 2016.

You are reviewing the license status of 3 licensed operators based on watches stood in the previous quarter.

Operator # 1 received his SRO license on June 10 of 2014.

Operator # 2 received her RO license on June 10 of 2014.

Operator # 3 received his RO license on November 15 of 2015.

All operators are current in LOCT.

INITIATING CUE:

Using the provided list of watches stood by each of the 3 operators in the previous quarter, determine whether or not each of their licenses is active or not as of April 1 per 40DP-9OP02, Conduct of Shift Operations.

Document your answers below by circling the status of each operator license as of April 1.

Operator # 1 License: Active / Inactive Operator # 2 License: Active / Inactive Operator # 3 License: Active / Inactive EXAMINEE

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 JPM INFORMATION TASK: 1290520004 - Rack in/rack out a 480 volt load center breaker Determined the minimum required Flash Protection Boundary is 10 feet and the TASK STANDARD: minimum required PPE/EPE: hearing protection, arc face shield with balaclava, RF gloves, FR shirt, FR pants, and FR coveralls.

K/A: G 2.1.26 RATING: RO: 3.4 SRO: 3.6 10CFR55: 45.12 POSITION(S): AO/RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/19/16 VALIDATED BY: Joseph Stevens DATE: 7/5/16 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 PROCEDURES/MATERIALS:

01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices o Section 4.10, PPE and EPE o Section 4.11, Barrier, Guards, and Posting Practices o Appendix A, Safe Working Distances o Appendix B, PPE/EPE Matrix 40OP-9PG01, 480V Class 1E Switchgear o Appendix B, Breaker Racking Instructions, Section B.1, Racking Out Breakers This JPM was written using Revision 12 of 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices and Revision 22 of 40OP-9PG01, 480V Class 1E Switchgear.

This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

The unit is hanging a clearance on the A Charging Pump, CHA-P01.

You have been directed to rack out the breaker for the A Charging Pump, PGA-L31C4, per 40OP-9PG01, 480V Class 1E Switchgear, Appendix B - Breaker Racking Instructions.

INITIATING CUE:

Identify the required Flash Protection Boundary and the MINIMUM Personal Protective Equipment / Electrical Protection Equipment (in addition to the PPE always required inside the unit) for this evolution per 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices.

Document your answers in the space provided below.

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 JPM START TIME:

JPM Step: 1

  • Determine the minimum Flash Protection Boundary per Appendix A.

Proc Step: N/A Standard: Determined the Flash Protection Boundary for this work is 10 feet.

Examiner Note: Examinee may also note that the walls, floor and ceiling of the switchgear room can be used as a part of the flash protection boundary, however the JPM step only requires identifying 10 feet as the boundary. The flash protection boundary is listed in 01DP-0IS13, PVNGS Electrical Safe Work Practices, Appendix A, page 3 of 4, for Door/Cover Closed & Secured for a 480V load center.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • Determine the MINIMUM PPE/EPE for the evolution.

Proc Step:

Standard: Determined that (in addition to the always required PPE) that the following PPE/EPE is required:

Hearing Protection Arc Face Shield with Balaclava FR Gloves FR Shirt FR Pants FR Coveralls Examiner Note: The listed PPE/EPE is from 01DP-0IS13, PVNGS Electrical Safe Work Practices, Appendix B, page 7 of 11, 301-600V Load Centers, Racking Breaker with Door Closed.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 01 03/09/05 3 Changed EPE requirements and Flash protection boundary.

02 01/27/2009 6 Changed format.

03 07/29/2015 3, 6 Changed glove requirements to FR and new format.

04 4/19/2016 6 Modified JPM from racking a 4.16kV breaker to racking a 480V breaker.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A6 Rev 1 EXAMINEE INITIAL CONDITIONS:

The unit is hanging a clearance on the A Charging Pump, CHA-P01.

You have been directed to rack out the breaker for the A Charging Pump, PGA-L31C4, per 40OP-9PG01, 480V Class 1E Switchgear, Appendix B - Breaker Racking Instructions.

INITIATING CUE:

Identify the required Flash Protection Boundary and the MINIMUM Personal Protective Equipment / Electrical Protection Equipment (in addition to the PPE always required inside the unit) for this evolution per 01DP-0IS13, Palo Verde Nuclear Generating Station Electrical Safe Work Practices.

Document your answers in the space provided below.

Flash Protection Boundary: _______________________________________

PPE/EPE Required: _____________________________________________

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 JPM INFORMATION TASK: 1290190102 - Ensure compliance with Tech Specs Identified the following Technical Specification LCO conditions entry and exit times, ONLY:

LCO 3.5.3 A entered at 0800 and exited at 1300 TASK STANDARD:

LCO 3.5.3 B entered at 1200 and exited at 1800 LCO 3.8.1 B entered at 1000 and exited at 1700 LCO 3.0.3 entered at 1600 and exited at 1700 K/A: G 2.2.40 RATING: RO: 3.4 SRO: 4.7 10CFR55: 45.13 POSITION(S): SRO VALIDATION TIME: 15 minutes Technical Specifications, Technical Specification Bases, Technical Requirements

REFERENCES:

Manual LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: YES APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 10/28/2015 VALIDATED BY: Joseph Stevens DATE: 7/05/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT/ UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 PROCEDURES/MATERIALS:

Technical Specifications Technical Specifications Bases Technical Requirements Manual (TRM)

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Given the following timeline of events on Unit 1 while operating at 100% power:

At time 0800, the A LPSI pump was declared inoperable.

At time 1000, the B EDG was declared inoperable.

At time 1200, the A HPSI pump was declared inoperable.

At time 1300, the A LPSI pump was declared OPERABLE.

At time 1700, the B EDG was declared OPERABLE.

At time 1800, the A HPSI pump was declared OPERABLE.

INITIATING CUE:

Your task is to determine all Technical Specification LCO conditions entered, the times they were entered, and, if applicable, exited, based on the provided timeline of events.

Document your answers in the table below.

NOTE: All provided boxes may or may not be used.

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 JPM START TIME:

Step: 1

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.5.3 condition A must be entered at 0800 due to the inoperable LPSI pump.

Examiner Note: Examinee may also list entering TLCO 3.5.201. This would not be incorrect but is also not critical.

Comments (required for UNSAT):

SAT UNSAT Step: 2

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.8.1 condition B must be entered at 1000 due to the inoperable EDG.

Comments (required for UNSAT):

SAT UNSAT Step: 3

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.5.3 condition B must be entered at 1200 due to the inoperable HPSI pump.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 Step: 4

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.5.3 condition A can be exited at 1300 due to the LPSI pump being declared OPERABLE.

Examiner Note: Examinee may also list exiting TLCO 3.5.201. This would not be incorrect but is also not critical.

Comments (required for UNSAT):

SAT UNSAT Step: 5

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.0.3 must be entered at 1600 due to both HPSI pumps being inoperable, which is an unanalyzed condition.

Examiner Note: Answer explanation:

At 1200, the B EDG and the A HPSI pump were inoperable at the same time. 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from that point (1600), if both are still inoperable, the B HPSI pump must be declared inoperable. Two trains of SI inoperable without 100% SI flow equivalent available is an unanalyzed condition which requires entry into LCO 3.0.3.

Comments (required for UNSAT):

SAT UNSAT Step: 6

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.8.1 condition B and LCO 3.0.3 can be exited at 1700 due to the EDG being declared OPERABLE.

Examiner Note: Answer explanation:

Since the B HPSI pump was only inoperable due to the B EDG being inoperable, both the B EDG and B HPSI pump are now OPERABLE. Since LCO 3.0.3 was entered due to two HPSI pumps being inoperable, LCO 3.0.3 can now be exited.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 Step: 7

  • Determine LCO condition(s) to be entered and/or exited.

Standard: Determined LCO 3.5.3 condition B can be exited at 1800 due to the A HPSI pump being declared OPERABLE.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 10/28/15 6 JPM created REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A7 Rev 1 EXAMINEE INITIAL CONDITIONS:

Given the following timeline of events on Unit 1 while operating at 100% power:

At time 0800, the A LPSI pump was declared inoperable.

At time 1000, the B EDG was declared inoperable.

At time 1200, the A HPSI pump was declared inoperable.

At time 1300, the A LPSI pump was declared OPERABLE.

At time 1700, the B EDG was declared OPERABLE.

At time 1800, the A HPSI pump was declared OPERABLE.

INITIATING CUE:

Your task is to determine all Technical Specification LCO conditions entered, the times they were entered, and, if applicable, exited, based on the provided timeline of events.

Document your answers in the table below.

NOTE: All provided boxes may or may not be used.

Time LCO condition entered LCO condition exited EXAMINEE

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 JPM INFORMATION TASK: 1290320301 - Hang a Clearance Determined AO Sally may receive a maximum dose of 50 mrem during the TASK STANDARD: remainder of her pregnancy, and determined that the NRC must be notified within 30 days of the overexposure of the embryo/fetus.

K/A: G 2.3.4 RATING: RO: 3.2 SRO: 3.7 10CFR55: 45.10 POSITION(S): SRO VALIDATION TIME: 20 minutes 75DP-0RP03, ALARA Program Overview, 75DP-9RP01, Radiation Exposure and

REFERENCES:

Access Control LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 4/19/2016 VALIDATED BY: Joseph Stevens DATE: 7/5/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 PROCEDURES/MATERIALS:

75DP-9RP01, Radiation Exposure and Access Control.

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

As of June 1, 2016, AO Sally had received a total effective dose equivalent of 485 mrem.

On June 2, 2016, she found out she is pregnant.

The doctor estimates her date of conception was January 1, 2016.

On June 3, 2016, she hung a clearance in the RCA..

She received 30 mrem while hanging the clearance.

On June 4, 2016, she completed 75DP-9RP01, Radiation Exposure and Access Control, Appendix A, Pre-Natal Dose Limit Statement, to declare her pregnancy.

INITIATING CUE:

The SM directs you to determine the MAXIMUM dose Sally can receive for the remainder of her pregnancy per 75DP-9RP01, Radiation Exposure and Access Control, determine if the NRC must be notified, and if applicable, the time requirement for the notification.

Document your answer on the space provided below.

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 JPM START TIME:

Step: 7

  • Determine the maximum dose available for the duration of the pregnancy.

Standard: Determined that AO Charlotte can receive a maximum of 50 mrem for the duration of the pregnancy.

Answer Explanation: Since she received > 500 mrem since the estimated date of conception, she is allowed a maximum of 50 additional mrem during the remainder of the pregnance.

Comments (required for UNSAT):

SAT UNSAT Step: 8

  • Determine if a notification to the NRC is required.

Standard: Determined that the NRC must be notified of the embryo/fetus receiving > 500 mrem.

Answer Explanation: Although the dose was received prior to the declaration of the pregnancy, AO Charlotte has received 515 mrem TEDE since the estimated date of conception which is considered an overexposure to the embryo/fetus and requires a written report to the NRC.

Comments (required for UNSAT):

SAT UNSAT Step: 9

  • Determine the required time to notify the NRC of the overexposure.

Standard: Determined the NRC must be notified within 30 days due to the overexposure of the embryo/fetus.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 2/24/2016 6 JPM created 1 4/19/2016 6 Numbers changed to modify the JPM.

2 9/29/2016 6 Added SRO only portion to end of JPM (second cue)

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A8 Rev 1 EXAMINEE INITIAL CONDITIONS:

As of June 1, 2016, AO Sally had received a total effective dose equivalent of 485 mrem.

On June 2, 2016, she found out she is pregnant.

The doctor estimates her date of conception was January 1, 2016.

On June 3, 2016, she hung a clearance in the RCA.

She received 30 mrem while hanging the clearance.

On June 4, 2016, she completed 75DP-9RP01, Radiation Exposure and Access Control, Appendix A, Pre-Natal Dose Limit Statement, to declare her pregnancy.

INITIATING CUE:

The SM directs you to determine the MAXIMUM dose Sally can receive for the remainder of her pregnancy per 75DP-9RP01, Radiation Exposure and Access Control, determine if the NRC must be notified, and if applicable, the time requirement for the notification.

Document your answer on the space provided below.

Maximum remaining dose: _________________________________

NRC notification required (circle one): YES / NO Notification due (if applicable): _____________________________

EXAMINEE

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 JPM INFORMATION TASK: 1240100202 - Classify events requiring emergency plan implementation Classified the event as HU2.2 within 15 minutes and completed NAN form EP-0541 TASK STANDARD:

within 13 minutes of the classification.

K/A: G 2.4.40 RATING: RO: 2.7 SRO: 4.5 10CFR55: 45.11 POSITION(S): SRO VALIDATION TIME: 15 minutes EP-0900, ERO Position Checklists, Appendix L, EP-0901, Classifications, EP-0902,

REFERENCES:

Notifications, EP-0905, Protective Actions, ODP-31, Operations Emergency Plan Implementation, and EAL Charts LOCATION: SIMULATOR PLANT CLASSROOM X TIME CRITICAL: YES ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 6/25/2015 VALIDATED BY: Joseph Stevens DATE: 7/05/2016 TECH OPERATIONS REVIEW: APPROVAL:

E-PLAN TRAINING REVIEW: APPROVAL:

Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT/ UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM A9 Rev 1

1. PROCEDURES/MATERIALS:

EP-0900, ERO Position Checklists, Appendix L EP-0901, Classifications EP-0902, Notifications EP-0905, Protective Actions ODP-31, Operations Emergency Plan Implementation EAL Charts A-G4-001 Met Tower Data File This JPM was written using Revision 14 of EP-0900, Revision 9 of EP-0901, Revision 8 of EP-0902, Revision 8 of EP-0905, and Revision 1 of ODP-31. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

You are the Unit 1 Shift Manager.

Unit 1 was operating at 100% power when Unit Aux Transformer, 1-E-MAN-X02, faulted.

SPTAs are in progress.

Area 1 has just reported massive bulging and scorching on the UAT.

The CRS will complete 14DP-0FP32, Emergency Notification and Response, as required.

INITIATING CUE:

Your task is to classify the event per EP-0901, Classifications.

Inform the examiner of your classification when you have completed the classification and document in the space provided below.

After you have informed the examiner of the classification, complete NAN Form EP-0541, through step 6 and hand to the examiner.

For the purposes of filling out EP-0541, you can assume:

o This is a drill o Authenticator Code is Tango Mike For the purpose of this JPM, all steps other than determining the correct EAL and filling out EP-0541 have been or will be performed by another EC qualified person.

This is a TIME CRITICAL JPM.

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 JPM START TIME:

JPM Step: 1* Classify the event using the appropriate E-Plan procedures and charts.

Standard: Classified the event as HU2.2 within 15 minutes.

Examiner Note: Document the time to classify below (must be 15 minutes):

JPM Start Time: ____________

Classification Time: _____________

Time to classify: ______________ minutes Comments (required for UNSAT):

SAT UNSAT Examiner Note: The following steps are sub-steps of filling out NAN Form EP-0541.

Step: 2* Determine if this is a drill or an actual event and check the correct box.

Standard: Determined this is a drill from the initiating cue and checked the This is a drill box on EP-0541.

Comments (required for UNSAT):

SAT UNSAT Step: 3* Check event level box and filled out the event declaration time, date and driving current classification level.

Standard: Checked the Unusual Event box, filled out the current time and date, and listed HU2.2 as the current classification level.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 Step: 4* Fill out the 35 foot elevation 15 minute average wind speed and direction.

Standard: Filled in 3.2 mph for wind speed and 285° for wind direction (data from the provided Met Data Tower sheet).

Comments (required for UNSAT):

SAT UNSAT Step: 5* Fill in the Authenticator Code.

Standard: Filled in Tango Mike as the authenticator code (code provided in the initiating cue).

Comments (required for UNSAT):

SAT UNSAT Step: 6 Check the correct communicator box.

Standard: Checked the STSC Comm box.

Comments (required for UNSAT):

SAT UNSAT Step: 7* Determined the radioactive release status and check the appropriate box.

Standard: Checked the There is NO radioactive release due to this event box.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 Step: 8* Determine protective actions, if any, and check the appropriate box.

Standard: Checked the There are NO PROTECTIVE ACTIONS required box.

Comments (required for UNSAT):

SAT UNSAT Step: 9* Sign the approval line and enter the current time and date.

Standard: Signed the approval line and entered the current time and date.

Examiner Note: Document the time to complete NAN Form EP-0541 (must be 15 minutes):

Classification Time: ______________

Time NAN Form EP-0541 turned in: _______________

Time to complete NAN Form EP-0541: ______________ minutes Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 01 9/25/07 6 Changed from EP040 to EP030 02 12/7/07 6 Revised cue for step 15 03 7/27/10 3 Modified JPM to rev 34 of EPIP-01 04 6/21/11 6 New JPM format and procedure revision 05 6/25/15 6 New JPM format REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM A9 Rev 1 EXAMINEE INITIAL CONDITIONS:

You are the Unit 1 Shift Manager.

Unit 1 was operating at 100% power when Unit Aux Transformer, 1-E-MAN-X02, faulted.

SPTAs are in progress.

Area 1 has just reported massive bulging and scorching on the UAT.

The CRS will complete 14DP-0FP32 as required.

INITIATING CUE:

Your task is to classify the event per EP-0901, Classifications.

Inform the examiner of your classification when you have completed the classification and document in the space provided below.

After you have informed the examiner of the classification, complete NAN Form EP-0541, through step 6 and hand to the examiner.

For the purposes of filling out EP-0541, you can assume:

o This is a drill o Authenticator Code is Tango Mike For the purpose of this JPM, all steps other than determining the correct EAL and filling out EP-0541 have been or will be performed by another EC qualified person.

This is a TIME CRITICAL JPM.

Event Classification: ________________

EXAMINEE

ES-301 Control Room / In-Plant Systems Outline Form ES-301-2 Facility: PVNGS Date of Examination: 10/28/16 Exam Level: RO SRO(I) SRO (U) Operating Test No.: 2016 NRC Control Room Systems@ (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function S1 001 (RO ONLY) Perform CEA Operability Check N, S 1 S2 013 Verify Recirculation Actuation Signal actuation A, D, EN, L, S 2 S3 006 Raise Safety Injection Tank pressure N, S 3 S4 003 Operate RCPs and seal bleedoff in response to a loss A, M, S 4P of NC S5 061 Loss of Turbine Water Cooling, Reducing Heat Loads A, D, L, S 4S on TC S6 022 Restoration of Containment Cooling D, L, S 5 S7 062 Perform contingency actions for verification of vital A, D, L, S 6 auxiliaries in SPTAs S8 015 De-energizing startup channels (40OP-9ZZ03, App D, L, N, S 7 section D.2.2)

In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

P1 068 Align borated water source A, D, E, R 8 P2 004 Respond to gas binding of a Charging Pump E, N, R 2 P3 028 Place Purge Exhaust in service E, D, R 5 RO: Will perform all simulator and in-plant JPMs SRO(I): Will perform all simulator and in-plant JPMs with the exception of S-1 SRO(U): Will perform S-2, S-4, S-5, P-1, P-3 (safety functions 2, 4P, 4S, 5 and 8) 1 of 4 PVNGS 2016 NRC RO & SRO JPM Outline ES-301-2 Rev 4

ES-301 Control Room / In-Plant Systems Outline Form ES-301-2

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 (5) / 4-6 (5) / 2-3 (4)

(C)ontrol room (D)irect from bank 9 (6) / 8 (6) / 4 (4)

(E)mergency or abnormal in-plant 1 (3) / 1 (3) / 1 (2)

(EN)gineered safety feature 1 (1) / 1 (1) / 1 (1) (control room system)

(L)ow Power / Shutdown 1 (5) / 1 (5) / 1 (2)

(N)ew or (M)odified from bank including 1(A) 2 (5 - 1A) / 2 (4 - 1A) / 1 (1 - 1A)

(P)revious 2 exams 3 (0) / 3 (0) / 2 (0) (randomly selected)

(R)CA 1 (3) / 1 (3) / 1 (2)

(S)imulator NRC JPM Examination Summary Description S1 The applicant will perform 40ST-9SF01, CEA Operability Checks, Section 6.1, Exercising CEAs at Power, following the replacement of an ACTM card for CEA 66. The applicant will select the correct CEA, select the correct mode of operation, insert the CEA a minimum of 5 (minimum required for the ST) not to exceed 6.6 (TS limit for CEA deviation) and withdraw the CEA back to the upper electrical limit. This is a new JPM and is covered by safety function 1.

S2 The applicant will be directed to perform 40EP-9EO03, LOCA, step 58, verification of RAS actuation. The applicant will determine that not all RAS actuated equipment automatically aligned to their actuated position and will take contingency actions in response to this condition. The applicant will have to identify the Train B ESF pump suction valve from containment, SIB-UV-675, did not open and stop the Train B HPSI and Train B CS Pumps. This is a time critical, alternate path, bank JPM and is covered by safety function 2.

S3 The applicant will be directed to raise pressure on Safety Injection Tank 1A per 40OP-9SI03, Safety Injection Tank Operations, Section 6.1, Pressurizing the Safety Injection Tanks to Establish or Maintain Normal Pressure. The applicant will align nitrogen to SIT 1A and commence raising pressure. The applicant must stop raising pressure after exceeding 615 psig (directed in cue) and prior to exceeding 625 psig (TS limit), and restore the normal nitrogen lineup. This is a new JPM and is covered by safety function 3.

S4 The applicant will be directed to perform 40AO-9ZZ03, Loss of Cooling Water, Section 4.0, Nuclear Cooling Water, steps 5 and 6. The applicant will be required to perform the procedural diagnostic steps to determine what the cause of the loss of NC was (an 2 of 4 PVNGS 2016 NRC RO & SRO JPM Outline ES-301-2 Rev 4

ES-301 Control Room / In-Plant Systems Outline Form ES-301-2 inadvertent closure of an NC containment isolation valve), attempt to mitigate the event by reopening the containment isolation valve (wont reopen), and take the contingency actions to close the other two NC containment isolation valves, trip the reactor, stop all of the RCPs, and isolate seal bleedoff. One of the seal bleedoff isolation valves will fail to close and the applicant will have to isolate bleedoff using alternate means (closing the inside and outside seal bleedoff containment isolation valves and closing the bleedoff relief isolation valve). This is a time critical, alternate path, modified bank JPM and is covered by safety function 4P.

S5 The applicant will be directed to perform 40AO-9ZZ03, Loss of Cooling Water, Appendix B, Minimize Cooling Load on TC, following a complete loss of Turbine Cooling Water.

The applicant will isolate SG blowdown, transition to auxiliary feedwater, trip the Main Feedwater Pumps, stop all Condensate Pumps and stop both Heater Drain Pumps. In the setup of the JPM, both TC pumps will be tripped, the reactor will have been tripped, and Auxiliary Feedwater Pump B will be tagged out. The cue will direct transitioning to Auxiliary Feedwater Pump N, which will not be able to be started due to one of the suction valves being seized closed. The applicant will determine that Auxiliary Feedwater Pump A is the only viable option and will manually start Auxiliary Feedwater Pump A to supply feedwater and allow tripping of the Main Feedwater Pumps. This is an alternate path, bank JPM covered by safety function 4S.

S6 The applicant will be directed to perform 40EP-9EO10, Standard Appendices, Appendix 17, Restoration of Containment Cooling. The applicant will have to restore chill water to containment, ensuring valves are operated in a particular sequence to ensure chill water reliefs do not lift, and reset and restart the appropriate Air Cooling Units to restore containment cooling. This is a bank JPM and is covered by safety function 5.

S7 The applicant will be directed to perform the Vital Auxiliaries verification per 40EP-9EO01, Standard Post Trip Actions. The applicant will determine that the Train B Class 4kV bus is de-energized with the B EDG running and EDG output breaker open. The applicant will utilize the Standard Appendix 115 hard card to take contingency actions to re-energize the Train B Class 4kV bus. Upon restoration of the bus, the applicant will then have to recognize that the associated Spray Pond Pump has not started automatically and start the pump manually within 2.6 minutes (time critical action). This is a time critical, alternate path, bank JPM covered by safety function 6.

S8 The applicant will be directed to de-energize startup channel NIs per 40OP-9ZZ03, Reactor Startup, Appendix D, Checking NI Overlap and Turning Off Startup Channels.

The applicant will de-energize high volts from the NIs, transfer detector display from startup channels to control channels, reset all trouble and high CPS alarms, and reset the Boron Dilution Alarm System (BDAS) alarm. This is a new JPM covering safety function 7.

P1 The applicant will be directed to align Charging Pump suction to the Refueling Water Tank (RWT) per 40AO-9ZZ19, Control Room Fire, Appendix G, Upper Auxiliary Building Actions. The applicant will enter the aux building and attempt to realign the Charging Pump suction by operating valves from their associated load centers, however CHE-HV-536, RWT Gravity Feed to Charging Pump Suction Valve, will not open at the load center 3 of 4 PVNGS 2016 NRC RO & SRO JPM Outline ES-301-2 Rev 4

ES-301 Control Room / In-Plant Systems Outline Form ES-301-2 requiring local manual operation of the valve. The other valves in the sequence will operate as expected from their load centers. This is a time critical, alternate path, bank JPM covered by safety function 8.

P2 The applicant will be directed to determine the failed Charging Pump Pulsation Dampener Bladder following gas binding of a Charging Pump and isolate the failed pump per 40AO-9ZZ05, Loss of Charging or Letdown, Appendix I, Venting Charging Pumps and Header to the Recycle Drain Header. The applicant will check pulsation dampener supply pressure on the Charging Pumps and when the faulted pump is identified, will isolate the affected Charging Pump. This is a new JPM covered by safety function 2.

P3 The applicant will be directed to place the Train A Purge Exhaust Unit in service per 40EP-9EO10, Standard Appendices, Appendix 19, Containment Hydrogen Control, Attachment 19-J, Placing Purge Exhaust in Service. The applicant will align air to the hydrogen recombiner, unisolate service air purge line to containment, and energize the purge unit duct heater to place the purge exhaust unit in service. This is a bank JPM covered by safety function 5.

4 of 4 PVNGS 2016 NRC RO & SRO JPM Outline ES-301-2 Rev 4

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 JPM INFORMATION TASK: 1250440201 - Respond to a Control Room Fire Aligned Charging Pump suction to the Refueling Water Tank and completed all time TASK STANDARD:

critical actions within the allotted time standards.

K/A: 068 AA1.08 RATING: RO: 4.2 SRO: 4.2 10CFR55: 41.7 POSITION(S): AO/RO/SRO VALIDATION TIME: 15 minutes

REFERENCES:

40AO-9ZZ19, Control Room Fire LOCATION: SIMULATOR PLANT X CLASSROOM TIME CRITICAL: YES ALTERNATE PATH: YES PRA/SRA RELATED: YES APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/19/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 PROCEDURES/MATERIALS:

40AO-9ZZ19, Control Room Fire, Appendix G, steps 1-7 Attached pictures of disconnect switch.

This JPM was written using Revision 33 of 40AO-9ZZ19. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

The time critical nature of this JPM is based on actions identified in Appendix D of 40DP-9ZZ04, Time Critical Action Program.

Due to the alternate portion of this JPM extending the completion time by ~ 5 minutes (validated via operator walkdown), the first three steps of 40AO-9ZZ19, Control Room Fire, Appendix G, are cued as being completed and the JPM is started upon entry to the RCA. The first three steps of Appendix G and transit time to the RCA was also validated to take ~ 5 minutes. Since not performing the first three steps or transiting to the RCA is approximately equal to the extra time to perform the time critical actions, the JPM is still treated as time critical with an initial time critical action of 30 minutes.

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

IN-PLANT JPMS ONLY:

Operation of in-plant equipment is to be SIMULATED ONLY. DO NOT operate any equipment.

Notify the Shift Manager when in-plant JPMs are being performed.

Inform the Control Room staff of any discovered deficiencies Comply with the REP. If it is not possible to enter an area it may be permissible to discuss the equipment and operation with evaluator. DO NOT enter Contaminated Areas or High Radiation Areas.

INITIAL CONDITIONS:

The Control Room has been evacuated due to a fire.

One Charging Pump is running.

INITIATING CUE:

The CRS directs you to realign charging pump suction to the Refueling Water Tank (RWT) per 40AO-9ZZ19, Control Room Fire, Appendix G, Upper Auxiliary Building Actions, steps 4-7.

Steps 1-3 of Appendix G have been completed.

Assume you have obtained a lantern.

THIS IS A TIME CRITICAL JPM

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 JPM START TIME:

Examiner Note: The cue should be provided to the examinee upon entry into the RCA. When the cue is read to the examinee, document the start time below.

Start time: ____________

JPM Step: 1

  • Perform the following at NHN-M7209, RWT Gravity Feed Line to Charging Pump Proc Step: 4.a Suction CHE-HV-536: (120 ft. Hallway East)

Place CS-3 in LOCAL.

Standard: Simulated placing CS-3 in LOCAL.

Examiner Cue: When the examinee simulates placing CS-3 in LOCAL:

CS-3 is pointing to LOCAL Comments (required for UNSAT):

SAT UNSAT Examiner Note: The following step represents the alternate path portion of the JPM.

JPM Step: 2

  • Perform the following at NHN-M7209, RWT Gravity Feed Line to Charging Pump Proc Step: 4.b Suction CHE-HV-536: (120 ft. Hallway East)

Open CHE-HV-536, RWT Gravity Feed to Charging Pump Suction, using the local control switch.

Standard: Simulated opening CHE-HV-536 and recognized that CHE-HV-536 did not open, requiring local manual operation per the contingency action.

Examiner Cue: When the examinee simulates opening CHE-HV-536:

CHE-HV-536 red light is OFF and the green light is ON Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 JPM Step: 3

  • Manually open CHE-HV-536. (BAMP Room)

Proc Step: 4.b.1 Standard: Simulated engaging the clutch and opening CHE-HV-536 locally.

This step must be completed within 30 minutes of the start of the JPM (based on TCA-31)

RWT flow established at time: _____________

Examiner Cue: When the examinee simulates opening CHE-HV-536:

CHE-HV-536 stem is up and the handwheel has rotated to the fully counterclockwise position If the examinee checks the Valve Position Indication (VPI):

Use a pen to indicate the VPI is at 100%.

Comments (required for UNSAT):

SAT UNSAT Examiner Note: Applicant and Examiner will need to perform a frisk prior to continuing the JPM. If applicant does not, correct him/her before moving on.

JPM Step: 4

  • Perform the following at NHN-M7208, Volume Control Tank Outlet CHN-UV-Proc Step: 5.a 501:

Place CS-3 in the LOCAL position.

Standard: Simulated placing CS-3 to LOCAL.

Examiner Cue: When the examinee simulates placing CS-3 in LOCAL:

CS-3 is pointing to LOCAL Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 JPM Step: 5

  • Perform the following at NHN-M7208, Volume Control Tank Outlet CHN-UV-Proc Step: 5.b 501:

WHEN CHE-HV-536 is open, THEN close CHN-UV-501, VCT Outlet using the local control switch.

Standard: Simulated closing CHN-UV-501.

This step must be completed within 44 minutes of the start of the JPM (based on TCA-32)

VCT isolated at time: ____________

Examiner Cue: When the examinee simulates closing CHN-UV-501:

CHN-UV-501 red light is OFF and the green light is ON Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 Examiner Note: The ZAN-C01 and ZAN-C02 cabinets are accessible from the back of the cabinets. When you walk behind the cabinets, C01 is the cabinet on the right.

Each cabinet has a left and right panel door. The four disconnect switches are located in ZAN-C01. The pictures provided show the inside of each side of ZAN-C01 as well as a close up of each subpanel containing the applicable disconnect switches. All four disconnect switches are marked with a bright orange R for remote shutdown.

JPM Step: 6

  • Open ALL of the following disconnects in ZAN-C01: (120 ft. Aux Bldg Hallway Proc Step: 6 East)

DS 26-07, CHE-FV-241, RCP 1A Seal Injection Inlet (Fails Open)

DS 24-17, CHE-FV-242, RCP 1B Seal Injection Inlet (Fails Open)

DS 22-13, CHE-FV-244, RCP 2B Seal Injection Inlet (Fails Open)

DS 22-14, CHE-HV-532, RWT to BAMPs Suction (Fails Open)

Standard: Simulated opening DS 26-07, 24-17, 22-13, and 22-14.

This step must be completed within 60 minutes of the start of the JPM (based on TCA-33)

Disconnect switches open at time: ___________

Examiner Cue: When ZAN-C01 is located, give the examinee the attached pictures and have them describe how to open the disconnect switches.

When the examinee describes how to open the disconnect switches:

DS 26-07, 24-17, 22-13, and 22-14 knife switches are in the fully down position, not in electrical contact Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 JPM Step: 7 Inform the CRS that charging pump suction has been shifted to the RWT.

Proc Step: 7 Standard: Simulated informing the CRS that charging pump suction has been shifted to the RWT.

Examiner Cue: When the examinee simulates informing the CRS:

The CRS has been informed. This JPM is complete Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 02 12/3/09 6 New JPM format 03 7/18/12 3, 6 Procedure change and new JPM format 04 7/17/15 6 New JPM format 05 11/5/15 6 Modified JPM by removing steps 1-3 to facilitate starting the JPM in the RCA REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM P1 Rev 1 EXAMINEE INITIAL CONDITIONS:

The Control Room has been evacuated due to a fire.

One Charging Pump is running.

INITIATING CUE:

The CRS directs you to swap charging pump suction to the RWT per 40AO-9ZZ19, Control Room Fire, Appendix G, Upper Auxiliary Building Actions, steps 4-7.

Steps 1-3 of Appendix G have been completed.

Assume you have obtained a lantern.

THIS IS A TIME CRITICAL JPM EXAMINEE

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM INFORMATION TASK: 0150090401 - Perform Charging Pump Pulsation Dampener Operations Identified Charging Pump E and ONLY Charging Pump E has a failed pulsation TASK STANDARD:

dampener bladder, and isolated Charging Pump E.

K/A: 004 A4.08 RATING: RO: 3.8 SRO: 3.4 10CFR55: 45.6 POSITION(S): AO/RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40AO-9ZZ05, Loss of Charging and Letdown, Appendix I LOCATION: SIMULATOR PLANT X CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 5/27/2016 VALIDATED BY: John Rodgers DATE: 7/7/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 PROCEDURES/MATERIALS:

40AO-9ZZ05, Loss of Charging or Letdown, Appendix I, Steps 1-7.

This JPM was written using Revision 29 of 40AO-9ZZ05, Loss of Charging or Letdown. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

IN-PLANT JPMS ONLY:

Operation of in-plant equipment is to be SIMULATED ONLY. DO NOT operate any equipment.

Notify the Shift Manager when in-plant JPMs are being performed.

Inform the Control Room staff of any discovered deficiencies Comply with the REP. If it is not possible to enter an area it may be permissible to discuss the equipment and operation with evaluator. DO NOT enter Contaminated Areas or High Radiation Areas.

INITIAL CONDITIONS:

Unit 1 has experienced a Loss of Letdown.

The CRS has entered 40AO-9ZZ05, Loss of Charging or Letdown.

A Charging Pump is running with B and E Charging Pumps in standby.

Subsequently:

The A Charging Pump became air-bound.

The CRS transitioned to Appendix G, Responding to Gas Binding of Charging Pumps.

All Charging Pumps handswitches have been placed in Pull-To-Lock.

VCT level is 40%.

INITIATING CUE:

The CRS directs you to perform 40AO-9ZZ05, Loss of Charging or Letdown, Appendix I, Venting Charging Pumps and Header to the Recycle Drain Header, steps 1-7.

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM START TIME:

JPM Step: 1 IF CHA-P01, Charging Pump A, was the standby pump at the time of the failure, Proc Steps: 1.a THEN perform the following:

through 1.e Open CHN-VZ02, CHN-PI-1010 Root Isolation Valve. (100 #1 Charging Pump Room)

Open CHA-VZ05, CHA-P01 Pulsation Dampener CHA-X07 N2 Inlet Isol Valve. (100 #1 Charging Pump Room)

Check CHN-PI-1010, CHA-P01 Pulsation Dampener CHA-X07 N2 Supply Press Indic, indicates less than 100 psig.

Close CHA-VZ05, CHA-P01 Pulsation Dampener CHA-X07 N2 Inlet Isol Valve. (100 #1 Charging Pump Room)

Close CHN-VZ02, CHN-PI-1010 Root Isolation Valve. (100 #1 Charging Pump Room)

Standard: Marked these steps and substeps N/A since Charging Pump A was operating at the time of failure.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.a THEN perform the following:

Open CHN-VZ03, CHN-PI-1020 Root Isolation Valve. (100 #2 Charging Pump Room)

Standard: Simulated opening CHN-VZ03.

Examiner Cue: When the examinee simulates opening CHN-VZ03:

The handwheel for CHN-VZ03 is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 3

  • IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.b THEN perform the following:

Open CHB-VZ06, CHB-P01 Pulsation Dampener CHB-X07 N2 Inlet Isol Valve. (100 #2 Charging Pump Room)

Standard: Simulated opening CHB-VZ06.

Examiner Cue: When the examinee simulates opening CHB-VZ06:

The handwheel for CHB-VZ06 is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 4

  • IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.c THEN perform the following:

Check CHN-PI-1020, CHB-P01 Pulsation Dampener CHB-X07 N2 Supply Press Indic, indicates less than 100 psig.

Standard: Checked Pulsation Dampener supply pressure at CHN-PI-1020.

Examiner Cue: When the examinee checks CHN-PI-1010:

Use a pen to simulate CHN-PI-1020 indicating 1500 psig.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 5 IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.c.1 THEN perform the following:

IF CHN-PI-1020 indicates approximately 1500 psig, THEN notify the SM/CRS that the CHB-P01 pulsation dampener bladder is NOT failed.

Standard: Simulated notifying the SM/CRS that CHB-P01 pulsation dampener bladder is NOT failed.

Examiner Cue: When the Examinee simulates notifying the SM/CRS that CHB-P01 pulsation dampener bladder is NOT failed:

The Control Room has been informed.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6

  • IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.d THEN perform the following:

Close CHB-VZ06, CHB-P01 Pulsation Dampener CHB-X07 N2 Inlet Isol Valve. (100 #2 Charging Pump Room)

Standard: Simulated closing CHB-VZ06.

Examiner Cue: When the examinee simulates closing CHN-VZ06:

The handwheel for CHB-VZ06 is in the fully clockwise position.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 7

  • IF CHB-P01, Charging Pump B, was the standby pump at the time of the failure, Proc Step: 2.e THEN perform the following:

Close CHN-VZ03, CHN-PI-1020 Root Isolation Valve. (100 #2 Charging Pump Room)

Standard: Simulated closing CHN-VZ03.

Examiner Cue: When the examinee simulates closing CHN-VZ03:

The handwheel for CHN-VZ03 is in the fully clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 8

  • IF CHE-P01, Charging Pump E, was the standby pump at the time of the failure, Proc Step: 3.a THEN perform the following:

Open CHN-VZ04, CHN-PI-1030 Root Isolation Valve. (100 #3 Charging Pump Room)

Standard: Simulated opening CHN-VZ04.

Examiner Cue: When the examinee simulates opening CHN-VZ04:

The handwheel for CHN-VZ04 is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 9

  • IF CHE-P01, Charging Pump E, was the standby pump at the time of the failure, Proc Step: 3.b THEN perform the following:

Open CHE-VZ07, CHN-PI-1030 Root Isolation Valve. (100 #3 Charging Pump Room)

Standard: Simulated opening CHE-VZ07.

Examiner Cue: When the examinee simulates opening CHN-VZ07:

The handwheel for CHE-VZ07 is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 10

  • IF CHE-P01, Charging Pump E, was the standby pump at the time of the failure, Proc Step: 3.c THEN perform the following:

Check CHN-PI-1030, CHE-P01 Pulsation Dampener CHE-X07 N2 Supply Press Indic, indicates less than 100 psig.

Standard: Identified Pulsation Dampener supply pressure at CHN-PI-1030 is 0 psig.

Examiner Cue: When the examinee checks CHN-PI-1030:

Use a pen to simulate CHN-PI-1030 indicating 0 psig.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 11

  • IF CHE-P01, Charging Pump E, was the standby pump at the time of the failure, Proc Step: 3.d THEN perform the following:

Close CHE-VZ07, CHN-PI-1030 Root Isolation Valve. (100 #3 Charging Pump Room)

Standard: Simulated closing CHE-VZ07.

Examiner Cue: When the examinee simulates closing CHE-VZ07:

The handwheel for CHE-VZ07 is in the fully clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 12

  • IF CHE-P01, Charging Pump E, was the standby pump at the time of the failure, Proc Step: 3.e THEN perform the following:

Close CHN-VZ04, CHN-PI-1030 Root Isolation Valve. (100 #3 Charging Pump Room)

Standard: Simulated closing CHN-VZ04 Examiner Cue: When the examinee simulates closing CHN-VZ04:

The handwheel for CHN-VZ04 is in the fully clockwise position.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 13 IF CHA-P01, Charging Pump A, has the failed discharge pulsation dampener Proc Step: 4.a and bladder, THEN perform the following to isolate CHA-P01, Charging Pump A:

4.b (100 #1 Charging Pump Room)

Close CHA-V316, Charging Pump CHA-P01 Suction Isolation Valve.

Close CHA-V339, Charging Pump CHA-P01 Discharge Valve.

Standard: Marked steps N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 14 IF CHB-P01, Charging Pump B, has the failed discharge pulsation dampener Proc Step: 5.a and bladder, THEN perform the following to isolate CHB-P01, Charging Pump B: (100 5.b #2 Charging Pump Room)

Close CHB-V319, Charging Pump CHB-P01 Suction Isolation Valve.

Close CHB-V337, Charging Pump CHB-P01 Discharge Valve.

Standard: Marked steps N/A.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 JPM Step: 15

  • IF CHE-P01, Charging Pump E, has the failed discharge pulsation dampener Proc Step: 6.a bladder, THEN perform the following to isolate CHE-P01, Charging Pump E:

(100 #3 Charging Pump Room)

Close CHE-V322, Charging Pump CHE-P01 Suction Isolation Valve.

Standard: Simulated closing CHE-V322 Examiner Cue: When the examinee simulates closing CHE-V322:

The handwheel for CHE-V322 is in the fully clockwise position.

If the examinee checks the VPI:

Use a pen to indicate CLOSED on the VPI.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 16

  • IF CHE-P01, Charging Pump E, has the failed discharge pulsation dampener Proc Step: 6.b bladder, THEN perform the following to isolate CHE-P01, Charging Pump E:

(100 #3 Charging Pump Room)

Close CHE-V335, Charging Pump CHE-P01 Discharge Valve.

Standard: Simulated closing CHE-V335 Examiner Cue: When the examinee simulates closing CHE-V335:

The handwheel for CHE-V335 is in the fully clockwise position.

If the examinee checks the VPI:

Use a pen to indicate CLOSED on the VPI.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 Procedure Note: Per CRDR 4648070, the impact on the charging pump and connected system components while operating with a failed pulsation dampener has not been analyzed for any specific time period.

JPM Step: 17 Notify the SM/CRS that the charging pump with the failed discharge pulsation Proc Step: 7 dampener bladder is unavailable for use.

Standard: Simulated notifying the SM/CRS that CHE-P01, Charging Pump E in unavailable for use due to a failed pulsation dampener bladder.

Examiner Cue: When the Examinee simulates informing the SM/CRS that CHE-P01, Charging Pump E in unavailable for use due to a failed pulsation dampener bladder:

The Control Room has been informed. This JPM is complete Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 5/27/2016 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM P2 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 has experienced a Loss of Letdown.

The CRS has entered 40AO-9ZZ05, Loss of Charging or Letdown.

A Charging Pump is running with B and E Charging Pumps in standby.

Subsequently:

The A Charging Pump became air-bound.

The CRS transitioned to Appendix G, Responding to Gas Binding of Charging Pumps.

All Charging Pumps handswitches have been placed in Pull-To-Lock.

VCT level is 40%.

INITIATING CUE:

The CRS directs you to perform 40AO-9ZZ05, Loss of Charging or Letdown, Appendix I, Venting Charging Pumps and Header to the Recycle Drain Header, steps 1-7.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 JPM INFORMATION TASK: 1240021701 - Direct Containment Hydrogen Control TASK STANDARD: Placed the Train A Hydrogen Recombiner Purge Exhaust Unit in service K/A: 028 A4.01 RATING: RO: 4.0 SRO: 4.0 10CFR55: 45.8 POSITION(S): AO/RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40EP-9EO10, Standard Appendix 19, Attachment 19-J LOCATION: SIMULATOR PLANT X CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/20/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 PROCEDURES/MATERIALS:

40EP-9EO10, Standard Appendices, Appendix 19, Containment Hydrogen Control, Attachment 19-J, Placing Purge Exhaust in Service.

This JPM was written using Revision 96 of 40EP-9EO10. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

IN-PLANT JPMS ONLY:

Operation of in-plant equipment is to be SIMULATED ONLY. DO NOT operate any equipment.

Notify the Shift Manager when in-plant JPMs are being performed.

Inform the Control Room staff of any discovered deficiencies Comply with the REP. If it is not possible to enter an area it may be permissible to discuss the equipment and operation with evaluator. DO NOT enter Contaminated Areas or High Radiation Areas.

INITIAL CONDITIONS:

A Large-break LOCA has occurred in Unit 1.

The CRS has entered 40EP-9EO10, LOCA.

Due to hydrogen concentration concerns inside containment, the CRS has decided to place the Train A Hydrogen Recombiner Purge Exhaust Unit in service.

INITIATING CUE:

The CRS has directed you to perform 40EP-9EO10, Standard Appendix 19, Attachment 19-J, to place the Train A Hydrogen Recombiner Purge Exhaust Unit in service.

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 JPM START TIME:

JPM Step: 1

  • IF A train will be used, THEN open ALL of the following valves:

Proc Step: 1 HPA-V005, A TRN H2 PURGE INLET (100 ft. Aux Bldg A Recombiner Area)

Standard: Simulated opening HPA-V005.

Examiner Cue: When the examinee simulates opening HPA-V005:

HPA-V005 handwheel is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • IF A train will be used, THEN open ALL of the following valves:

Proc Step: 1 HPA-V001, AIR SUPPLY TO A RECOMBINER (100 ft. Aux Bldg A Recombiner Area)

Standard: Simulated opening HPA-V001.

Examiner Cue: When the examinee simulates opening HPA-V001:

HPA-V001 handwheel is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 JPM Step: 3

  • IF A train will be used, THEN open ALL of the following valves:

Proc Step: 1 IAN-V061, SERVICE AIR PURGE ISOLATION TO CONTAINMENT (100 ft. Aux Bldg Purge Exh Unit)

Standard: Simulated opening IAN-V061.

Examiner Cue: When the examinee simulates opening IAN-V061:

IAN-V061 handwheel is in the fully counter-clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 4

  • IF A train will be used, THEN close HPA-V013, HYDROGEN RECOMBINER Proc Step: 2 OUTLET ISOLATION (100 ft. Aux Bldg 'A' Recombiner Area).

Standard: Simulated closing HPA-V013.

Examiner Cue: When the examinee simulates closing HPA-V013:

HPA-V013 handwheel is in the fully clockwise position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5 IF B train will be used, THEN open ALL of the following valves:

Proc Step: 3 HPB-V006, B TRN H2 PURGE INLET (100 ft. Aux Bldg B Recombiner Area)

HPB-V003, AIR SUPPLY TO B RECOMBINER (100 ft. Aux Bldg B Recombiner Area)

IAN-V061, SERVICE AIR PURGE ISOLATION TO CONTAINMENT (100 ft. Aux Bldg Purge Exh Unit)

Standard: Marked step N/A.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 JPM Step: 6 IF B train will be used, THEN close HPB-V012, HYDROGEN RECOMBINER Proc Step: 4 OUTLET ISOLATION (100 ft. Aux Bldg 'B' Recombiner Area).

Standard: Marked step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 7

  • Place HPN-HS35, PURGE UNIT DUCT HTR in the ON position.

Proc Step: 5 (100 ft. Aux Bldg Purge Exh Unit)

Standard: Examinee simulated placing the HPN-HS35 handswitch to the ON position.

Examiner Cue: When the examinee simulates placing handswitch HPN-HS35 to ON:

HPN-HS35 handswitch is in the UP position Comments (required for UNSAT):

SAT UNSAT JPM Step: 8 Inform the responsible operator of BOTH of the following:

Proc Step: 6 Attachment 19-J is completed The Purge Exhaust Unit is in service Standard: Examinee simulated informing the control room that Attachment 19-J is complete and the Train A Hydrogen Recombiner Purge Exhaust Unit is in service.

Examiner Cue: When the Examinee simulates informing the control room that Attachment 19-J is complete and the Train A Hydrogen Recombiner Purge Exhaust Unit is in service:

This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 00 4/20/2016 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM P3 Rev 1 EXAMINEE INITIAL CONDITIONS:

A Large-break LOCA has occurred in Unit 1.

The CRS has entered 40EP-9EO10, LOCA.

Due to hydrogen concentration concerns inside containment, the CRS has decided to place the Train A Hydrogen Recombiner Purge Exhaust Unit in service.

INITIATING CUE:

The CRS has directed you to perform 40EP-9EO10, Standard Appendix 19, Attachment 19-J, to place the Train A Hydrogen Recombiner Purge Exhaust Unit in service.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM INFORMATION TASK: 1100030401 - Perform CEA Exercising Inserted CEA 66 a minimum of 7 steps (5.25 inches), and a maximum of 8 steps (6 TASK STANDARD:

inches), then withdrew CEA 66 to the UEL in MANUAL INDIVIDUAL.

K/A: 001 A4.03 RATING: RO: 4.0 SRO: 3.7 10CFR55: 45.6 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40ST-9SF01, CEA Operability Checks LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 5/16/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 SIMULATOR SETUP:

Reset to IC-601 or Reset to IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP: N/A COMMAND DESCRIPTION INSTRUCTIONS FOR SETUP:

Ensure control boards and pertinent procedures are free of marks or additional information.

Acknowledge alarms.

GO TO FREEZE.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 35 of 40ST-9SF01, Section 6.1 and Appendix A - CEA Exercising at Power. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 is operating at 100% power.

An ACTM card for CEA 66 has just been replaced.

INITIATING CUE:

The CRS directs you to perform 40ST-9SF01, CEA Operability Checks, Section 6.1, Exercising CEAs at Power, for CEA 66 only.

Section 6.1, Exercising CEAs at Power, is complete through step 6.1.4.

Start on step 6.1.5.

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM START TIME:

JPM Step: 1 Monitor ALL of the following parameters during CEA movement:

Proc Step: 6.1.5 Reactor Power (Plant Computer)

CEA individual and group positions (CEAPDS Video Display, CEDMCS Control Panel, CEA Position Meter, CEA Group Position Meter)

RCS temperature and Reactor power (CPC Remote Operators Module)

CEA positions and deviations (CEAC Remote Operators Module)

Reactor power, RCS temperature, Turbine first stage pressure, ASI (ERFDADS)

Standard: Monitored the appropriate parameters during CEA movement.

Comments (required for UNSAT):

SAT UNSAT Procedure Note: RSPTs are located 1.5 inches apart. Moving a CEA 0.75 inches (one step) may result in a 1.5 inch change in CEA position as seen by the CPCs and the CEACs.

Proc Caution: Some ASI perturbations will result due to performance of this procedure at power.

JPM Step: 2 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.1 CEA Exercising at Power:

Ensure Appendix A - CEA Exercising at Power is used for place keeping.

Standard: Place-kept in Appendix A.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM Step: 3 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.2 CEA Exercising at Power:

Select position indication for CEA to be exercised on at least one available CPC CEAC Operator Module digital display.

Standard: Selected CEAC CEA COMPARISON, then selected GROUP 1/2.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 4

  • Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.3 CEA Exercising at Power:

Place GROUP SELECT switch to group containing CEA to be exercised.

Standard: Placed GROUP SELECT switch to 2.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5

  • Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.4 CEA Exercising at Power:

Place INDIVIDUAL CEA SELECT switches to CEA to be exercised.

Standard: Placed the TENS switch to 6, and the UNITS switch to 6 (for CEA 66).

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6

  • Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.5 CEA Exercising at Power:

Place MODE SELECT switch to MI (MANUAL INDIVIDUAL) position.

Standard: Placed the MODE SELECT switch to MANUAL INDIVIDUAL.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM Step: 7 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.6 CEA Exercising at Power:

Ensure CEA to be exercised is at the UEL position.

Procedure Note: CEA position from CEACs may be used if SFN-JI-17 is not available for any or all CEAs; however both initial and final CEA positions must be determined from the same source.

Standard: Ensured CEA 66 in at the UEL Comments (required for UNSAT):

SAT UNSAT JPM Step: 8 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.7 CEA Exercising at Power:

IF the CEA pulse count indication is less than 150 inches withdrawn, THEN perform Appendix B - PMS Resetting of CEA Positions, to reset pulse counters to 150 inches withdrawn.

Standard: Verified the pulse counter for CEA 66 read 150 inches withdrawn and marked this step N/A.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM Step: 9

  • Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.8 CEA Exercising at Power:

Insert the CEA being exercised seven steps (greater than or equal to five inches).

Standard: Inserted CEA 66 seven or eight steps (5.25 to 6.5 inches) for a final position of 144.75 to 143.5 inches.

Examiner Note: Seven steps will insert the CEA to 144.75 inches withdrawn.

Eight steps will insert the CEA to 144.0 inches withdrawn.

Nine steps will insert the CEA to 143.25 inches withdrawn.

If the examinee inserts CEA 66 less than seven steps but then inserts CEA 66 additional steps to achieve a total insertion of 7 or 8 steps, this Critical Task is satisfied. If the examinee inserts CEA 66 a total of 9 steps or more using any combination of insertions, this will constitute an entry into LCO 3.1.5 Condition A, and therefore the Critical Step would be UNSAT.

Examiner Cue: The CEA TECH SPEC VIOLATION alarm is expected during this evolution since the setpoint for the alarm is a 3 deviation from the group. If the examinee attempts to perform the ARP actions:

Another operator will perform ARP actions Comments (required for UNSAT):

SAT UNSAT JPM Step: 10 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.9 CEA Exercising at Power:

IF a CWP alarm has annunciated on window 4A09B during the CEA insertion, THEN press and hold the CWP BYPASS (CWP/B) pushbutton until the alarm is clear to withdraw the CEA being exercised.

Standard: IF window 4A09B (CWP - CEA WITHDRAWL PROHIBIT) alarmed, the examinee pressed and held the CWP BYPASS (CWP/B) pushbutton until the alarm cleared.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 JPM Step: 11

  • Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.10 CEA Exercising at Power:

Withdraw the CEA being exercised to the UEL position.

Standard: Withdrew CEA 66 to the UEL.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 12 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.11 CEA Exercising at Power:

Ensure the CEA being exercised is restored to the As-Left Guide Tube Wear position from Step 6.1.3: (circle) UEL / UEL-1 Examiner Note: UEL already circled since step 6.1.3 is already completed per the initial conditions and initiating cue.

Standard: Ensured CEA 66 is at the UEL Comments (required for UNSAT):

SAT UNSAT JPM Step: 13 Perform the following to exercise all full strength CEAs listed in Appendix A -

Proc Step: 6.1.6.12 CEA Exercising at Power:

Record the results of the exercise test in Appendix A - CEA Exercising at Power.

Standard: Recorded the results in Appendix A.

Examiner Cue: After the Examinee recorded the results in Appendix A:

This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 5/16/16 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S1 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 is operating at 100% power.

An ACTM card for CEA 66 has just been replaced.

INITIATING CUE:

The CRS directs you to perform 40ST-9SF01, CEA Operability Checks, Section 6.1, Exercising CEAs at Power, for CEA 66 only.

Section 6.1, Exercising CEAs at Power, is complete through step 6.1.4.

Start on step 6.1.5.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 JPM INFORMATION TASK: 1240040201 - Implement LOCA instructions and contingencies Stopped the HPSI and CS pumps on loop with failed containment sump suction valve, TASK STANDARD: closed CHA-HV-531 and CHB-HV-530 within 5 minutes of starting the JPM, and closed SIB-UV-667.

K/A: 006 A3.08 RATING: RO: 4.2 SRO: 4.3 10CFR55: 45.7 POSITION(S): RO VALIDATION TIME: 7 minutes

REFERENCES:

40EP-9EO03, Loss of Coolant Accident LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: YES ALTERNATE PATH: YES PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/18/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 SIMULATOR SETUP:

Reset to IC-602 or IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION mfTH01A f:100 LOOP 1A LOCA - COLD LEG at 100% severity cmMVRH04SIBUV675_6 Mechanical seizure of Containment Sump Isolation Valve SIB-UV-675 cmMVSI01SIBUV667_5 Automatic close signal failure: HPSI Pump to RWT Iso Valve SIB-UV-667 INSTRUCTIONS FOR SETUP:

Ensure the control boards and pertinent procedures are free of marks or additional information .

Insert a Large Break LOCA (mfTH01A f:100).

Insert a seizure of SIB-UV-675 in the closed position (cmMVRH04SIBUV675_6).

Insert a failure of SIB-UV-667 to auto close on the RAS (cmMVSI01SIBUV667_5.

Allow the reactor to automatically trip or manually trip the reactor.

Trip all 4 RCPs and ensure ADVs are throttled open.

Allow Refueling Water Tank level to lower to Recirculation Actuation Signal (RAS) setpoint (9.4%). NOTE: You will receive a RAS in approximately 20-30 minutes.

When RAS initiates, GO TO FREEZE.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 38 of 40EP-9EO03, Loss of Coolant Accident. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

A large break LOCA has occurred in Unit 1.

The CRS has entered 40EP-9EO03, Loss of Coolant Accident.

A Recirculation Actuation Signal (RAS) has just actuated and Step 57 of 40EP-9EO03, Loss of Coolant Accident has just been completed.

INITIATING CUE:

The CRS has directed you to perform 40EP-9EO03, Loss of Coolant Accident, Step 58, a through d.

THIS IS A TIME CRITICAL JPM

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 JPM START TIME:

Examiner Note When the cue is read to the examinee, they have 5 minutes to complete JPM step 5 (close CHA-HV-531 and CHB-HV-530).

Start Time:____________

JPM Step: 1 IF a RAS has actuated, THEN perform the following:

Proc Step: 58.a Ensure that both LPSI Pumps are stopped.

Standard: Verified both LPSI pumps have stopped .

Comments (required for UNSAT):

SAT UNSAT Examiner Note: The following step represents the alternate path portion of the JPM.

JPM Step: 2 IF a RAS has actuated, THEN perform the following:

Proc Step: 58.b Ensure that the ESF pump suction has shifted to the containment.

Standard: Determined that the B ESF pump suction valves from containment did open with the exception of SIB-UV-675, and transitioned to contingency step 58.b.1.

Examiner Note: The examinee should attempt to open SIB-UV-675 on B02, but the valve will not open. Failing to attempt to open SIB-UV-675 does NOT constitute a Critical Step failure.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 JPM Step: 3* IF any ESF pump suctions can NOT be shifted to the containment sump, THEN Proc Step: 58.b.1 perform the following:

IF ANY HPSI Pump is running with its associated Containment suction closed, THEN stop the affected HPSI Pump.

Standard: Stopped HPSI pump B by taking the handswitch SIB-HS-2 on B02 to START to pick up the override, then to STOP to stop the pump.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 4* IF any ESF pump suctions can NOT be shifted to the containment sump, THEN Proc Step: 58.b.2 perform the following:

IF ANY CS Pump is running with its associated Containment suction closed, THEN stop the affected CS Pump.

Standard: Stopped CS pump B by taking the handswitch SIB-HS-6 on B02 to START to pick up the override, then to STOP to stop the pump.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5* Close BOTH of the following valves:

Proc Step: 58.c CHA-HV-531, RWT to Train A Safety Injection Valve CHB-HV-530, RWT to Train B Safety Injection Valve Standard: Closed both CHA-HV-531, and CHB-HV-530 within 5 minutes of the start of the JPM.

Examiner Note Both CHB-HV-530 and CHA-HV-531 are closed at time : _____________

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 JPM Step: 6

  • Ensure ALL of the following valves are closed:

Proc Step: 58.d SIA-UV-666, HPSI A Pump Recirc Valve SIA-UV-664, Containment Spray Pump A Recirc Valve SIA-UV-669, LPSI Pump A Recirc Valve SIB-UV-667, HPSI B Pump Recirc Valve SIB-UV-665, CS Pump B Recirc Valve SIB-UV-668, LPSI Pump B Recirc Valve Standard: Closed SIB-UV-667 and ensured all of the other above valves are closed.

Examiner Cue When the examinee has ensured all the above valves are closed:

This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 01 4/18/2016 3 Changes to procedure numbering and order of actions in step 58; changes to JPM format.

REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S2 Rev 1 EXAMINEE INITIAL CONDITIONS:

A large break LOCA has occurred in Unit 1.

The CRS has entered 40EP-9EO03, Loss of Coolant Accident.

A Recirculation Actuation Signal (RAS) has just actuated and Step 57 of 40EP-9EO03, Loss of Coolant Accident has just been completed.

INITIATING CUE:

The CRS has directed you to perform 40EP-9EO03, Loss of Coolant Accident, Step 58, a through d.

THIS IS A TIME CRITICAL JPM EXAMINEE

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 JPM INFORMATION TASK: 120020601 - Pressurize a Safety Injection Tank Safety Injection Tank 1A pressure raised high enough to clear the non-class alarm, TASK STANDARD: 2B12A - SIT PRESS HI-LO and class alarm, RKA-UA-2C - SIT 1A-1B PRESS LOW, without bringing in a SIT pressure high pressure alarm.

K/A: 006 A4.02 RATING: RO: 4.0 SRO: 3.8 10CFR55: 45.6 POSITION(S): RO/SRO VALIDATION TIME: 15 minutes

REFERENCES:

40OP-9SI03, Safety Injection Tank Operations LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/18/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 SIMULATOR SETUP:

Reset to any IC and perform the INSTRUCTIONS FOR SETUP below (This JPM can be run on any IC in MODES 1, 2, and 3, and MODE 4 with Pressurizer Pressure greater than 1837 psig.

SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION mfSI03C f:1 SIT-1A Gas Leak INSTRUCTIONS FOR SETUP:

Ensure the control boards and pertinent procedures are free of marks or writing.

GO TO RUN.

Insert SIT-1A Gas leak (mfSI03C f:1) until SIT-1A pressure lowers to 605 psig.

Acknowledge alarms.

GO TO FREEZE.

DELETE the SIT-1A Gas Leak malfunction.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 37 of 40OP-9SI03, Safety Injection Tank Operations. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

A nitrogen leak from Safety Injection Tank (SIT) 1A has caused pressure to lower to 605 psig.

The source of the leak has been located and repaired INITIATING CUE:

The CRS directs you to raise pressure in SIT 1A to clear the SIT 1A low pressure alarms without bringing in a SIT 1A high pressure alarm, per 40OP-9SI03, Section 6.1, Pressurizing the Safety Injection Tanks to Establish or Maintain Normal Pressure.

Steps 6.1.1 through 6.1.3.3 are complete. Start on step 6.1.3.4.

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 JPM START TIME:

JPM Step: 1

  • Open GAA-UV-1 using GAA-HS-1, HP N2 TO SI TANKS.

Proc Step: 6.1.3.4 Standard: Opened GAA-UV-1 using GAA-HS-1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2

  • Open the nitrogen supply valve for the SIT to be pressurized:

Proc Step: 6.1.3.5 SIB-HV-612 using SIB-HS-612, NITROGEN TO SIT 2A VLV SIB-HV-622 using SIB-HS-622, NITROGEN TO SIT 2B VLV SIB-HV-632 using SIB-HS-632, NITROGEN TO SIT 1A VLV SIB-HV-642 using SIB-HS-642, NITROGEN TO SIT 1B VLV Standard: Opened SIB-HV-632 using SIB-HS-632.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 3

  • Open the nitrogen supply valve for the SIT to be pressurized to Proc Step: 6.1.3.6 commence pressurization:

SIA-HV-619 using SIA-HS-619, NITROGEN TO SIT 2A VLV SIA-HV-629 using SIA-HS-629, NITROGEN TO SIT 2B VLV SIA-HV-639 using SIA-HS-639, NITROGEN TO SIT 1A VLV SIA-HV-649 using SIA-HS-649, NITROGEN TO SIT 1B VLV Standard: Opened SIA-HV-639 using SIA-HS-639.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 JPM Step: 4

  • WHEN SIT pressure is at the desired pressure, THEN close the nitrogen supply Proc Step: valve opened in Step 6.1.3.6 to stop pressurization:

SIA-HV-619 using SIA-HS-619, NITROGEN TO SIT 2A VLV SIA-HV-629 using SIA-HS-629, NITROGEN TO SIT 2B VLV SIA-HV-639 using SIA-HS-639, NITROGEN TO SIT 1A VLV SIA-HV-649 using SIA-HS-649, NITROGEN TO SIT 1B VLV Standard: 6.1.3.7 Closed SIA-HV-639 using SIA-HS-639 when SIT 1A low pressure alarms are clear and prior to bringing in a SIT 1A high pressure alarm.

Examiner Note The non-class low pressure alarm clears at 605 psig.

The class low pressure alarm clears at 610 psig.

The non-class high pressure alarm comes in at 620 psig.

When both SIT 1A low pressure alarms are clear, the critical step is met.

However if the examinee continues to raise pressure until the SIT 1A high pressure alarm comes in (620 psig), the critical step is failed.

If SIA-HV-639 is closed prior to reaching 615 psig, the examinee may reopen until the desired pressure is reached.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5 Close the nitrogen supply valve opened in Step 6.1.3.5:

Proc Step: 6.1.3.8 SIB-HV-612 using SIB-HS-612, NITROGEN TO SIT 2A VLV SIB-HV-622 using SIB-HS-622, NITROGEN TO SIT 2B VLV SIB-HV-632 using SIB-HS-632, NITROGEN TO SIT 1A VLV SIB-HV-642 using SIB-HS-642, NITROGEN TO SIT 1B VLV Standard: Closed SIB-HV-632 .

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 JPM Step: 6 Repeat Steps 6.1.3.1 through 6.1.3.8 until desired SIT pressure is reached.

Proc Step: 6.1.3.9 Standard: Either repeated steps 6.1.3.1 through 6.1.3.8 if needed, or marked step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 7 WHEN pressurization of SITs is complete, THEN close GAA-UV-1 using GAA-Proc Step: 6.1.3.10 HS-1, HP N2 TO SI TANKS.

Standard: Closed GAA-UV-1.

Examiner Cue When the examinee closes GAA-UV-1:

This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S3 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 00 4/18/2016 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

EXAMINEE INITIAL CONDITIONS:

A nitrogen leak from Safety Injection Tank (SIT) 1A has caused pressure to lower to 605 psig.

The source of the leak has been located and repaired INITIATING CUE:

The CRS directs you to raise pressure in SIT 1A to clear the SIT 1A low pressure alarms without bringing in a SIT 1A high pressure alarm, per 40OP-9SI03, Section 6.1, Pressurizing the Safety Injection Tanks to Establish or Maintain Normal Pressure.

Steps 6.1.1 through 6.1.3.3 are complete. Start on step 6.1.3.4.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 JPM INFORMATION TASK: 1250030401 - Respond to a Loss of Nuclear Cooling Water Reactor tripped, all RCPs secured within 10 minutes, and seal bleedoff isolated by TASK STANDARD:

closing CHB-UV-505, CHA-UV-506, and CHA-UV-507.

K/A: 003 A1.08 RATING: RO: 2.5 SRO: 2.6 10CFR55: 45.3 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40AO-9ZZ03, Loss of Cooling Water, Section 4.0, Nuclear Cooling Water LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: YES ALTERNATE PATH: YES PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 5/02/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 SIMULATOR SETUP:

Reset to IC-604 or Reset to IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION cmMVCC04NCBUV403_3 Spurious Nuclear Cooling containment isolation valve closure (NCB-UV-403) cmMVCC04NCBUV403_6 d:12 Mechanical seizure of Nuclear Cooling containment isolation valve (NCB-UV-403) cmMVCV14RCEHV431_6 Mechanical Seizure of RCP 1B Controller Bleedoff Valve INSTRUCTIONS FOR SETUP:

Ensure control boards and pertinent procedures are free of marks or additional information.

Go to RUN.

Insert the following malfunctions from the table above:

o cmMVCC04NCBUV403_3 o cmMVCC04NCBUV403_6 d:12 o cmMVCV14RCEHV431_6 WAIT 15 seconds then acknowledge alarms.

GO TO FREEZE.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 10 of 40AO-9ZZ03, Loss of Cooling Water, Section 4.0, Nuclear Cooling Water. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 is 100% power and you have just received low flow alarms on NCW to the RCPs.

The CRS has entered 40AO-9ZZ03, Loss of Cooling Water INITIATING CUE:

The CRS directs you to perform 40AO-9ZZ03, Loss of Cooling Water, Section 4.0, Nuclear Cooling Water.

This is a TIME CRITICAL JPM.

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 JPM START TIME:

Examiner Note: After the cue is read to the examinee, if Nuclear Cooling Water is not restored to the RCPs within 10 minutes, the Reactor must be tripped, all RCPs must be stopped within 10 minutes, and seal bleedoff must be isolated.

JPM Step: 1 Enter AOP Entry Time and Date.

Proc Step: 1 Standard: Entered entry time and date.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2 IF seal injection is NOT in service, AND cooling water is NOT restored to ANY Proc Step: 2 operating RCP within three minutes of the initial loss, THEN perform the following:

Ensure the reactor is tripped.

Stop all of the RCPs.

Isolate controlled bleedoff.

Standard: Marked step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 3 IF seal injection is in service, AND cooling water is NOT restored to ANY Proc Step: 3 operating RCP within 10 minutes of the initial loss, THEN perform the following:

Ensure the reactor is tripped.

Stop all of the RCPs.

Isolate controlled bleedoff.

Standard: Acknowledged step and continued with the procedure.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 JPM Step: 4 IF no Nuclear Cooling Water pumps are running, THEN perform the following:

Proc Step: 4.a IF at least one Nuclear Cooling Water pump is available, THEN start the Nuclear Cooling Water Pump.

Standard: Determined that a NCW pump is operating and marked this step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5 IF no Nuclear Cooling Water pumps are running, THEN perform the following:

Proc Step: 4.b IF electrical power must be restored to start a Nuclear Cooling Water Pump, THEN perform the following:

o Place both NC Pump handswitches in PULL TO LOCK.

o PERFORM 40AO-9ZZ12, Degraded Electrical Power.

Standard: Marked this step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6 IF at least one Nuclear Cooling Water pump is running, AND NCWS PMPS Proc Step: 5 DSCH HDR PRESS HI-LO (7A07B) is in alarm due to low pressure, THEN perform the following:

Start the standby NC Pump.

Standard: Determined that the operating NCW Pump is operating normally with NO low discharge pressure alarm and marked this step N/A.

Examiner Note: Window 7A07B may be in alarm, but the alarm would be due to high discharge pressure due to part of the system being isolated.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 JPM Step: 7 IF at least one Nuclear Cooling Water pump is running, AND NCWS PMPS Proc Step: 5 DSCH HDR PRESS HI-LO (7A07B) is in alarm due to low pressure, THEN perform the following:

Check that no NC system leaks exist by performing the following:

o Direct an operator(s) to walkdown NC system piping.

o Evaluate indications and alarms on the control boards.

Standard: Determined that no low discharge pressure alarm existed and marked this step N/A.

Examiner Note: Window 7A07B may be in alarm, but the alarm would be due to high discharge pressure due to part of the system being isolated.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 8 IF ANY of the NC Containment Isolation Valves have failed closed, AND there is Proc Step: 6.a NOT a valid CSAS signal present, THEN perform the following:

Open ANY closed isolation valves.

Standard: Examinee recognized that valve NCB-UV-403 has closed and attempted to open NCB-UV-403.

Examinee may contact an Area Operator to enter containment and open NCB-UV-403 locally.

Examiner Cue: If examinee requests an AO to manually open NCB-UV-403, respond:

The CRS has determined a containment entry can NOT be performed.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 Examiner Note The following step represents the first alternate path portion of the JPM.

JPM Step: 9

  • IF ANY of the NC Containment Isolation Valves will NOT open, THEN perform Proc Step: 6.a.1.1 the following:

Close all NC CTMT Isolation Valves Standard: Closed remaining NCW CTMT isolation valves by rotating handswitches NCA-HS-402 and NCB-HS-401 to the CLOSE position.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 10

  • IF ANY of the NC Containment Isolation Valves will NOT open, THEN perform Proc Step: 6.a.1.2 the following:

Ensure that the Reactor is tripped.

Standard: Manually tripped the reactor by depressing reactor trip pushbuttons on Board B05.

Examiner Cue: If examinee begins to perform SPTAs:

Another operator will perform the SPTAs, continue with AOP actions Comments (required for UNSAT):

SAT UNSAT JPM Step: 11

  • IF ANY of the NC Containment Isolation Valves will NOT open, THEN perform Proc Step: 6.a.1.3 the following:

Stop all of the RCPs.

Standard: Secured all four RCPs within 10 minutes of the start of the JPM Time all RCPs secured: __________

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 Examiner Note The following step represents the second alternate path portion of the JPM.

JPM Step: 12

  • IF ANY of the NC Containment Isolation Valves will NOT open, THEN perform Proc Step: 6.a.1.4 the following:

Isolate seal bleedoff.

Standard: Due to RCE-UV-431 failing to close, the examinee isolated seal bleedoff by closing CHB-UV-505, CHA-UV-506, and CHA-UV-507.

Examiner Cue: After the RCPs are secured and seal bleedoff is secured:

This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 5/2/16 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S4 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 is 100% power and you have just received low flow alarms on NCW to the RCPs.

The CRS has entered 40AO-9ZZ03, Loss of Cooling Water INITIATING CUE:

The CRS directs you to perform 40AO-9ZZ03, Loss of Cooling Water, Section 4.0, Nuclear Cooling Water.

This is a TIME CRITICAL JPM.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 JPM INFORMATION TASK: 1250030501 - Respond to a loss of turbine cooling water Blowdown stopped, Auxiliary Feed Water feeding both SGs using AFA-P01, and the TASK STANDARD: A and B Main Feed Pumps, A, B, and C Condensate Pumps, and A and B Heater Drain Pumps are all stopped.

K/A: 062 AA1.02 RATING: RO: 3.2 SRO: 3.3 10CFR55: 45.7 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40AO-9ZZ03, Loss of Cooling Water, Appendix B, Minimize Cooling Load on TC LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: YES PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/11/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 SIMULATOR SETUP:

Reset to IC-605 or Reset to IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION Out of Service File - AFB Tagout AFB diMC_ZDCTAHS1 f: AS IS Override HV-1 in the closed position doMC_ZDCTAHS1_R1 f: AS IS Override HV-1 in the closed position cmCPTP04TCNP01A_6 86 LO of TC Pump A cmCPTP04TCNP01B_6 86 LO of TC Pump B INSTRUCTIONS FOR SETUP:

Ensure control boards and pertinent procedures are free of marks or additional information.

GO TO RUN.

RUN Scenario Out of Service Files - AFB.

Hang tags on the associated components on AFB-P01.

Insert the following malfunctions from the table above:

o diMC_ZDCTAHS1 f: AS IS o doMC_ZDCTAHS1_R1 f: AS IS o cmCPTP04TCNP01A_6 o cmCPTP04TCNP01B_6 Place both TC Pumps in Pull to Lock.

Manually trip the reactor.

Acknowledge alarms.

GO TO FREEZE.

After the cue has been read, GO TO RUN.

REQUIRED CONDITIONS:

AFB-P01 tagged out with tags hung on control board.

Both TC pumps tripped.

Reactor tripped.

Aux feed NOT aligned to the SGs.

PROCEDURES/MATERIALS:

This JPM was written using Revision 10 of 40AO-9ZZ03, Loss of Cooling Water, Appendix B, Minimize Cooling Load on TC. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

The reactor was manually tripped from 100% power due to a complete loss of Turbine Cooling Water.

AFB-P01 is tagged out for emergent corrective maintenance.

INITIATING CUE:

The CRS has directed you to perform 40AO-9ZZ03, Loss of Cooling Water, Appendix B, Minimize Cooling Loads on TC.

The CRS has directed using AFN-P01 for feeding the SGs.

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 JPM START TIME:

JPM Step: 1 Enter Appendix Entry Time and Date.

Proc Step: 1 Standard: Entered Appendix entry time and date.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2* Ensure that S/G Blowdown is stopped.

Proc Step: 2 Standard: Ensured blowdown is stopped by ANY of the following sets of manipulations:

SG1 Path Selector Valves handswitch SCN-HS-1 to OFF

  • SG2 Path Selector Valves handswitch SCN-HS-2 to OFF
  • OR SG1 Downcomer Blowdown Valve HV-47 to CLOSE
  • SG1 Cold Leg Isolation Valve HV-41 to CLOSE SG1 Hot Leg Isolation Valve HV-43 to CLOSE SG2 Downcomer Blowdown Valve HV-48 to CLOSE
  • SG2 Cold Leg Isolation Valve HV-44 to CLOSE SG2 Hot Leg Isolation Valve HV-42 to CLOSE OR SG1 Common Upstream Isolation Valve UV-500P to CLOSE
  • OR SG1 Common Downstream Isolation Valve UV-500Q to CLOSE
  • AND SG2 Common Upstream Isolation Valve UV-500R to CLOSE
  • OR SG2 Common Downstream Isolation Valve UV-500S to CLOSE
  • Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 JPM Step: 3 Ensure that the Steam Generators are being fed by Auxiliary Feedwater.

Proc Step: 3 Standard: Attempted to open Pump Suction From CST Valves HV-1 and HV-4, identified that HV-1 will not open, and determined that AFA-P01 should be used to feed the SGs.

Examiner Cue: If asked as the CRS how the examinee should proceed:

What do you recommend?, then concur with whatever the examinee recommends.

If called as the Area Operator to manually open CST valve HV-1, report:

I am unable to manually open HV-1.

Comments (required for UNSAT):

SAT UNSAT Examiner Note: The following step represents the alternate path portion of the JPM.

JPM Step: 4

Proc Step: 3 Standard: Aligned AFA-P01 to feed SGs as follows:

Open SG1 Steam Supply to Pump Bypass Valve UV-134 Open SG2 Steam Supply to Pump Bypass Valve UV-138 Open AFW to SG1 Downstream Valve UV-36 Open AFW to SG2 Downstream Valve UV-37 Throttle open AFW to SG1 Upstream Valve HV-32 Throttle open AFW to SG2 Upstream Valve HV-33 Examiner Note: The expectation for running AFA-P01 is to use both steam supply valves UV-134 and UV-138, however if only one is used, the critical step is still met.

Examinee may close the downcomer valves when establishing aux feed flow.

Operation of the downcomer valves is unrelated to the critical step, Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 JPM Step: 5

Standard: Ensured both Main Feedwater Pumps are tripped.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6 Ensure both Main Feedwater Pump turning gear handswitches are in PULL TO Proc Step: 5 LOCK.

Standard: Placed both Main Feedwater Pump turning gear handswitches in PULL TO LOCK.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 7

  • WHEN both Main Feedwater Pumps are tripped, THEN ensure that all Condensate Proc Step: 6 Pumps are stopped.

Standard: Stopped all Condensate Pumps.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 JPM Step: 8

  • Ensure that both Heater Drain Pumps are stopped.

Proc Step: 7 Standard: Stopped both Heater Drain Pumps.

Examiner Cue: Once the examinee stops both Heater Drain Pumps, This JPM is complete Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S5 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 00 7/9/15 6 New JPM 01 4/11/16 6 Revised for 2016 LOIT NRC Exam REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

EXAMINEE INITIAL CONDITIONS:

The reactor was manually tripped from 100% power due to a complete loss of Turbine Cooling Water.

AFB-P01 is tagged out for emergent corrective maintenance.

INITIATING CUE:

The CRS has directed you to perform 40AO-9ZZ03, Loss of Cooling Water, Appendix B, Minimize Cooling Loads on TC.

The CRS has directed using AFN-P01 for feeding the SGs.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 JPM INFORMATION TASK: 1240021501 - Restoration of Containment Cooling following a SIAS Started Train A CEDM ACUs (fans A and C) and Train A Containment Normal TASK STANDARD:

ACUs (fans A and C)

K/A: 022 A4.01 RATING: RO: 3.6 SRO: 3.6 10CFR55: 45.5 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40EP-9EO10, Standard Appendices, Appendix 17 LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/19/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 SIMULATOR SETUP:

Reset to IC-606 or Reset to IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION mfTH06A f:50 Steam Generator Tube Rupture in S/G #1 Scenario File mccon Resets SIAS load shed panels INSTRUCTIONS FOR SETUP:

Ensure the control boards and pertinent procedures are free of marks or writing.

GO TO RUN.

Insert SGTR in #1 SG (mfTH06A).

Manually trip the reactor and stabilize the plant.

Allow a SIAS/CIAS to automatically actuate.

Run scenario file mccon to reset SIAS Load-shed panels.

Acknowledge alarms.

GO TO FREEZE.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 96 of 40EO-9EP10, Standard Appendices, Appendix 17.

This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 has tripped due to a Steam Generator Tube Rupture.

SIAS and CIAS were actuated.

The CRS is directing actions in 40EP-9EO04, Steam Generator Tube Rupture.

Train A CEDM ACUs and Train A Containment Normal ACUs were running before the SIAS/CIAS.

SIAS Load-shed panels have been re-energized.

INITIATING CUE:

The CRS directs you to restore Train A Containment Cooling per 40EP-9EO10, Standard Appendix 17.

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 JPM START TIME:

JPM Step: 1 Check that ALL of the following are operating:

Proc Step: 1 PW pump NC pump At least one Normal Chiller Standard: Checked power available/running indications for PW, NC, and at least one normal chiller.

Comments (required for UNSAT):

SAT UNSAT Procedure Note: Step 2 actions are sequenced to provide an added measure for maintaining the pressure of the in-containment piping above the saturation pressure and further minimize the development of water hammer conditions upon system restoration.

JPM Step: 2 WHEN a NC pump is running, THEN perform the following:

Proc Step: 2 a. Ensure NCB-UV-401, NC Containment Upstream Supply Isolation, is open.

b. Ensure NCB-UV-403, NC Containment Upstream Return Isolation, is open.
c. Ensure NCA-UV-402, NC Containment Downstream Return Isolation, is open.

Standard: Verified the valves open in the order indicated:

a. NCA-UV-401
b. NCB-UV-403
c. NCB-UV-402 Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 Procedure Note: Step 3 actions are sequenced to provide an added measure for maintaining the pressure of the in-containment piping above the saturation pressure and further minimize the development of water hammer conditions upon system restoration.

JPM Step: 3

  • WHEN a WC pump is running, THEN perform the following:

Proc Step: 3 a. Ensure WCB-UV-63, WC Supply Header Outside Containment Isolation, is open.

b. Ensure WCB-UV-61, WC Return Header Inside Containment Isolation, is open.
c. Ensure WCA-UV-62, WC Return Header Outside Containment Isolation, is open.

Standard: Overrode and opened the valves in the order indicated:

a. WCB-UV-63
b. WCB-UV-61
c. WCA-UV-62 Comments (required for UNSAT):

SAT UNSAT JPM Step: 4 Ensure IAA-UV-2, Instrument Air Containment Isolation, is open.

Proc Step: 4 Standard: Verified IAA-UV-2 is open.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5 If PBA-S03 or PBB-S04 is being supplied by offsite power, then perform all of the Proc Step: 5.a following:

Ensure at least one Normal Chiller is running.

Standard: Verified at least one Normal Chiller is running.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 JPM Step: 6

  • IF SIAS has initiated THEN place the handswitch to for ALL of the following to Proc Step: 5.b the Auto After Stop (green flag) position:

Train A CEDM ACUs

  • Train B CEDM ACUs Train A Containment Normal ACUs
  • Train B Containment Normal ACUs Standard: Placed the handswitches for the CEDM ACUs and the Containment Normal ACUs to STOP and then AUTO.

Examiner Note: The critical portion of this step is that at least the Train A handswitches are taken to STOP then AUTO.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 7

  • Ensure at least one train of CEDM ACUs is running.

Proc Step: 5.c Standard: Started Train A CEDM ACUs per Initiating CUE Comments (required for UNSAT):

SAT UNSAT JPM Step: 8

  • Ensure at least one train of Containment Normal ACUs is running.

Proc Step: 5.d Standard: Started Train A Containment Normal ACUs per Initiating CUE Examiner Note: After the Examinee started Train A Containment Normal ACUs:

This JPM is complete Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 01 4/19/16 6 JPM Format Change REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S6 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 has tripped due to a Steam Generator Tube Rupture.

SIAS and CIAS were actuated.

The CRS is directing actions in 40EP-9EO04, Steam Generator Tube Rupture.

Train A CEDM ACUs and Train A Containment Normal ACUs were running before the SIAS/CIAS.

SIAS Load-shed panels have been re-energized.

INITIATING CUE:

The CRS directs you to restore Train A Containment Cooling per 40EP-9EO10, Standard Appendix 17.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 JPM INFORMATION TASK: 1240010101 - Implement the Standard Post Trip Actions PBB-S04 energized from the B EDG within 14 minutes, with speed raised to between TASK STANDARD: 59.9 and 60.5 Hz, and ensured the B Spray Pond Pump running within 2 minutes and 36 seconds (2.6 minutes) of the B EDG loading onto PBB-S04.

K/A: 062 A4.01 RATING: RO: 3.3 SRO: 3.1 10CFR55: 45.5 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes 40EP-9EO01, Standard Post Trip Actions, 40EP-9EO10, Standard Appendices,

REFERENCES:

Appendix 115, SPTA Supplement Actions LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: YES PRA/SRA RELATED: YES APPROVALS DEVELOPED/REVISED BY: John Rodgers DATE: 10/28/2015 VALIDATED BY: Joseph Stevens DATE: 06/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 SIMULATOR SETUP:

Reset to IC-605 or Reset to IC-20 and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP:

COMMAND DESCRIPTION cmBKED06PBBS04K_1 PBB-S04 Normal Supply Breaker fails to auto open mfEG23B f:-1 EDG B Speed Setpoint low cmCPCC09SPBP01_5 B Spray Pond Pump fails to auto start mfED10B NBN-X04 transformer fault INSTRUCTIONS FOR SETUP:

Ensure control boards and pertinent procedures are free of marks or additional information.

ENSURE the SPTA and Appendix 115 hardcards are clean and available for use at B01.

GO TO RUN.

Insert the following malfunctions from the table above:

o cmBKED06PBBS04K_1 o mfEG23B f:-1 o cmCPCC09SPBP01_5 o mfED10B Manually trip the reactor.

Acknowledge alarms.

GO TO FREEZE.

After the initiating cue is read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 21 of 40EP-9EO01, Standard Post Trip Actions, and Revision 96 of 40EP-9EO10, Standard Appendices, Appendix 115, SPTA Supplement Actions.

This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 has just tripped from 100% power.

The reactivity report and verification of turbine trip and generator output breakers being open have been completed.

INITIATING CUE:

The CRS has directed you to continue SPTAs, per 40EP-9EO01, Standard Post Trip Actions.

Start on step 3.b.

THIS IS A TIME CRITICAL JPM.

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 JPM START TIME:

Examiner Note: The examinee will use the SPTA hard card to continue SPTAs.

Examinee has 14 minutes (15 - 1 minute) to energize PBB-S04 from the B EDG.

JPM Step: 1 Check that station loads have transferred to offsite electrical power such that BOTH Proc Step: 3.b of the following conditions are met:

All vital and non-vital AC buses are powered All vital and non-vital DC buses are powered Standard: Identified PBB-S04 is de-energized and addressed the contingency actions.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2 If PBA-S03 or PBB-S04 is NOT powered from offsite, THEN perform the Proc Step: 3.b.1.1 following:

Ensure the associated DG has started Standard: Checked that the B EDG is running.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 Examiner Note: The following steps represent the alternate path portion of the JPM.

JPM Step: 3 If PBA-S03 or PBB-S04 is NOT powered from offsite, THEN perform the Proc Step: 3.b.1.2 following:

Ensure that the associated DG output breaker is closed. REFER TO Supplemental SPTA Actions (DG Running With Output Breaker Open) -

Hard Card Standard: Referred to the DG Running With Output Breaker Open hard card for actions to re-energize PBB-S04.

Examiner Note: At this point, the examinee should transition to the Appendix 115 hard card.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 4 If PBA-S03 or PBB-S04 is NOT powered from offsite power, AND the associated Proc Step: 1.a DG is running with its output breaker open, THEN perform the following:

Check BOTH of the following:

o DG frequency between 59.9 - 60.5 Hz.

o DG voltage between 4080 - 4300 V Standard: Verified DG voltage is between 4080 - 4300 V, identified DG frequency is below the minimum of 59.9 Hz and proceeded to the contingency actions.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5

  • Perform the following:

Proc Step: 1.a.1.1 Place the associated DG handswitch to START to override the DG.

Standard: Placed the associated DG handswitch to START to override the DG.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 JPM Step: 6

  • Perform the following:

Proc Step: 1.a.1.2 IF speed criteria is NOT met, THEN adjust the associated DG frequency to 59.9 - 60.5 Hz.

Standard: Raised DG frequency to between 59.9 and 60.5 Hz.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 7

  • Ensure BOTH of the following supply breakers on the affected bus are open (B01):

Proc Step: 1.b Normal supply breaker Alternate supply breaker Standard: Identified the normal supply breaker (PBB-S04K) is closed and opened the normal supply breaker.

Time EDG loaded onto PBB-S04: ___________ (must be done within 14 min)

Examiner Note: When the normal supply breaker is opened, the DG output breaker will close and re-energize PBB-S04. At this point, the examinee should continue on in 40EO-9EO01, Standard Post Trip Actions.

Comments (required for UNSAT):

SAT UNSAT Examiner Note: The examinee should continue in SPTAs starting with step 3.b contingency action b.1.3.

JPM Step: 6 If the associated DG is NOT at rated speed and voltage Proc Step: 3.b.1.3 Standard: Marked step N/A, OR if speed was NOT raised earlier in the JPM, then the applicant must raise speed to 59.9 and 60.5 Hz to satisfy the critical step.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 Examiner Note: The Spray Pond Pump should auto start 25 seconds after the EDG loads onto the bus.

JPM Step: 7

  • If a DG is running THEN perform the following:

Proc Step: 3.b.2.1 IF the associated Spray Pond Pump is NOT running, THEN start the associated Spray Pond Pump.

Standard: Identified the associated Spray Pond Pump is not running and started the B Spray Pond Pump.

Time Spray Pond Pump started: ___________ (must be within 2.6 min of PBB-S04 being powered by the B EDG)

Examiner Cue: When the examinee has started the B Spray Pond Pump:

This JPM is complete Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 0 10/28/15 6 JPM created 1 4/11/16 6 Updated to new procedure revision for use on 2016 NRC Initial Exam REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S7 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 has just tripped from 100% power.

The reactivity report and verification of turbine trip and generator output breakers being open have been completed.

INITIATING CUE:

The CRS has directed you to continue SPTAs, per 40EP-9EO01, Standard Post Trip Actions.

Start on step 3.b.

THIS IS A TIME CRITICAL JPM.

EXAMINEE

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM INFORMATION TASK: 1270030401 - Operate the plant during a reactor startup Startup Channels have been de-energized, Control Channels have been energized, and TASK STANDARD:

Inadvertent Boron Dilution Alarms have been reset.

K/A: 015 A4.02 RATING: RO: 3.9 SRO: 3.9 10CFR55: 45.2 POSITION(S): RO/SRO VALIDATION TIME: 10 minutes

REFERENCES:

40OP-9ZZ03, Reactor Startup, Appendix D, Section D.2 LOCATION: SIMULATOR X PLANT CLASSROOM TIME CRITICAL: NO ALTERNATE PATH: NO PRA/SRA RELATED: NO APPROVALS DEVELOPED/REVISED BY: Joseph Stevens DATE: 4/19/2016 VALIDATED BY: John Rodgers DATE: 6/27/2016 TECH OPERATIONS REVIEW: N/A APPROVAL: N/A E-PLAN TRAINING REVIEW: N/A APPROVAL: N/A Only required for E-Plan JPMs EVALUATION EXAMINEE: DATE:

EVALUATOR: GRADE (circle): SAT / UNSAT*

START: STOP: TOTAL TIME: minutes

  • A grade of UNSAT for E-Plan JPMs requires a PVAR to be written, remediation, and re-evaluation. PVAR #

Issues identified on E-Plan JPMs during performance will be documented with a formal post-critique using Form EP-0800 and forwarded to the Emergency Preparedness organization for resolution.

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 SIMULATOR SETUP:

Reset to IC-9 or Reset to any Reactor Start-up IC and perform the INSTRUCTIONS FOR SETUP below SIMULATOR SCENARIO FILES, MALFUNCTIONS, REMOTE FUNCTIONS, ETC. FOR SETUP: N/A COMMAND DESCRIPTION INSTRUCTIONS FOR SETUP:

Ensure control boards and pertinent procedures are free of marks or writing.

GO TO RUN.

Withdraw control rods per 40OP-9ZZ03, Reactor Startup, until overlap is observed between Start-up Channels and Log Safety Channels (~ Group 4 CEAs at 40 withdrawn).

Ensure SEN-JR-5 is selected to S/U Channel.

Display the following ERFDADS points on the terminal facing the CEDMCS controls:

o SENIS1 (Startup counts) o SENIS2 (Startup counts) o SEJ1AA (Log power) o SEJ1BB (Log power)

Ensure the Inadvertent Boron Dilution Alarm is in on B03.

Acknowledge alarms.

GO TO FREEZE.

After the cue has been read, GO TO RUN.

PROCEDURES/MATERIALS:

This JPM was written using Revision 63 of 40OP-9ZZ03, Reactor Startup, Appendix D, Section D.2. This JPM may be used with later revisions if it is verified that the later revision does not affect the Steps/Standards of the JPM.

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 INFORMATION PRESENTED TO EXAMINEE:

ALL JPMS:

You may use any source of information normally available (procedures, prints, OAPs, etc.).

Classroom instruction materials (Lesson Plans, System Training Manuals, PowerPoint presentations, classroom notes, etc.) are not permitted to be used.

If there is a question regarding reference material desired to be used, ask evaluator prior to seeking reference.

INITIAL CONDITIONS:

Unit 1 is performing a reactor startup after a refueling outage.

The unit is currently in MODE 2 and proper NI overlap has just been verified.

40OP-9ZZ03, Reactor Startup, Appendix D is complete through step D.2.1.3.

INITIATING CUE:

The CRS directs you to de-energize Startup Channels per 40OP-9ZZ03, Reactor Startup, Appendix D, Checking NI Overlap and Turning Off Startup Channels, Section D.2, Turning Off Startup Channels.

Start on Step D.2.2.

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 INFORMATION FOR EVALUATOR USE:

An asterisk (*) denotes a Critical Step. Failure of a Critical Step will result in an UNSAT evaluation.

At the discretion of the Evaluator, this JPM may be terminated when the Task Standard is met or adequate time has been allowed to complete the JPM.

Any step marked UNSAT requires comments.

If this is the first JPM of the set, then ensure the examinee has been briefed.

Step sequence is not critical unless noted or will prevent the Task Standard from being met.

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM START TIME:

JPM Step: 1 Perform the following in preparation for de-energizing the Startup Channels:

Proc Step: D.2.2.1 Position SEN-HS-5A, SU CH 1 Volt Cutoff, to CONTROL CHANNEL 1.

Standard: Placed SEN-HS-5A, SU CH 1 Volt Cutoff, to CONTROL CHANNEL 1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 2 Perform the following in preparation for de-energizing the Startup Channels:

Proc Step: D.2.2.2 Position SEN-HS-6A, SU CH 2 Volt Cutoff, to CONTROL CHANNEL 2.

Standard: Placed SEN-HS-6A, SU CH 1 Volt Cutoff, to CONTROL CHANNEL 2 Comments (required for UNSAT):

SAT UNSAT JPM Step: 3 Perform the following in preparation for de-energizing the Startup Channels:

Proc Step: D.2.2.3 Shift SEN-JR-005, Startup/Control Flux Lvl, to CONTROL, using the right or left arrow on the circular selector on the face.

Standard: Pushed the right or left arrow on the circular selector on the front of SEN-JR-005, Startup/Control Flux Lvl, and shifted to CONTROL.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM Step: 4

  • Perform the following at the Startup and Control Channel Drawer, to turn off High Proc Step: D.2.3.1 Voltage:

Press the H.V. PERMIT push-button on Startup Channel 1.

Standard: Depressed the H.V. PERMIT push-button on Startup Channel 1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 5 Perform the following at the Startup and Control Channel Drawer, to turn off High Proc Step: D.2.3.2 Voltage:

Observe the amber H.V. PERMIT light is off, at Startup Channel 1.

Standard: Observed the amber H.V. PERMIT light is off, at Startup Channel 1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 6

  • Perform the following at the Startup and Control Channel Drawer, to turn off High Proc Step: D.2.3.3 Voltage:

Press the H.V. PERMIT push-button on Startup Channel 2.

Standard: Depressed the H.V. PERMIT push-button on Startup Channel 2.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM Step: 7 Perform the following at the Startup and Control Channel Drawer, to turn off High Proc Step: D.2.3.4 Voltage:

Observe the amber H.V. PERMIT light is off, at Startup Channel 2.

Standard: Observed the amber H.V. PERMIT light is off, at Startup Channel 2.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 8

  • Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.1 indication to the Control Channels:

Press the STARTUP/CONTROL push-button for Startup and Control Channel 1.

Standard: Depresses the STARTUP/CONTROL push-button for Startup and Control Channel 1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 9 Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.2 indication to the Control Channels Observe the red backlight STARTUP portion is off, at the pushbuttons for Startup and Control Channel 1.

Standard: Observed the red backlight STARTUP portion is off, at the pushbuttons for Startup and Control Channel 1.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM Step: 10 Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.3 indication to the Control Channels Observe the green backlight CONTROL portion is on, at the pushbuttons for Startup and Control Channel 1.

Standard: Observed the green backlight STARTUP portion is on, at the pushbuttons for Startup and Control Channel 1.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 11

  • Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.4 indication to the Control Channels:

Press the STARTUP/CONTROL push-button for Startup and Control Channel 2.

Standard: Depresses the STARTUP/CONTROL pushbutton for Startup and Control Channel 2.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 12 Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.5 indication to the Control Channels:

Observe the red backlight STARTUP portion is off, at the pushbuttons for Startup and Control Channel 2.

Standard: Observes the red backlight STARTUP portion is off, at the pushbuttons for Startup and Control Channel 2.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM Step: 13 Perform the following at the Startup and Control Channel Drawer, to shift Proc Step: D.2.4.6 indication to the Control Channels:

Observe the green backlight STARTUP portion is on, at the pushbuttons for Startup and Control Channel 2 Standard: Observes the green backlight STARTUP portion is on, at the pushbuttons for Startup and Control Channel 2.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 14 IF any TROUBLE light is on, THEN reset the light by pressing the TROUBLE Proc Step: D.2.4.7 pushbutton for ANY affected channel:

Startup and Control Channel 1 Startup and Control Channel 2 Standard: Marked step N/A.

Comments (required for UNSAT):

SAT UNSAT JPM Step: 15 IF any HIGH CPS light is on, THEN reset the light by pressing the HIGH CPS Proc Step: D.2.4.8 pushbutton for ANY affected channel:

Startup and Control Channel 1 Startup and Control Channel 2 Standard: Marked step N/A.

Comments (required for UNSAT):

SAT UNSAT

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 JPM Step: 16

  • Reset the Inadvertent Boron Dilution alarms, as follows:(Located behind B04, in Proc Step: D.2.5 cabinet J-ZJN-C06)

Press the RESET pushbutton, on JSEN-NI-005, BDAS Display Module.

Press the RESET pushbutton, on JSEN-NI-006, BDAS Display Module Standard: Reset the Inadvertent Boron Dilution alarms by pressing the RESET pushbutton for both BDAS channels Examiner Cue Once the examinee resets the Inadvertent Boron Dilution alarms, This JPM is complete.

Comments (required for UNSAT):

SAT UNSAT JPM STOP TIME:

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 RECORD OF REVISIONS REVISION # REVISION DATE REASON COMMENTS 00 4/19/2016 6 New JPM REASON REVISED Enter the numbers corresponding to the reason revised in the Reason Revised column and brief description of changes in Comments Column. Comments are to be numbered consecutively in each revision.

1. Vendor reference document upgrade
2. Plant modification (include number)
3. Procedure upgrade
4. Internal or External Agency Commitment (indicate item number)
5. Technical Specification Change (indicate amendment number)
6. Other (explain in comments)

2016 PVNGS NRC Initial Exam JPM S8 Rev 1 EXAMINEE INITIAL CONDITIONS:

Unit 1 is performing a reactor startup after a refueling outage.

The unit is currently in MODE 2 and proper NI overlap has just been verified.

40OP-9ZZ03, Reactor Startup, Appendix D is complete through step D.2.1.3.

INITIATING CUE:

The CRS directs you to de-energize Startup Channels per 40OP-9ZZ03, Reactor Startup, Appendix D Start on Step D.2.2.

EXAMINEE

Appendix D Scenario Outline Form ES-D-1 Facility: PVNGS Scenario No.: 1 Op Test No.: 2016 NRC Exam Examiners: Operators:

Initial Conditions: 2% power, MOC, AFA-P01 OOS Turnover: Maintain steady state operations, transfer from B EHC Pump in service to A EHC Pump in service.

Event No. Malf. Event Type* Event Description No.

1 N (BOP) Transfer from EHC Pump B to EHC Pump A in service 2 I (ATC) Pressurizer Level Transmitter RCA-LI-110X fails to 100%

TS (SRO) 3 C (SRO, BOP) Plant Cooling Water Pump shaft shear, standby pump fails to auto start 4 I (SRO, ATC, BOP) Reactor Regulating System THOT fails high 5 I (SRO, BOP) Inadvertent MSIS TS (SRO) 6 M (ALL) Loss of Off-Site Power (trip initiator) 7 C (ATC, SRO) Full Strength CEA 57 fails to insert on trip - emergency boration 8 C (BOP, SRO) B EDG Output Breaker fails to close 9 M (ALL) Aux Feed Pump AFN-P01 overcurrent trip

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (TS)Technical Specifications Actual Target Quantitative Attributes 8 Total malfunctions (5-8) 3 Malfunctions after EOP entry (1-2) 4 Abnormal events (2-4) 2 Major transients (1-2) 1 EOPs entered/requiring substantive actions (1-2) 1 EOP contingencies requiring substantive actions (0-2) 3 Critical tasks (2-3)

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 2016 NRC Exam Scenario 1 Overview Event 1 The BOP will transfer from EHC (Electro-Hydraulic Control) Pump B to ECH Pump A per 40OP-9CO01, Electro-Hydraulic Control System, Section 6.7, Shifting from Hydraulic Fluid Pump B to Hydraulic Fluid Pump A.

Event 2 Pressurizer level transmitter RCA-LI-110X will fail to 100%. The ATC will address the ARP due to level being ~ 70% higher than setpoint and letdown will isolate in ~ 45 seconds. The ARP will direct selecting the unaffected channel of level control. If letdown isolates, the CRS will direct the restoration of letdown after the unaffected channel has been selected.

The CRS will also address TS due to LT-110X being a PAMI indication.

Event 3 The running PW pump will experience a sheared shaft. The standby pump will fail to auto start. The CRS will enter 40AO-9ZZ03, Loss of Cooling Water, and direct starting the standby pump manually.

Event 4 A THOT input to the RRS System (input to Tave 1) will fail high. The CRS will enter 40AO-9ZZ16, RRS Malfunctions, and direct the BOP to determine the failed transmitter at the RRS cabinet and select the unaffected channel. The CRS will also direct the ATC to take either MANUAL or LOCAL / AUTO control of pressurizer level since the remote setpoint will be failed high as a result of the THOT failure.

Event 5 A Train B MSIS will occur resulting in a loss of Feedwater to both SGs. The CRS will enter 40AO-9ZZ17, Inadvertent PPS-ESFAS Actuations, and direct the BOP to restore Feedwater using Aux Feedwater.

Event 6 When feed has been restored, a loss of off-site power will occur. This will result in a reactor trip. The CRS will enter 40EP-9EO01, SPTAs.

Event 7 Due to full strength CEA 57 failing to insert on the trip, the CRS will direct the ATC to commence emergency borating to the RCS. The ATC will have to use an alternate boration path due to the loss of power on the trip.

Event 8 The Train B class 4kV bus will be de-energized due to the B EDG output breaker failing to close. The BOP will attempt to close the output breaker but will not be successful. As a result, he will have to direct an AO to emergency stop the EDG within 15 minutes due to running with no cooling water.

Event 9 8 minutes after the reactor trip, AFW pump AFN-P01 will trip on 86 lockout (overcurrent trip) putting the crew in a LOFW event. Due to the B AFW pump being available (only AFW pump available) and power available on only the A train, the CRS will enter the Functional Recovery procedure. The CRS will direct energizing the B 4kV bus from the A EDG and restoring Feedwater with the B AFW pump.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 Critical Task # 1: Commence borating to the RCS at a rate of 26 gpm within 15 minutes of the reactor trip due to less than all full-strength CEAs being fully inserted.

Safety Significance: Per the Time Critical Action Program, commence emergency boration (MODES 3

- 5) within 15 minutes due to minimum shutdown margin less than limit in COLR. With less than all full strength CEAs fully inserted, the SDM is assumed to be less than minimum required. Justification for the 15 minutes is from 40DP-9ZZ04, Time Critical Action Program. Justification for the 26 gpm limit is from Technical Specification Bases for LCO 3.1.1, SDM - Reactor Trip Breakers Open.

Cueing: The crew will have indication of the stuck CEA from the Rod Bottom Light for the CEA failing to illuminate on the trip as well as the CPDS (CEA Position Display System) indicating one CEA failed to insert on the reactor trip.

Measurable Performance Indicator: The crew will align Charging Pump suction from the Refueling Water Tank (RWT) and ensure adequate Charging Pump flow of greater than or equal to 26 gpm. The crew will have to manually start a Charging Pump to achieve the minimum required boration flow of 26 gpm. Additionally, the crew will need to start at least one Charging Pump per step 4 of SPTAs for inventory control as well as to utilize Auxiliary Spray to control RCS pressure. Adequate boration flow can also be seen using the CVCS System Diagram using an ERFDADS computer display.

Performance Feedback: The crew will have indication of boration flow by ensuring the Charging Pump suction has been aligned to the Refueling Water Tank and Charging Pump flow is 26 gpm.

Critical Task # 2: Operate Auxiliary Spray and/or ADVs as necessary to prevent lifting primary safety valves.

Safety Significance: Due to the loss of all feedwater and the requirement to maintain boration flow to ensure the reactivity safety function is satisfied, auxiliary spray and/or ADVs will be required to maintain RCS pressure less than the lift setpoint for primary safeties. Lifting of the primary safety valves would unnecessarily complicate the event, challenging the RCS inventory and pressure control safety functions.

Cueing: The crew will have indication of a loss of all feed water as well as the running Charging Pump (which they cannot secure due to the requirement to maintain a boration to satisfy the reactivity control safety function), and PZR level and pressure rising. The crew should recognize that action is needed to prevent lifting a primary safety valve.

Measureable Performance Indicator: The crew will operate controls for the Pressurizer Auxiliary Spray and/or Steam Generator ADVs as necessary while observing board indications for pressurizer level and pressure.

Performance Feedback: Board and computer indications of RCS pressure (primary safety valve lift setting of 2475 psig) as well as Primary Safety Valve position indicators on B04. The crew will demonstrate satisfactory performance by maintaining primary pressure less than the lift setpoint of the PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 Primary Safety Valves (2475 psig).

Critical Task # 3: Restore power to Train B Class 4kV bus PBB-S04 prior to exiting MVAC-2, DGs, and restore feed to at least one SG prior to exiting HR-1, SG with no SI.

Safety Significance: The crew will have to restore feed water to at least one SG to ensure adequate inventory in the SG(s) to remove decay heat from the core.

Cueing: The crew will have indication of a complete loss of feed water due to the MSIS stopping both Main Feedwater Pumps, AFA-P01 is OOS, AFN-P01 will experience a sheared shaft ~ 8 minutes after the reactor trip, and the loss of power to AFB-P01. There will also be indication provided by all feed water flow indicators indicating 0 gpm to each SG.

Measurable Performance Indicator: The crew will have to close breakers to connect the Train A and Train B 4kV buses, start AFB-P01, and open flow control valves to commence feeding at least one SG.

Performance Feedback: When the crew has restored power to AFB-P01, started AFB-P01 and aligned a feed path to at least one SG, the crew will have indication of feed flow to at least one SG as well as a rising trend on SG level(s), and depending on feed flow rate, a lowering trend on RCS temperature.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 Turnover Plant Conditions:

2% power, MOC, 250 EFPD.

AFN-P01 supplying feed to both SGs.

SG levels are being controlled using Downcomer Bypass valves.

CEDMCS Mode Selector Switch is in Manual Sequential.

Main Generator output breakers are closed to re-ring the bus, the MOD is open.

Pressurizer is in boron equalization.

PC Cleanup is NOT recirculating the RWT.

Unit 2 is supplying the Aux Steam cross-tie header.

Equipment Out of Service:

AFA-P01 is OOS for bearing replacement.

Expected return to service in the next 12 - 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.

LCO 3.7.5, Auxiliary Feedwater System, Conditions A and B were entered 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> ago.

Risk Management Action Level is ORANGE.

Planned Shift Activities:

Transfer from EHC (Electro-Hydraulic Control) Pump B to EHC Pump A per 40OP-9CO01, Electro-Hydraulic Control System, Section 6.7, Shifting from Hydraulic Fluid Pump B to Hydraulic Fluid Pump A, in preparation for maintenance on EHC Pump B.

An area operator is standing by in the field to support the EHC Pump swap.

Maintain power stable as final preparations are being made for placing a MFW Pump in service and resuming the power ascension to 12% power.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 DRIVER INSTRUCTIONS for SIMULATOR SETUP RESET to IC-10 and run Scenario 2016 NRC Scenario 1 EVENT TYPE MALF # DESCRIPTION DEMAND INITIATOR VALUE 1 None None Transfer from B EHC Pump to A EHC Pump None None 2 MF CV14A RCA-LI-110X fails to 100% 100 Key 2 3 CM CPSW01 Plant Cooling Water Pump B shaft shear Sheared Key 3 PWNP01 B_1 3 CM CPSW01 Plant Cooling Water Pump A fails to auto start FTAS Key 3 PWNP01 A_5 4 CM TRRX05 RCS Thot transmitter TT-111X fails to 650°F 650 Key 4 RCNTT1 11X_1 5 MF RP06B1 Train B MSIS actuation Actuate Key 5 5 MF RP06B2 Train B MSIS actuation Actuate Key 5 6 MF ED02 Loss of Offsite Power Loss Key 6 7 MF RD03K CEA 57 fails to insert on trip As-Is Setup 8 MF EG09B B EDG output breaker fails to close As-Is Setup 9 MF FW21A AFN-P01 overcurrent trip (8 minute time delay) Trip Rx Trip N/A RF EG21 Emergency Stop B EDG Stop Key 31 PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Scenario Event Description NRC Exam Scenario # 1 Driver Setup:

RESET to IC-10 Ensure SG levels are stable between 45 and 50% NR.

Run 2016 NRC Scenario 1 event file Run AFA-P01 Scenario file Place OOS tags on AFA-P01 Ensure the Simulator Parameter Recording Task is initiated PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 1 Page 8 of 36 Event

Description:

Transfer from B EHC Pump to A EHC Pump running Time Position Applicants Actions or Behavior Procedure Caution: If EHC fluid pressure drops to 1100 psig, the Main Turbine will trip.

BOP 1. Start Hydraulic Fluid Pump A by momentarily placing handswitch CON-HS-4, Hydraulic Fluid Pump A P01A, to START.

BOP 2. Check ALL the following for Hydraulic Fluid Pump A:

The red START light at handswitch CON-HS-4, Hydraulic Fluid Pump A P01A, is on.

Motor amps are less than 219 amps.

Pump discharge pressure is between 1500 psig and 1750 psig, indicated locally on CON-PI-007, A CO Pump Local Disch Press Indicator.

Driver Cue: When called to report A EHC Pump discharge pressure, wait 15 seconds and report discharge pressure is 1650 psig and stable.

Procedure Note: In the following step, the handswitch will return to the center AUTO position when released.

BOP 3. Perform the following for Hydraulic Fluid Pump B:

Stop Hydraulic Fluid Pump B by momentarily placing handswitch CON-HS-5, HYDRAULIC FLUID PUMP B P01B, to STOP.

Check the green STOP light is on at handswitch CON-HS-5, HYDRAULIC FLUID PUMP B P01B.

Examiner Note: When the B EHC Pump has been stopped, or at lead evaluators discretion, proceed to Event 2, Pressurizer Level Transmitter RCA-LI-110X fails to 100%.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 9 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 2, Pressurizer Level Transmitter RCA-LI-110X fails to 100%

Indications Available:

4A02B PZR LVL HI-LO Rising letdown flow Examiner Note: The following steps are from 40AL-9RK4A, window 4A02B, PZR LVL HI-LO Examiner Note: The CRS may direct the RO to start a second Charging Pump prior to addressing the ARP (allowed as a Prompt and Prudent action). If the second Charging Pump is started prior to addressing the ARP, letdown will likely not auto isolate.

If the crew decides to hard start a second charging pump and then return it to auto after-start when the event has been mitigated, they will

1. Check BOTH of the following level indications:

ATC RCA-LI-110X, Level Control Channel X RCB-LI-110Y, Level Control Channel Y

2. Check ALL of the following Pressurizer backup heaters are energized:

RCA-HS-100-4, Backup Heaters Bank RCB-HS-100-5, Backup Heaters Bank ATC RCN-HS-100-6, Backup Heaters Bank RCN-HS-100-7, Backup Heaters Bank RCN-HS-100-8, Backup Heaters Bank RCN-HS-100-9, Backup Heaters Bank PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 10 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

3. IF ONE of the following level control channels has failed:

RCA-LI-110X, Level Control Channel X RCB-LI-110Y, Level Control Channel Y THEN perform the following:

Place RCN-HS-110, Level Control Selector Channel X/Y, to ONE of the following unaffected level instruments:

ATC CH-X CH-Y Place RCN-HS-100-3, Heater Control Selector Level Trip Channel X/Y, to ONE of the following unaffected level instruments:

CH-X CH-Y

4. IF BOTH of the following conditions exist:

RCN-LIC-110, Level Setpoint Control, is in REMOTE and AUTOMATIC Pressurizer level is NOT recovering THEN perform the following:

Place RCN-LIC-110, Level Setpoint Control, in ONE of the following ATC at direction of the SM/CRS:

o LOCAL AUTOMATIC (REFER TO the Shifting RCN-LIC-110, Pressurizer Level Control, Modes appendix in 40OP-9CH01, CVCS Normal Operations) o MANUAL Adjust RCN-LIC-110, Level Setpoint Control, to maintain Pressurizer level between 33% and 52.5%.

5. IF BOTH of the following conditions exist:

The standby charging pump is operating The SM/CRS directs stopping the standby charging pump THEN stop the standby charging pump per 40OP-9CH01, CVCS Normal Operations.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 11 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

6. IF a level channel failure is the cause of the alarm condition, THEN perform the following:

REFER TO LCO 3.3.10, Post Accident Monitoring (PAM)

CRS Instrumentation.

REFER TO LCO 3.3.11, Remote Shutdown System.

Initiate a Condition Report for Maintenance to troubleshoot and repair the failed instrument.

Technical Specifications:

Due to the failure of RCA-LI-110X, LCO 3.3.10, Post Accident Monitoring Instrumentation, Condition A o Restore required channel to OPERABLE within 30 days LCO 3.3.11, Remote Shutdown System, Condition A o Restore required functions to OPERABLE within 30 days

7. IF Pressurizer steady state level exceeded 56%, THEN REFER TO LCO 3.4.9, Pressurizer.

Examiner Note: If letdown isolated as a result of RCA-LI-110X failing to 100%, the crew will perform 40AO-9ZZ05, Loss of Charging or Letdown. The following steps are from the AOP:

CRS 1. Enter AOP Entry Time and Date

2. IF BOTH of the following occur at any time during this procedure:

Pressurizer level lowers to 33%

Restoration of charging is NOT impending THEN trip the reactor.

Procedure Note: Multiple indications and SM/CRS discretion should be applied to diagnosing Charging Pump gas binding.

3. IF Charging Pump gas binding is indicated by ANY of the following:

Charging header flow fluctuations Charging header pressure fluctuations Charging header flow less than expected for running charging pumps Charging suction source (VCT, RWT) level lost THEN perform Appendix G, Responding to Gas Binding of Charging Pumps.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 12 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

4. IF a Charging line rupture has occurred, THEN perform the following:

Close CHB-UV-515, Letdown To Regen HX Isolation Valve, to isolate letdown flow.

Place ALL of the following handswitches in PULL-TO-LOCK:

CHA-HS-216, Charging Pump 1 P01 CHB-HS-217, Charging Pump 2 P01 CHA-HS-218A, Charging Pump 3 P01 CHB-HS-218, Charging Pump 3 P01 Perform the following to close CHN-UV-501, VCT Outlet:

CHN-HS-501, Volume Control Tank Outlet Vlv, in CLOSE.

Direct an operator to open NHN-M7208, Cktbrk for Volume Control Tk Outlet Vlv CHN-UV-501.

WHEN NHN-M7208 is open, THEN release CHN-HS-501.

5. IF Charging Flow can NOT be restored through the normal Charging Pump discharge flowpath, THEN perform Appendix J, Charging Thru HPSI Cold Leg Injection via SIE-V508.

ATC 6. Place RCN-LIC-110, PLCS Master Controller, in MAN with 0% output.

ATC 7. Check that letdown backpressure is less than setpoint.

8. If pressurizer level is 33% or more AND rising, THEN ensure no more ATC than one Charging Pump is running.
9. IF ANY of the following:

Pressurizer level is 56% or more and rising Pressurizer level is 27% or less and lowering THEN perform the following:

Ensure LCO 3.4.9, Pressurizer, has been declared not met AND Condition A has been entered.

Initiate actions to place the Unit in Mode 3 with Reactor Trip Breakers open within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

Initiate actions to place the Unit in Mode 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 13 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

10. IF letdown was NOT manually isolated, THEN determine the cause of the loss of letdown (REFER TO Appendix E, Supplementary Information) by evaluating ANY of the following:

PLCS failures CREW NC flow to Letdown Heat Exchanger SIAS/CIAS CVCS component failures Loss of IA Loss of power

11. IF the selected Letdown Control or Backpressure Control Valve(s) has failed, AND it is desired to place the standby valve in service, THEN PERFORM Appendix F, Aligning Letdown Control And Backpressure Valves.
12. IF ALL of the following conditions exist:

CHB-UV-515, Letdown To Regen HX Isolation Valve, closed due to an invalid high temperature interlock CHN-TI-221, Regenerative Heat Exchanger Letdown Temperature, indication is available Letdown is desired THEN direct maintenance to PERFORM 81DP-0DC17, Temporary Modification Control, to install a jumper across relay63X-T221, points 19 and 20 in cabinet E-ZJB-C03.(REFER TO drawing E-CHB-031)

13. IF CHB-UV-523, Regenerative Heat Exchanger Outlet Isolation Valve, is closed due to an invalid high temperature alarm, AND letdown is desired, THEN place CHB-HS-523, LETDOWN CTMT ISOL, to OPEN.
14. IF letdown can be restored, THEN perform the following:

CRS PERFORM Appendix A, Restoration of Letdown With A Pressurizer Steam Bubble.

Examiner Note: The following steps are from Appendix A, Restoration of Letdown with a Pressurizer Steam Bubble ATC 1. Enter Appendix Entry Time and Date

2. Ensure at least ONE of the following valves are closed:

CHB-UV-515, Letdown To Regen HX Isolation Valve ATC CHA-UV-516, Letdown To Regen HX Isolation Valve CHB-UV-523, Regenerative Heat Exchanger Outlet Isolation Valve PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 14 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

3. Ensure BOTH of the following Letdown Control Valves are closed:

ATC CHE-LV-110P, Letdown Control Valve CHE-LV-110Q, Letdown Control Valve

4. Ensure BOTH of the following ERFDADS points associated with Letdown are set to alarm at the appropriate setpoint:

ATC CHT221, Regen Hx Outlet Temperature, at a high alarm of 380°F CHP201, Letdown Intermediate Press / Backpressure, at a low alarm of 205 psig

5. Perform the following:

ATC Place CHN-PIC-201, Letdown Backpressure Controller, in MAN.

Open the selected Letdown Backpressure Valve(s) to 60% output.

Procedure Note: RCP HP seal cooler inlet temperature is expected to rise to between 200°F and 220°F when seal injection is stopped. All other seal temperatures are expected to remain normal.

6. IF ANY of the following:

NO Charging Pumps are running ONLY one Charging Pump is available THEN perform the following:

Ensure controlled bleedoff is isolated on all standby RCPs prior to Seal 2 Outlet Temperature exceeding 250°F.

Isolate RCP seal injection by closing ONE of the following:

o Seal Injection Flow Control Valves o CHB-HV-255, Seal Injection Supply Header Isolation Valve Ensure CHN-HS-240, Charging Line to RC Loop 2A VLV PDV-240, is in OPEN MOD.

IF NO Charging Pump is running, THEN start one Charging Pump.

7. WHEN the selected Letdown Control Valve(s) is closed, THEN ensure ALL of the following isolation valves are open:

ATC CHB-UV-523, Regenerative Heat Exchanger Outlet Isolation Valve CHB-UV-515, Letdown To Regen HX Isolation Valve CHA-UV-516, Letdown To Regen HX Isolation Valve

8. IF ANY isolation valve is open in override or manual, THEN ensure compliance with LCO 3.6.3, Containment Isolation Valves.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 15 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

9. IF letdown flow has been lost for 22 minutes or more, AND RCS temperature is greater than 130°F,THEN perform the following:

Open CHN-HV-526, Letdown Control Valves Bypass Valve.

WHEN flow has been maintained through CHN-HV-526 for at least four minutes, THEN close CHN-HV-526.

Procedure Note: Saturation temperature for 220 psig is 395°F and saturation temperature for 300 psig is 421°F.

Procedure Caution: Insufficient letdown backpressure will cause flashing in the letdown system.

10. Slowly adjust the Letdown Control Valve(s) AND Backpressure Control Valve(s) to establish ALL of the following:

Letdown flow approximately 25 - 35 gpm Letdown backpressure 220 to 300 psig ATC Regenerative Heat Exchange Letdown Temperature less than saturation temperature for the existing backpressure, as indicated on CHN-TI-221, Regenerative Heat Exchanger Letdown Temperature.

ATC 11. WHEN letdown flow is indicated, THEN maintain Letdown Heat Exchanger Outlet Temperature less than 135°F.

12. IF a second charging pump will NOT be started, THEN perform the following:

Place CHN-HS-4, Charging Pump Mode Selector, in a position such that the running charging pump is designated as the Always Running pump.

Slowly adjust the Letdown Control Valve(s) AND Backpressure Control Valve(s) to establish ALL of the following:

o The desired pressurizer level o Letdown backpressure 220 to 300 psig o Regenerative Heat Exchange Letdown Temperature less than saturation temperature for the existing backpressure, as indicated on CHN-TI-221, Regenerative Heat Exchanger Letdown Temperature o Letdown Heat Exchanger temperature less than 135°F GO TO step 20.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 16 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

13. IF a second charging pump will be started, THEN ensure ALL of the following are in manual:

ATC RCN-LIC-110, PLCS Master Controller CHN-PDIC-240, Charging Header Backpressure Control Valve CHN-PIC-201, Letdown Backpressure Control Procedure Note: LD HDR SYS TRBL (3A10A) will alarm and remain locked in as long as PTID CHPS201, Letdown Heat Exchanger to LD Back Press Valve Press Hi - Lo is 308 psig or less. This alarm is used to diagnosis a letdown line break in the Aux Building and to ensure subcooling. This alarm will not be available once backpressure is reduced to less than 308 psig.

ATC 14. Ensure CHN-PIC-201 is adjusted to maintain 220 - 300 psig and as close to 220 psig as possible.

Procedure Note: With one charging pump running, the nominal, steady-state regen heat exchanger outlet temperature is approximately 265° as indicated on CHN-TI-221. This temperature will decrease when the second charging pump is started. Subsequent manual increases in letdown flow rate may cause transient temperature increases up to 380°F or higher if not properly controlled.

ATC 15. Start the second Charging Pump.

Procedure Caution: Any increase in letdown flow rate may produce relatively large increases in intermediate letdown pressure as indicated by CHN-PIC-201. These pressure spikes may result in the lifting of CHN-PSV-345, Regen Hx to Letdown Hx Relief.

16. Perform the following:

Slowly adjust RCN-LIC-110 to establish ALL the following:

o Appropriate letdown flow for two charging pumps o Letdown flow less than 150 gpm ATC o Letdown Heat Exchanger temperature less than 135°F IF CHT221 reaches 380°F or more, THEN reduce the letdown flow to drop temperature to less than 380°F.

Slowly adjust CHN-PIC-201 to maintain backpressure 220 to 300 psig.

17. IF a third charging pump will NOT be started, THEN perform the following:

Slowly adjust RCN-LIC-110 to establish ALL of the following:

o The desired pressurizer level ATC o Letdown flow less than 150 gpm o Letdown Heat Exchanger temperature less than 135°F Slowly adjust CHN-PIC-201 to maintain backpressure 220 to 300 psig.

GO TO step 20.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 2 Page 17 of 36 Event

Description:

Pressurizer Level Transmitter LT-110X fails high Time Position Applicants Actions or Behavior

20. WHEN pressurizer level is at the desired setpoint, THEN perform the following:

Ensure RCN-LIC-110 is in MANUAL.

ATC Transfer RCN-LIC-110 to ONE of the following:

o Remote Automatic o Local Automatic

21. IF CHN-PDIC-240, Charging Header Backpressure Control Valve, is in MAN,THEN perform the following:

ATC Slowly adjust CHN-PDIC-240 to 90-135 psid.

Place CHN-PDIC-240 in AUTO.

22. Perform the following:

ATC Slowly adjust CHN-PIC-201 setpoint to 375 psig.

Place CHN-PIC-201 in AUTO.

23. IF CHN-TIC-223, Letdown Hx Outlet Temperature Controller, is in MANUAL, AND plant conditions will allow, THEN transfer CHN-TIC-223 to AUTO with a setpoint of 120°F.
24. IF the Pressurizer Level Control System is automatically controlling ATC pressurizer level, THEN ensure ALL available Charging Pumps are green flagged for automatic control.
25. IF letdown has been restored with BOTH of the following:

Only one charging pump available Seal injection isolated THEN perform the following:

IF BOTH of the following:

o Pressurizer level is NOT at the desired setpoint o The SM/CRS directs THEN place RCN-LIC-110, PLCS Master Controller, in MAN and restore pressurizer level to the desired setpoint.

WHEN pressurizer level is at the desired setpoint, THEN transfer RCN-LIC-110 to ONE of the following:

o Remote Automatic o Local Automatic ATC 26. IF RCP seal injection is in operation, THEN ensure flow is 6.0 to 7.5 gpm.

Examiner Note: When RCN-HS-110 has been taken to the Y position and (if applicable) the ATC operator has commenced restoring letdown, or at Lead Evaluators discretion, proceed to Event 3, B Plant Cooling Water Pump trip.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 3 Page 18 of 36 Event

Description:

B Plant Cooling Water Pump shaft shear, A Plant Cooling Water Pump fails to auto start Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 3, B Plant Cooling Water Pump shaft shear Indications Available:

7A05B PCW DSCH PRESS HI-LO Abnormally low amps on B Plant Cooling Water Pump Examiner Note: The following steps are from 40AO-9ZZ03, Loss of Cooling Water Examiner Note: Although not procedurally directed, when the crew determines that the B Plant Cooling Water Pump has a sheared shaft, the crew should secure the pump to ensure no further damage to the pump or connected equipment is potentially damaged.

CRS 1. Enter AOP Entry Time and Date

2. IF no Plant Cooling Water pumps are running, THEN perform the following:
a. IF at least one Plant Cooling Water Pump is available, THEN start the Plant Cooling Water Pump.
b. IF electrical power must be restored to start a Plant Cooling Water Pump, THEN perform the following:
1) Place both PW Pump handswitches in PULL TO LOCK.
2) PERFORM 40AO-9ZZ12, Degraded Electrical Power.

Driver Cue:

If called to investigate the B PW Pump and the B Pump has NOT been secured, wait 1 minute and report that the motor is running but the pump does not appear to be turning.

If called to investigate the B PW Pump and the B Pump HAS been secured, wait 1 minute and report that the pump is not running and there are no abnormal indications locally.

If called to perform post-start checks on the A Pump, wait 1 minute and report that the post-start checks are sat.

If called to walkdown the PW system to look for leaks, wait 5 minutes and report no indication of leaks on the PW system.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 3 Page 19 of 36 Event

Description:

B Plant Cooling Water Pump shaft shear, A Plant Cooling Water Pump fails to auto start Time Position Applicants Actions or Behavior

3. IF at least one Plant Cooling Water pump is running, AND supply pressure is 40 psig or less, THEN perform the following:
a. Start the standby pump.

BOP b. Direct an operator(s) to walkdown PW system piping to check that no leaks exist.

c. Direct an operator to check the suction screen for the operating pump is NOT clogged.
4. IF the PW system has been restored, THEN GO TO the appropriate CRS procedure for current plant conditions.

Examiner Note: When the A PW Pump has been started, or at Lead Evaluators discretion, proceed to Event 3, RRS THOT fails high.

  • If letdown isolated during Event 2, do not proceed to Event 4 until letdown has been restored.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 20 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 4, RRS THOT fails high Indications Available:

RCN-TT-111X indicating off-scale high Pressurizer level setpoint rises to 53%

Lowering letdown flow Examiner Note: The following steps are from 440AO-9ZZ16, RRS Malfunctions CRS 1. Enter AOP Entry Time and Date ATC 2. Ensure that CEDMCS is NOT in Auto Sequential

3. Check that pressurizer level is trending to the proper setpoint for ATC reactor power:

REFER TO Appendix A, Pressurizer Level Setpoint Program Examiner Note: Pressurizer level setpoint at 2% power should be 33%, however the setpoint is now 53% due to the high Thot failure. Based on the crew interpretation of the step, they may or may not take the contingency actions listed below (step 3.1) 3.1 Perform all of the following:

a. IF RCN-LIC-110, Pressurizer Level Control, is in Remote Automatic, THEN transfer RCN-LIC-110 to MANUAL.
b. Ensure RCN-LIC-110, Pressurizer Level Control, is in ONE of the following:
  • Local Automatic ATC
  • Manual
c. Maintain pressurizer level 33 to 53%. REFER TO Appendix A, Pressurizer Level Setpoint Program.
d. Ensure adequate charging flow for present plant conditions.
e. IF letdown isolates, THEN PERFORM 40AO-9ZZ05, Loss of Charging or Letdown.

Examiner Note: Steps for changing the mode of operation for RCN-LIC-110, Pressurizer Level Controller, are located in 40OP-9CH01, CVCS Normal Operations, and are located at the end of Event 4.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 21 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior

4. Determine the failed instrument by observing ALL of the following:
  • RCN-TT-111Y, Tcold
  • RCN-TT-121Y, Tcold CREW
  • RCN-TT-111X, Thot (failed instrument)
  • RCN-TT-121X, Thot
  • RCN-TR-100 (sum / avg circuit)
5. IF RCN-TR-100 indicates a failed instrument in the TAVG circuit, BOP THEN perform Attachment C-2, Determining the Failed TAVG Instrument, to determine the failed instrument.

Examiner Note: Attachment C-2 is performed outside of the control room. Steps from Attachment C-2 are located at the end of this section.

Procedure Note: Failure of a temperature instrument could affect COLSS if the failed instrument is still reading within its normal range.

6. Determine the impact of the failure. REFER TO Appendix B, CRS Control System Response to Instrument Failures.
7. IF RRS is selected to ONE of the following:
  • Average
  • The affected instrument THEN perform the following:
a. IF RCN-LIC-110, Pressurizer Level Control, is in Remote Automatic, THEN transfer RCN-LIC-110 to MANUAL.

ATC

b. Ensure RCN-LIC-110, Pressurizer Level Control, is in ONE of the following:
  • Local Automatic
  • Manual
c. Perform Appendix C, Operation of the Reactor Regulation System, to select the unaffected instrument at the RRS Test Panel.

Examiner Note: Appendix C is performed outside of the control room. Steps from Appendix C are located at the end of this section.

BOP 8. Check that Tavg/Tref mismatch is 3°F or less.

9. Place CEDMCS in the desired mode of operation.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 22 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior

10. IF Remote Automatic operation of the PLCS is desired, THEN perform the following:
a. Ensure RCN-LIC-110, Pressurizer Level Control, is in ATC MANUAL.
b. Transfer RCN-LIC-110, Pressurizer Level Control, to Remote Automatic.

CRS 11. GO TO the appropriate procedure for the current plant conditions.

Examiner Note: When the unaffected Tavg channel (Tavg 2) has been selected and PLCS has either been returned to Remote Automatic or the crew decides to leave PLCS in Local Automatic, or at Lead Evaluators discretion, proceed to Event 5, Inadvertent MSIS.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 23 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior Examiner Note: The following steps are from Attachment C-2, Determining the Failed Tavg Instrument.

1. REFER TO Attachment C-3, Reactor Regulation System Test BOP Drawer Pushbutton Description, for descriptions of the Reactor Regulation System Test Drawer pushbuttons.

Procedure Note: DVM voltage going to zero when the TEST PROBE pushbutton is depressed indicates that all the other pushbutton inputs are disconnected.

BOP 2. Press the TEST PROBE pushbutton.

BOP 3. Check that DVM voltage indicates zero volts.

BOP 4. Press the DVM pushbutton that corresponds to TAVG1 (Reactor Coolant Average Temperature 1).

BOP 5. Record voltage indicated on the DVM for TAVG1 in the table in step 16.

BOP 6. Press the TEST PROBE pushbutton.

BOP 7. Check that DVM voltage indicates zero volts.

BOP 8. Press the DVM pushbutton that corresponds to TAVG2 (Reactor Coolant Average Temperature 2).

BOP 9. Record voltage indicated on the DVM for TAVG2 in the table in step 16.

BOP 10. Press the TEST PROBE pushbutton.

BOP 11. Check that DVM voltage indicates zero volts.

BOP 12. Press the DVM pushbutton that corresponds to TAVG (Reactor Coolant Average Temperature).

BOP 13. Record voltage indicated on the DVM for TAVG in the table in step 16.

BOP 14. Press the TEST PROBE pushbutton.

BOP 15. Check that DVM voltage indicates zero volts.

BOP 16. Record voltage indicated on the DVM for the selected TAVG in the table below.

17. Determine which instrument is failed by comparing the voltages BOP recorded in step 16. To the normal TLI for the current power per Attachment C-4, DVM Voltage and Associated Approximate Input Value.

BOP 18. Notify the SM/CRS of the failed instrument.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 24 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior Examiner Note: The following steps are from Appendix C, Operation of the Reactor Regulating System IF a temperature instrument has failed, THEN perform the following:

BOP a. REFER TO Attachment C-3, Reactor Regulation System Test Drawer Pushbutton Description, for descriptions of the Reactor Regulation System Test Drawer pushbuttons.

Procedure Note: DVM voltage going to zero when the TEST PROBE pushbutton is depressed indicates that all the other pushbutton inputs are disconnected.

BOP b. Press the TEST PROBE pushbutton.

BOP c. Check that DVM voltage indicates zero volts.

d. Press the DVM pushbutton that corresponds to the TAVG to be selected:

BOP TAVG1 (RCS Average Temperature Loop 1)

TAVG2 (RCS Average Temperature Loop 2)

TAVG (RCS Average Temperature)

e. Record voltage indicated on the DVM for the selected TAVG in the BOP table below:
f. Check that DVM voltage recorded in step 1.e. represents the BOP normal TAVG for the current power per Attachment C-4, DVM Voltage and Associated Approximate Input Value.
g. WHEN evaluation of DVM voltage is complete, THEN press the BOP TEST PROBE pushbutton to disconnect the DVM from the input.

Procedure Caution: Selecting AVG while the Tavg Deviation light is lit will generate an AMI.

h. Place the TAVG INPUT selector switch to the selected input:

TAVG1 (RCS Average Temperature Loop 1)

BOP TAVG2 (RCS Average Temperature Loop 2)

TAVG (RCS Average Temperature)

BOP i. Inform the CRS of the status of the RRS panel.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 25 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior Examiner Note: The following steps are from 40OP-9CH01, CVCS Normal Operations, Appendix M, Shifting RCN-LIC-110, Pressurizer Level Control, Modes:

1.0 Shifting to Manual Mode ATC 1.1 Press the MAN pushbutton ATC 1.2 Check the MAN pushbutton backlight is ON 1.3 Adjust the output using the slide bar at the bottom of the controller as ATC directed by an approved procedure or by the SM/CRS 2.0 Shifting to Remote/Automatic Mode 2.1 IF RCN-LIC-110, Pressurizer Level Control, is in AUTO, THEN press ATC the MAN pushbutton ATC 2.2 Check the MAN pushbutton backlight is ON 2.3 Place the Remote/Local Automatic Mode Select switch to R ATC (Remote)

ATC 2.4 Ensure switch travels fully to R (Remote) 2.5 WHEN BOTH of the following:

Pressurizer Level (Red pointer) is approximately equal to the Remote Setpoint (Black and white pointer)

ATC Letdown flow is sufficient to maintain Pressurizer Level at the Remote Setpoint THEN press the AUTO pushbutton ATC 2.6 Check the AUTO pushbutton backlight is ON 2.7 Adjust the Local/Automatic setpoint (Black pointer) using the ATC thumbwheel as directed by an approved procedure or by the SM/CRS.

3.0 Shifting to Local/Automatic Mode Procedure Caution: Circuitry for shifting RCN-LIC-110 between the Remote/Local Auto modes involves a break before make switch. Directly shifting between these modes without going through the MANUAL mode can affect controller output.

3.1 Adjust the Local/Automatic setpoint (Black pointer) to match the ATC Remote setpoint (Black and white pointer) using the thumbwheel 3.2 IF RCN-LIC-110, Pressurizer Level Control, is in AUTO, THEN press ATC the MAN pushbutton ATC 3.3 Check the MAN pushbutton backlight is ON ATC 3.4 Place the Remote/Local Automatic Mode Select switch to L (local)

ATC 3.5 Ensure the switch travels fully to L (local)

ATC 3.6 Press the AUTO pushbutton PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 4 Page 26 of 36 Event

Description:

RRS THOT fails high Time Position Applicants Actions or Behavior ATC 3.7 Check the AUTO pushbutton backlight is ON PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 5 Page 27 of 36 Event

Description:

Inadvertent Train B MSIS Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 5, Inadvertent Train B MSIS Indications Available:

MSIS alarm on B05 MSIVs closing Rising SG pressures Loss of feed flow Examiner Note: The following steps are from 40AO-9ZZ17, Inadvertent PPS-ESFAS Actuations Driver Note: If the crew decides to manually trip the reactor, or the reactor automatically trips, immediately INITIATE Key 6, Loss of Offsite Power.

CRS 1. Enter AOP Entry Time and Date

2. IF Reactor Power is greater than 5%, AND ANY of the following conditions exist:

MSIVs close FWIVs close THEN perform the following:

a. Trip the reactor.
b. GO TO 40EP-9EO01, Standard Post Trip Actions.

2.1 IF Shutdown Cooling is in service, THEN perform the following:

a. IF ANY Wet Lay-up Recirc Pump(s) are running, THEN direct an operator to open ANY of the following breakers for the running pump(s).

SGN-P01A

  • NHN-M1311, Wet Layup Recirc Pump SGN-P01A SGN-P01B
  • NHN-M1006, Wet Layup Recirc Pump SGN-P01B
b. GO TO step 6.
3. IF both MSIVs closed on any Steam Generator, THEN operate ADVs BOP as needed to maintain Steam Generator pressures within the desired band.

Examiner Note: The crew will operate two ADVs (one per SG) to reestablish steaming. In order to open each ADV, they will have to place the two permissive handswitches below the ADV controller to open permissive, dial the thumbwheel on the ADV controller to ~ 30% to get the ADV off its closed seat, and then adjust the thumbwheel to the desired position.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 5 Page 28 of 36 Event

Description:

Inadvertent Train B MSIS Time Position Applicants Actions or Behavior

4. IF feedwater is isolated to any Steam Generator, THEN ensure SG feed is established using ANY of the following:

BOP AFB-P01 AFA-P01 Examiner Note: In order to feed both SGs with AFB-P01:

Start AFB-P01 using the pump handswitch Open UV-34, Aux FW to SG1 Downstream Valve Throttle open UV-30, Aux FW to SG1 Upstream Valve Open UV-35, Aux FW to SG2 Downstream Valve Throttle open UV-31, Aux FW to SG2 Upstream Valve

5. IF the Condenser Reheat Tray level is in the indicating range locally (CDN-LG-88 & 89),THEN override and open BOTH of the following:

SGA-HS-1133, Steam Trap SGN-M23 Inlet Isolation Valve UV-1133 SGA-HS-1134, Steam Trap SGN-M24 Inlet Isolation Valve UV-1134

6. Perform the following:
a. PERFORM Appendix C, PPS-ESFAS Check (attachment C-10, MSIS Train B), steps 2. and 3. to check that equipment actuated as expected.

ATC

b. Document components that failed to actuate in the Control Room Log.
c. Ensure compliance with Technical Specifications for components that failed to actuate or were overridden.
7. Ensure compliance with BOTH of the following:

CRS LCO 3.3.5, ESFAS Instrumentation LCO 3.3.6, ESFAS Logic & Manual Trip Technical Specifications: Due to the inadvertent MSIS, LCO 3.3.6, ESFAS Logic and Manual Trip, Condition D o Restore inoperable channel to OPERABLE within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Examiner Note: When the crew has restored feed water to at least one SG, commenced steaming with ADVs, and the CRS has addressed Tech Specs, or at Lead Evaluators discretion, proceed to Event 6, Loss of Offsite Power.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 29 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 6, Loss of Offsite Power Indications Available:

Loss of non-class loads Reactor trip Loss of RCPs Examiner Note: The following steps are from 40EP-9EO01, Standard Post Trip Actions CRS 1. Open the placekeeper and enter the EOP entry time.

2. Determine if Reactivity Control acceptance criteria is met:

BOP Check that reactor power is dropping.

BOP Check that start-up rate is negative.

BOP (check Check that ALL full strength CEAs are inserted.

CEAs (CA) Borate the RCS until adequate SDM as required by Tech inserted) Specs is established using ANY of the following:

Appendix 103, RCS Makeup/Emergency Boration ATC Appendix 10, Charging Pump Alternate Suction to the RWT /

(Emergency Restoration borate) Appendix 11, Charging Pump Alternate Suction to the SFP /

Restoration SI flow Critical Task # 1: Commence borating to the RCS at a rate of 26 gpm within 15 minutes of the reactor trip due to less than all full-strength CEAs being fully inserted.

Time of Trip (start time): __________

Boration commenced: ___________

SAT / UNSAT Examiner Note: Normally, the emergency boration would be completed using Appendix 103-A, however since the Boric Acid Flow Controller is de-energized, the RO will use another section of Appendix 103. Most likely choice will be Appendix 103-D. The steps from 103-D are listed below:

ATC 1. Ensure that CHE-HV-532, RWT to Boric Acid Makeup Pumps, is open.

ATC 2. Place CHN-HS-527, VCT Bypass, in the CLOSE position.

ATC 3. Ensure CHN-FIC-210X, Reactor Makeup Water to VCT Flow Control, is in manual with 0% output.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 30 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior ATC 4. Place CHN-HS-210, Makeup Mode Select Switch, in MANUAL.

ATC 5. Ensure the BAMPs are stopped.

ATC 6. Open CHE-HV-536, RWT to Charging Pumps.

ATC 7. Close CHN-UV-501, Volume Control Tank Outlet.

ATC 8. IF one Charging Pump is running, AND the second pump will be started, THEN perform the following:

Ensure at least 20 seconds since last pump start or suction valve manipulation.

Start the second Charging Pump.

9. When it is desired to restore charging pump suction to the VCT, THEN perform the following:

Open CHN-UV-501.

Close CHE-HV-536.

Examiner Note: The step below is the continuation of verifying Reactivity Control acceptance criteria is satisfied.

Check that the Main Turbine is tripped.

3. Determine if Maintenance of Vital Auxiliaries acceptance criteria is met:

Check that the Main Generator output breakers are open.

Examiner Note: The Main Generator breakers are closed, however since the Motor Operator Disconnect (MOD) is open, the Main Generator Output breakers do not need to be opened. The breakers are closed to re-ring the bus for enhanced reliability when the main generator is not online.

BOP Check that station loads have transferred to offsite electrical power such that BOTH of the following conditions are met:

All vital and non-vital AC buses are powered All vital and non-vital DC buses are powered (CA) IF PBA-S03 or PBB-S04 is NOT powered from offsite, THEN perform the following:

Ensure that the associated DG has started.

Ensure that the associated DG output breaker is closed.

Refer to Supplemental SPTA Actions (DG Running With Output Breaker Open) - Hard Card.

Examiner Note: The following steps are from the Supplemental SPTA Actions Hard Card PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 31 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior BOP Check BOTH of the following:

DG frequency between 59.9 - 60.5 Hz DG voltage between 4080 - 4300 V BOP Ensure BOTH of the following supply breakers on the affected bus are open (B01):

Normal supply breaker Alternate supply breaker BOP Check all three supply breaker 86-lockout relays on the affected bus are reset.

BOP IF the associated DG is at rated speed and voltage, AND its output breaker is still open, THEN perform the following:

(Local action Place the associated synchronizing switch to ON.

to stop EDG) Close the associated DG output breaker (CA) IF the associated DG output breaker can NOT be closed, THEN direct an operator to emergency stop the associated DG.

Place the associated synchronizing switch to OFF.

Driver Cue: When called to emergency stop the B EDG, wait 30 seconds and INITIATE Key 31.

Examiner Note: The following steps are the continuation of SPTAs

4. Determine if RCS Inventory Control acceptance criteria is met:

ATC Check that pressurizer level meets BOTH of the following:

10 - 65%

Trending as expected to 33 - 53%

ATC Check that the RCS is 24°F or more subcooled.

ATC Check that BOTH of the following are in service to all RCPs:

Seal injection Nuclear Cooling Water (CA) Isolate controlled bleedoff from ANY RCP(s) as appropriate. REFER TO 40AO-9ZZ04, Reactor Coolant Pump Emergencies, Appendix E, Control Board B04 Label.

Examiner Note: The ATC should close CHB-UV-505, CHA-UV-506, and CHA-HV-507 to isolate controlled bleedoff.

5. Determine if RCS Pressure Control acceptance criteria is met:

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 32 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior ATC Check BOTH of the following:

Pressurizer pressure is 1837 - 2285 psia Pressurizer pressure is trending as expected to 2225 - 2275 psia (CA) Restore and maintain pressurizer pressure to the normal control band by any of the following:

Operation of PPCS Manual operation of pressurizer heaters and spray valves Critical Task # 2: Operate Auxiliary Spray and/or ADVs as necessary to prevent lifting primary safety valves.

No start or stop time since this step is continually applicable.

SAT / UNSAT

6. Determine if Core Heat Removal acceptance criteria is met:

ATC Check ALL of the following:

At least one RCP is operating Loop T is less than 10°F RCS is 24°F or more subcooled

7. Determine if RCS Heat Removal acceptance criteria is met:

BOP Check that at least one SG meets BOTH of the following conditions:

Level is 35% WR or more Feedwater is restoring or maintaining level 45 - 60% NR (CA) Restore and maintain level in at least one SG 45 - 60%

NR Examiner Note: AFN-P01 will trip 8 minutes after the reactor trip. This may or may not happen prior to addressing RCS Heat Removal. If the pump has not yet tripped, this step may be revisited, however the crew will not be able to restore feed until transitioning to the Functional Recovery procedure.

BOP Check that Tcold is 560 - 570°F (CA) IF Tcold is greater than 570°F, then perform the following:

Ensure that feedwater is being restored to at least one SG Restore Tcold to 560 - 570°F using SBCS or ADVs PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 33 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior BOP Check that SG pressure is 1140 - 1200 psia (CA) IF SG pressure drops to the MSIS setpoint, THEN ensure MSIS has actuated (CA) IF SG pressure is less than 1140 psia, THEN perform the following:

Ensure the SBCS valves are closed Ensure the ADVs are closed IF SG pressure is greater than 1200 psia, THEN restore and maintain SG pressure to less than 1200 psia using SBCS or ADVs

8. Determine if Containment Isolation acceptance criteria is met:

ATC Check that containment pressure is less than 2.5 psig ATC Check BOTH of the following conditions:

No valid containment area radiation monitor alarms or unexplained rise in activity No valid steam plant activity monitor alarms or unexplained rise in activity

9. Determine if Containment Temperature and Pressure Control acceptance criteria are met:

ATC Check that containment temperature is less than 117°F (CA) IF containment temperature is 117°F or more, AND a SIAS has NOT actuated, THEN ensure that ALL of the available systems are in operation:

Containment Normal ACUs CEDM ACUs Reactor Cavity Fans PZR Cooling Fans ATC Check that containment pressure is less than 2.5 psig Examiner Note: The CRS should diagnose a Loss of Feedwater event is in progress with the success path being to cross-tie class power in order to restore feedwater. This requires entry into the Functional Recovery procedure.

The following steps are from 40EP-9EO09, Functional Recovery CRS 1. Ensure the event is being classified.

CRS 2. Enter the EOP entry time.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 34 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior

3. IF pressurizer pressure remains below the SIAS setpoint, THEN perform the following:

Ensure ONE RCP is stopped in each loop.

IF RCS subcooling is less than 24°F, THEN ensure all RCPs are stopped.

4. IF any RCPs are operating, THEN perform Appendix 16, RCP Trip Criteria and check RCP operating limits satisfied.

BOP 5. Perform the following:

Ensure that the Steam Generator Sample Valves are open.

Direct Chemistry to perform 74DP-9ZZ05, Abnormal Occurrence Checklist.

ATC 6. Place the Hydrogen Analyzers in service.

Examiner Note: Only the Train A Hydrogen Analyzer will be placed in service due to the loss of PBB-S04.

CRS 7. Identify the success path(s) to be used to satisfy each safety function.

REFER to BOTH of the following:

Section 4.0, Safety Function Tracking Section 6.0, Resource Assessment Trees Examiner Note: The CRS should jeopardize MVAC-2, DGs, and HR-1, SG with no SI CRS 8. Perform Section 5.0, Safety Function Status Check for those success paths in use.

CRS 9. Perform ALL of the following in the order listed:

Success path instructions for those safety functions that are in jeopardy Success path instructions for those safety functions that are challenged Success path instructions for all other non-shaded paths in use Examiner Note: The following steps are from MVAC-2, DGs CRS 1. Open the placekeeper

2. IF at least one vital 4.16 kV AC bus is energized from a SBOG, THEN GO TO step 9 CRS 3. IF one vital 4.16 kV AC bus is energized from a Diesel Generator, AND the equipment needed to maintain Safety Functions is NOT available on the energized bus, THEN GO TO step 11.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 35 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior ATC 11. IF one vital 4.16 kV AC bus is energized by its Diesel Generator, AND vital AC powered equipment needed to maintain Safety Functions is NOT available on the energized bus, THEN perform ONE of the following:

Appendix 58, Cross-Tie DG B to PBA-S03 Appendix 59, Cross-Tie DG A to PBB-S04 Examiner Note: The following steps are from Appendix 59, Cross-Tie DG A to PBB-S04 ATC 1. Direct an operator to perform Attachment 59-A, Disable PBB-S04 Breakers Driver Action: When directed to perform Attachment 59-A, run the 59-A scenario and pause the scenario when all of the 125 VDC control power breakers are open. After notifying the control room that the breakers are disabled, continue the 59-A scenario. Report that attachment 59-A is complete when the scenario has finished executing.

ATC 2. Ensure that ALL of the following breakers are open:

NAN-S03A PBA-S03K PBA-S03L NAN-S04A PBB-S04L PBB-S04K ATC 3. Ensure that PBB-S04B, Diesel Generator B 4.16 kV Breaker, is open ATC 4. Place ALL of the following in PULL TO LOCK:

Train B Containment Normal ACUs Train B CEDM ACUs ATC 5. Perform the following:

Place synchronizing switch PBA-SS-S03L, 4.16 kV Bus S03 Normal Supply, to ON Close breaker PBA-S03L, 4.16 kV Bus S03 Normal Supply Place synchronizing switch PBA-SS-S03L to OFF PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 1 Event # 6, 7, 8, 9 Page 36 of 36 Event

Description:

Loss of Offsite Power, Stuck CEA, Loss of Train B 4kV Bus PBB-S04, AFN-P01 Shaft Shear - Loss of Feedwater/Functional Recovery Time Position Applicants Actions or Behavior ATC 6. When informed by the area operator that the PBB-S04 breakers are disabled, THEN perform the following to close PBB-S04L from the Control Room:

Place synchronizing switch PBB-SS-S04L, 4.16 kV Bus S04 Alternate Supply, to ON Close breaker PBB-S04L, 4.16 kV Bus S04 Alternate Supply Place synchronizing switch PBB-SS-S04L to OFF ATC 7. WHEN PBB-S04 is energized, THEN direct an operator to ensure that ANY of the breakers for the battery chargers that were initially aligned to the Train B 125 V DC buses are ON and that the main contactors are closed:

PHB-M3627, Battery Charger B E-PKB-H12 PHB-M3209, Battery Charger D E-PKD-H14 PHB-M3425, Battery Charger BD E-PKB-H16 ATC/BOP 8. Perform the following:

Stop non-essential loads on PBA-S03 Reset and start loads on PBB-S04 as required Critical Task # 3: Restore power to Train B Class 4kV bus PBB-S04 prior to exiting MVAC-2, DGs, and restore feed to at least one SG prior to exiting HR-1, SG with no SI.

SAT / UNSAT Examiner Note: In order to restart AFB-P01, the operator will have to take the handswitch to the STOP position to reset the 86 lockout on the breaker, and then start the pump by taking the handswitch to START.

Scenario Termination: When the crew has restarted AFB-P01 and reinitiated feed flow to at least one SG, or at lead evaluators discretion, the scenario may be terminated.

PVNGS 2016 NRC Exam Scenario # 1 Rev 4

Appendix D Scenario Outline Form ES-D-1 Facility: PVNGS Scenario No.: 2 Op Test No.: 2016 NRC Exam Examiners: Operators:

Initial Conditions: 100% power, MOC, AFA-P01 OOS Turnover: Maintain steady state operations, transfer house loads from the unit aux transformers to the startup transformers.

Event No. Malf. Event Type* Event Description No.

1 N (ATC) Transfer of House Loads from Unit Aux Xfmr to S/U Xfmrs 2 I (CRS, BOP) SG level transmitter fails to 53%

3 C (CRS, BOP, Inadvertent Train B CSAS ATC)

TS (CRS) 4 R (BOP, ATC) CEA 66 drop C (CRS)

TS (CRS) 5 M (ALL) ESD inside containment 6 C NAN-S01 and NAN-S02 normal supply breakers 86LO on reactor trip.

7 C (BOP) SIAS/CIAS/MSIS fail to auto actuate 8 C Train A CS Flow Control Valve SIA-UV-672 seized closed 9 M (ALL) Train B CS Pump sheared shaft

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor, (TS)Technical Specifications Actual Target Quantitative Attributes 8 Total malfunctions (5-8) 4 Malfunctions after EOP entry (1-2) 3 Abnormal events (2-4) 2 Major transients (1-2) 2 EOPs entered/requiring substantive actions (1-2) 1 EOP contingencies requiring substantive actions (0-2) 3 Critical tasks (2-3)

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 2016 NRC Exam Scenario 2 Overview Event 1 To support maintenance, transfer house loads from the Unit Aux Transformer to the Start-up Transformers. This is accomplished by energizing NAN-S01 from NAN-S03, and NAN-S02 from NAN-S04.

Event 2 SG #2 level transmitter LT-1122 will fail to 53%. The DWFCS will respond by reducing feed flow to SG #2 in an effort to lower level to the setpoint of 50%. The crew will take action per the ARP to place the faulty transmitter in maintenance, and restore SG level to the normal program band.

Event 3 An inadvertent CSAS will occur on Train B. The crew will enter 40AO-9ZZ17, Inadvertent PPS-ESFAS Actuations, to stop the CS pump, close the CS flow control valve and restore NC flow to containment. The CRS will address TS for the actuation and the containment isolation valves which were overridden and opened in response to this event.

Event 4 CEA 66 will fall to the bottom of the core. The crew will enter 40AO-9ZZ11, CEA Malfunctions, and commence a power reduction within 10 minutes. The crew will continue the power reduction to comply with the Core Operating Limits Report by reducing turbine load and commencing a boration.

Event 5 An ESD will occur inside containment. The crew will trip the reactor and enter 40EP-9EO01, Standard Post Trip Actions.

Event 6 On the trip, NAN-S01 and NAN-S02 supply breakers will trip resulting in a loss of all 4 RCPs and several non-class loads. Additional impacts to this loss are the loss of instrument air compressors and power to the Controlled Bleedoff Valves. This will required the crew to isolate bleedoff using the containment isolation valves and will have to override and reopen Instrument air to containment valve IAA-UV2 in order to maintain bleedoff isolated.

Event 7 SIAS/CIAS/MSIS will all fail to auto actuate at either 3.1 psig in containment or 960 psia SG pressure. The crew will manually actuate all 3 ESFAS actuations (unless SIAS and CIAS auto actuate at 1837 psig RCS pressure before the manual actuations are performed) which will result in the BOP having to transition to AFB-P01 for feeding and ADVs for steaming. SIAS and CIAS will auto actuate if RCS pressure lowers to 1837 psig, which will occur after 3 psig in the containment is reached. The main event here is the complete failure of MSIS to actuate.

Event 8 When containment pressure reaches 8.5 psig, CSAS will actuate. The crew will have to recognize that the Train A CS flow control valve is seized shut and the B CS Pump will not auto start due to actions taken in the earlier inadvertent CSAS. The crew will have to manually start the B CS Pump and open the B CS flow control valve. Additionally, the crew will have to manually close the Train B NC containment isolation valves which were overridden open in during the inadvertent CSAS earlier in the scenario.

Event 9 5 minutes after the reactor trip, the B CS Pump shaft will shear. The crew will have to recognize that they no longer meet the safety function for containment temperature and pressure control. The CRS will transition to the Functional Recovery procedure due to no containment spray flow and direct aligning the Train B LPSI Pump to the Train B CS header to regain spray flow into containment.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 Critical Task # 1: When the Main Steam Isolation setpoints are exceeded, ensure Main Steam Isolation has actuated prior to automatic AFAS actuation.

Safety Significance: MSIS ensures acceptable consequences during an MSLB or FWLB (between the steam generator and the main feedwater check valve) either inside or outside containment. If the AFAS actuates prior to the MSIS, the inventory of the Condensate Storage Tank may also begin to flow out the steam break. MSIS isolates both steam generators if either generator indicates a low pressure condition or a high level condition or if a high containment pressure condition exists. This prevents an excessive rate of heat extraction and subsequent cooldown of the RCS during these events.

Cueing: The crew should recognize the failure of MSIS to actuate when containment pressure exceeds 3.1 psig OR when either SG pressure lowers to less than 960 psia (both are setpoints for MSIS).

Measurable Performance Indicator: The crew will have to manually actuate MSIS by taking the four handswitches for each ESFAS channel actuation (on B05) to the actuate position. This can be confirmed by the red MSIS lights on the vertical section of B05 as well as the actuation logic lights for each actuation extinguishing on the horizontal section of B05. The AFAS actuation will occur at 25.2%

wide range in either SG and will be indicated by the red AFAS-1 (or AFAS-2) light on the vertical section of B05.

Performance Feedback: The crew will have indication of successful actuations by observing the red SIAS/CIAS/MSIS lights on the vertical section of B05 as well as the actuation logic lights for each actuation extinguishing on the horizontal section of B05, as well as by observing the actuated equipment for each ESFAS actuation going to its actuated position.

Critical Task # 2: Following a plant overcooling event, stabilize RCS Temperature and operate Safety Injection to prevent lifting the primary safeties.

Safety Significance: Following an ESD and subsequent SI injection into the RCS, if RCS temperature is not stabilized when the affected SG reaches dryout conditions, the subsequent heat up and repressurization will create a potential for PTS as well as raise RCS pressure to the point where primary safety valves lift, challenging the RCS inventory and pressure control safety functions.

Cueing: SG dryout will be indicated by a rise in affected loop Tcold and pressure in the affected SG approaching containment pressure. At this point, the crew should set and maintain a pressure band in the unaffected SG corresponding to the lowest Tcold reached in the affected RCS loop, +/- 50 psig.

Measurable Performance Indicator: When the crew identifies dryout in the affected SG, they will lower and maintain pressure in the unaffected SG at saturation pressure for the lowest Tcold observed in the affected loop, and/or by throttling SI flow to minimize the addition of inventory to the RCS. This critical task is satisfactory if pressure is controlled in the unaffected SG such that primary safeties remain closed.

Performance Feedback: The crew will have indication of RCS Tcold and pressurizer pressure being PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 stabilized and under control. SG dryout will be indicated primarily based on Tcold starting to rise in the affected loop as well as affected SG pressure approaching containment pressure. The status of primary safety valves can be observed using the safety valve position indicators on B04 as well as by observing primary pressure < 2475 psig.

Critical Task # 3: Align LPSI for CS to restore the CTPC safety function within 30 minutes of entering 40EP-9EO09, Functional Recovery.

Safety Significance: Failure to maintain containment temperature and pressure control reduces margin to the design of the containment building, which provides a barrier to fission product release to the general public.

Cueing: The crew will recognize the failure of the Train A CS flow control valve and the sheared shaft on the B CS Pump, resulting in zero CS flow.

Measurable Performance Indicator: The crew will align the B LPSI pump to the B CS header and start the LPSI Pump to initiate CS flow. Flow will not be indicated on the CS flow transmitter and will be verified using trends on containment pressure to validate adequate flow.

Performance Feedback: The crew will validate LPSI is providing adequate CS flow by observing a lowering trend of containment pressure using the ERFDADS computer terminal.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 Turnover Plant Conditions:

100% power, MOC, 250 EFPD.

PC Cleanup is NOT recirculating the RWT.

Unit 2 is supplying the Aux Steam cross-tie header.

Equipment Out of Service:

AFA-P01 is OOS for bearing replacement.

Expected return to service is 12-16 hours.

LCO 3.7.5, Auxiliary Feedwater System, Conditions A and B were entered 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> ago.

Risk Management Action Level is ORANGE.

Planned Shift Activities:

Transfer NAN-S01 to NAN-S03 per 40OP-9NA03, Section 6.19, Transferring NAN-S01 to NAN-S03, and transfer NAN-S02 to NAN-S04 per 40OP-9NA03, Section 6.24, Transferring NAN-S02 to NAN-S04.

Prerequisites have been completed for both sections and the procedures have been filled out accordingly.

Maintain steady state conditions for the remainder of the shift.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 DRIVER INSTRUCTIONS for SIMULATOR SETUP RESET to IC-20 and run Scenario 2016 NRC Scenario 2 EVENT TYPE MALF # DESCRIPTION DEMAND INITIATOR VALUE 1 None None Transfer NAN-S01 and NAN-S02 None None to Offsite power 2 CM TRFW04SGNLT1122_1 SG Level Transmitter LT-1122 53 Key 2 fails to 53%

3 MF RP06H1 Inadvertent Train B CSAS Actuate Key 3 RP06H2 4 MF RD02I CEA 66 Drops to bottom of core 100 Key 4 5 MF MS01B ESD inside containment (5 10 Key 5 minute ramp) 6 CM BKED04NANS01A_5 NAN-S01 supply breaker trip Trip Rx trip CM BKED05NANS02A_5 NAN-S02 supply breaker trip Trip Rx trip 7 CM BSRP01BSSG1PRLOAT_1 SIAS/CIAS/MSIS fail to auto Fail to auto Setup actuate actuate CM BSRP01BSSG1PRLOBT_1 CM BSRP01BSSG1PRLOCT_1 CM BSRP01BSSG1PRLODT_1 CM BSRP01BSSG2PRLOAT_1 CM BSRP01BSSG2PRLOBT_1 CM BSRP01BSSG2PRLOCT_1 CM BSRP01BSSG2PRLODT_1 CM BSRP01BSCNTPRHIAT_1 CM BSRP01BSCNTPRHIBT_1 CM BSRP01BSCNTPRHICT_1 CM BSRP01BSCNTPRHIDT_1 8 CM MVRH03SIAUV672_6 Train A CS Flow Control Valve Seized Rx trip SIA-UV-672 seized closed 9 CM CPRH05SIBP03_1 Train B CS Pump sheared shaft Sheared Rx trip (5 minute delay)

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Scenario Event Description NRC Exam Scenario # 2 Driver Setup:

RESET to IC-20 Run 2016 NRC Scenario 2 event file Run AFA-P01 OOS Scenario file Place OOS tags on AFA-P01 Ensure the Simulator Parameter Recording Task is initiated PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 1 Page 8 of 31 Event

Description:

Transfer NAN-S01 and NAN-S02 to Off-Site Power Time Position Applicants Actions or Behavior Examiner Note: The following steps are from 40OP-9NA03, 13.8kV Electrical System (NA),

starting on step 6.19.8.

ATC 8. Place Synch Switch NAN-SS-S03B, 13.8 kV Bus S03 - S01 Tie, in ON ATC 9. Check for proper synchronization by observing the Synchroscope needle is in approximately the 12 oclock position.

ATC 10. Take handswitch NAN-HS-S03B, 13.8 kV Bus S03 - S01 Tie, to CLOSE.

ATC 11. Check NAN-S01A, 4.16 kV S01 Supply Breaker, automatically opens.

ATC 12. Check NAN-S01, 13.8 kV Bus S01, voltage is between 12.42 kV and 14.49 kV.

ATC 13. Place Synch Switch NAN-SS-S03B, 13.8 kV Bus S03 - S01 Tie, in OFF.

ATC 14. Remove the key from Synch Switch NAN-SS-S03B.

Examiner Note: The following steps are from 40OP-9NA03, 13.8kV Electrical System (NA),

starting on step 6.24.8.

ATC 8. Place Synch Switch NAN-SS-S04B, 13.8 kV Bus S04 - S02 Tie, in ON.

ATC 9. Check for proper synchronization by observing the Synchroscope needle is in approximately the 12 oclock position.

ATC 10. Take handswitch NAN-HS-S04B, 13.8 kV Bus S04 - S02 Tie, to CLOSE.

ATC 11. Check NAN-S02A, 4.16 kV S02 Supply Breaker, automatically opens.

ATC 12. Check NAN-S02, 13.8 kV Bus S02, voltage is between 12.42 kV and 14.49 kV.

ATC 13. Place Synch Switch NAN-SS-S04B, 13.8 kV Bus S04 - S02 Tie, in OFF.

Examiner Note: Once NAN-S01 and NAN-S02 have been transferred, proceed to Event 2, SG2 Level transmitter LT-1122 fails to 53%.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 2 Page 9 of 31 Event

Description:

SG 2 Level Transmitter LT-1122 fails to 53%

Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 2, LT-1122 fails to 53%

Indications Available:

Lowering level in SG # 2 Annunciator 6A06A, FWCS PROCESS TRBL alarm Examiner Note: The following steps are from 40AL-9RK6A, window 6A06A

1. Check BOTH of the following for SG 1 at DFWCS to validate the alarm:

BOP LT-1111, SG 1 Level Transmitter LT-1112, SG 1 Level Transmitter

2. Check BOTH of the following for SG 2 at DFWCS to validate the alarm:

BOP LT-1121, SG 2 Level Transmitter LT-1122, SG 2 Level Transmitter

3. IF BOTH of the following conditions exist:

SG level deviation is NOT attributed to a failed instrument SG high rate blowdowns are in progress THEN exit this alarm response Procedure Caution: When actual SG level is less than the controlling setpoint, placing the faulty level transmitter in Maintenance may result in an overpower event

4. IF BOTH of the following conditions exist:

The deviation is the result of an actual low SG level The SM/CRS determines the low level condition may result in an overpower event THEN perform the following at DFWCS:

BOP Place the faulty level transmitter in Maintenance Lower the affected SG level setpoint to match the actual indicated level on the valid level transmitter for the affected SG Raise the affected SG level slowly to the setpoint for the unaffected SG Reset the DFWCS alarm on the Process Alarm page Procedure Note: Raising the affected SG level in a controlled slow manner will minimize the potential for an overpower transient

5. Place the faulty level transmitter in Maintenance
6. Reset the DFWCS alarm on the Process Alarm page BOP 7. Initiate a PVAR for I&C to troubleshoot and correct the problem.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 2 Page 10 of 31 Event

Description:

SG 2 Level Transmitter LT-1122 fails to 53%

Time Position Applicants Actions or Behavior

8. WHEN the faulted instrument has been restored, THEN restore all DFWCS in the correct selection for the current plant conditions as directed by the SM/CRS Examiner Note: When the failed transmitter has been placed in maintenance and the crew is restoring SG level, or at lead evaluators discretion, proceed to EVENT 3, Inadvertent Train B CSAS.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 3 Page 11 of 31 Event

Description:

Inadvertent Train B CSAS Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 3, Inadvertent Train B CSAS Indications Available:

CSAS alarm on B05 Starting of Train B actuated CSAS equipment Examiner Note: The following steps are from 40AO-9ZZ17, Inadvertent PPS-ESFAS Actuations CRS 1. Enter AOP entry time and date CRS 2. Record the time of the CSAS actuation Procedure Note: Overriding or antipumping equipment disables automatic operation of the equipment on a valid PPS-ESFAS actuation. Depending on plant conditions, this action may make the equipment inoperable.

3. IF ANY Containment Spray Pump is running, AND BOTH of the following conditions exist:

Containment Spray Pump is NOT being used for SDC ATC SIAS has NOT actuated THEN place the Containment Spray Pump hand switch in STOP to anti-pump the CS Pump

4. IF ANY Containment Spray Pump is running, AND BOTH of the following conditions exist:

Containment Spray Pump is NOT being used for SDC SIAS has actuated THEN override and stop the Containment Spray Pump Procedure Caution: Attempting to close the Containment Spray Header Isolation Valves while the valves are stroking to their actuated position may trip the valve breaker on overload and allow continued spray flow by gravity drain.

ATC 5. Override and close all open Containment Spray Header Isolation Valves Procedure Note: Opening the NC Containment Supply Isolation Valve prior to opening the NC Containment Return Isolation Valves may result in lifting the NC reliefs in Containment.

6. Open ANY of the following as needed to restore Nuclear Cooling Water to Containment:

BOP NCA-UV-402, NCW Containment Downstream Return Isolation Valve NCB-UV-403, NCW Containment Upstream Return Isolation Valve NCB-UV-401, NCW Containment Upstream Supply Isolation Valve PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 3 Page 12 of 31 Event

Description:

Inadvertent Train B CSAS Time Position Applicants Actions or Behavior

7. IF seal injection is NOT in service, AND cooling water is NOT restored to ANY operating RCP within three minutes of the initial loss, THEN perform the following:

Ensure the reactor is tripped Stop all of the RCPs Isolate controlled bleedoff Examiner Note: The 10 minute clock starts when the RCP LO NC FLOW alarms come in on B04 (loud green alarms on the upper left hand corner of B04 - panels 4KA-UA-4D and RKA-UA-4E) and stops when both alarms are clear.

8. IF seal injection is in service AND cooling water is NOT restored to ANY operating RCP within 10 minutes of the initial loss, THEN perform the following:

CRS Ensure the reactor is tripped Stop all of the RCPs Isolate controlled bleedoff

9. IF IAA-UV-2, Outside Containment Isolation Valve, has closed, THEN perform the following:

IF ANY of the following valves have failed closed, THEN place their hand switches to CLOSE:

Letdown to Regen HX Isolation Valves CHA-UV-516 CHB-UV-515 Blowdown Containment Isolation Valves SGA-UV-500P SGB-UV-500R Override and open IAA-UV-2 Ensure PZR Sprays are operating to control PZR pressure

10. IF letdown is isolated, THEN perform the following:

Ensure no more than one Charging Pump is running Perform 40AO-9ZZ05, Loss of Charging or Letdown

11. If Containment is accessible, THEN perform the following:

Direct RP/Containment Coordinator to evacuate Containment Announce the following over the plant communications systems:

Attention all personnel, attention all personnel, evacuate Containment and follow RP directions PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 3 Page 13 of 31 Event

Description:

Inadvertent Train B CSAS Time Position Applicants Actions or Behavior

12. IF BOTH of the following conditions exist:

ANY Control Room Essential AHUs started ATC It is desired to stop the running Control Room AHUs THEN override and stop the running fans

13. IF RCP Seal Bleedoff isolated to the VCT, THEN override and open the ATC closed RCP Seal Bleedoff Isolation Valves
14. IF Steam Generator Blowdown is isolated, THEN perform the following:

Inform Chemistry that Blowdown is isolated Perform 40OP-9SG03, Operating the Steam Generator Blowdown System to restore Blowdown

15. IF a CS Pump needs to be started and a SIAS has NOT actuated, THEN perform the following:

Inform an operator that the CS Pump breaker will close upon restoration of control power Direct the operator to cycle control power to the CS Pump breaker

16. IF a CS Pump needs to be started AND a SIAS actuated while the CS Pumps were stopped, THEN perform the following:

CRS Place the CS Pump handswitch to START and release the switch Place the CS Pump handswitch to START

17. Perform the following:

Perform Appendix C, PPS-ESFAS Check, steps 2 and 3 to check that equipment actuated as expected ATC Document components that failed to actuate in the Control Room Log Ensure compliance with Technical Specifications for components that failed to actuate or were overridden

18. Ensure compliance with BOTH of the following:

CRS LCO 3.3.5, ESFAS Instrumentation LCO 3.3.6, ESFAS Logic & Manual Trip PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 3 Page 14 of 31 Event

Description:

Inadvertent Train B CSAS Time Position Applicants Actions or Behavior Technical Specifications:

Due to the inadvertent CSAS, LCO 3.3.6, ESFAS Logic and Manual Trip, Condition D o Restore inoperable channel to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.

Due to overriding CSAS actuated containment isolation valves, LCO 3.6.3, Containment Isolation Valves, Condition A o Isolate the affected penetration flowpath by use of at least one closed and deactivate automatic valve, closed manual valve, blind flange, or check valve with flow through the valve secured AND verify the affected penetration flowpath is isolated within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

Due to overriding and stopping the Containment Spray Pump and closing the Spray Flow Isolation valve, LCO 3.6.6, Containment Spray System, Condition A o Restore containment spray train to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

NOTE: May also enter the following for components:

IF the CTMT SUMP EXCESS LEAKAGE alarm comes in (likely),

LCO 3.4.16, Leakage Detection Instrumentation, Condition A IF the Control Room Essential AHU is overridden and stopped, LCO 3.7.11, Control Room Essential Filtration, Condition A IF the Control Room Essential AHU is overridden and stopped, LCO 3.7.12, Control Room Emergency Air, Condition A IF the B HPSI Pump is overridden and stopped, LCO 3.5.3, ECCS - Operating, Condition B IF the B LPSI Pump is overridden and stopped, LCO 3.5.3, ECCS - Operating, Condition A Examiner Note: When the crew has stopped the CS Pump, closed the CS flow control valve, reinitiated NC flow to containment, and the CRS has addressed Technical Specifications, or at lead evaluators discretion, proceed to EVENT 4, CEA 66 drop PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 15 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 4, CEA 66 Drop Indications Available:

CEA 66 fully inserted in core CEA Rod Bottom Light illuminated Lowering power level Examiner Note: The following steps are from 40AO-9ZZ11, CEA Malfunctions CRS 1. Enter AOP entry time and date

2. Check that at least on CEA is deviating from its group by greater ATC than 6.6 inches.
3. If the reactor was NOT critical prior to the CEA deviation, THEN GO TO Appendix F, CEA Deviation Prior To Criticality
4. IF one CEA is deviating from its group by greater than 6.6 inches, AND any CEA Reg Group is below the Transient Insertion Limit, THEN perform the following:

Trip the reactor GO TO 40EP-9EO01, Standard Post Trip Actions

5. IF two or more CEAs are deviating by greater than 9.9 inches from their associated group, THEN perform the following:

Trip the reactor GO TO 40EP-9EO01, Standard Post Trip Actions

6. IF reactor power was less than 1% prior to the CEA deviation, THEN GO TO Appendix G, CEA Deviation Prior to 1% Power ATC 7. Ensure CEDMCS is in STANDBY CRS 8. Direct an operator to perform Appendix E, Initial Actions Driver Cue: If sent to the CEDMCS room to investigate the CEA drop, wait 1 minute and report that the breaker for CEA 66 is tripped-free and a CWP alarm is in on the local alarm panel.

Examiner Note: Appendix E steps are at the end of this section of the scenario guide.

9. Record BOTH of the following:

CRS CEA deviation time Initial (pre-deviation) power level PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 16 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Procedure Note: If the reason for the CEA deviation is known (e.g. ACTM actuation), an attempt to realign the CEA can be made. However due to the time limitations for a power reduction, continuing with the procedure is required until the CEA deviation is less than 6.6 inches.

10. IF the CEA deviation is less than 9.9 inches, AND is can be realigned quickly without requiring troubleshooting, THEN concurrently perform BOTH of the following:

Align the deviated CEA with its group Continue with this procedure until the CEA is aligned

11. IF reactor power is 35% or less, THEN GO TO step 25 Procedure Note: The intent of step 12 is to not require a power reduction if only one CEA has slipped and remains in the top ten inches of the core. If this is the case, the conditions in step 12 are required to be met continuously throughout the event.
12. IF only ONE CEA is misaligned from its group by greater than 6.6 inches, AND ALL of the following conditions are continuously met from the time of the deviation:

All CEAs remain above 142.5 withdrawn by pulse counter All CEAs remain above 140.1 withdrawn by RSPT indication Reactor power is > 95% rated thermal power COLSS is in service All CEACs in service COLSS Azimuthal Power Tilt is less than 3%

THEN GO TO step 25 Procedure Note: The effects of a boration to the RCS may take 4 to 6 minutes to be seen, therefore initiating a boration (step 16) should be done as soon as possible.

13. Perform the following to start a power reduction within 10 minutes of the initial CEA deviation:

BOP Log the start time for power reduction Lower the turbine load to raise Tave 3°F greater than Tref PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 17 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior

14. Determine the required power reduction based on initial power from ONE of the following:

Greater than 80% requires a 20% power reduction CRS Greater than 70% to 80% requires a 15% power reduction Greater than 45% to 70% requires a 10% power reduction Greater than 35% to 45% requires a 5% power reduction

15. Calculate the number of gallons of boric acid needed (STA CRS reactivity worksheet) for the downpower

_____ % X _____ gal/% = _____ gal Examiner Note: The CRS should direct a boration for a 20% power reduction. The STA reactivity worksheet indicates 60 gallons / 1% for a total of 1200 gallons of boric acid.

The steps for the boration from 40OP-9CH01, CVCS Normal Operations, are located at the end of this section.

16. Commence borating to the charging pump suction using BOTH of the following criteria:

ATC Minimum rate of 35 gpm Amount determined in step 15

17. Reduce reactor power to comply with the power reduction CRS requirements of Appendix B, Core Power Reduction After a CEA Deviation
18. WHEN the requirements of Appendix B, Core Power Reduction After a CEA Deviation, allow temperature to be lowered, THEN BOP adjust turbine load to maintain Tave 3°F (+ 0.5 / - 0.0) greater than Tref
19. When CEA realignment can occur, THEN perform Appendix I, CEA realignment Procedure Note: Appendix J, LCO Required Action Tracker, is reference use, and may be performed by the CRS, but should be provided to the SM or STA to be used as a guide to the LCO required actions.

CRS 20. Initiate Appendix J, LCO Required Action Tracker PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 18 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Technical Specifications:

Due to the CEA being misaligned by > 6.6, LCO 3.1.5, CEA Alignment, Condition A o Reduce THERMAL POWER in accordance with the limits in the COLR within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and restore CEA alignment within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

Due to the PDIL alarm circuit being inoperable, LCO 3.1.7, Condition D o Perform SR 3.1.7.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and once every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> thereafter.

Due to LPD being above limits, LCO 3.2.1, Linear Heat Rate, Condition A o Restore LHR to within limits within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

Due to DNBR being above limits, LCO 3.2.4, Departure From Nucleate Boiling Ration (DNBR), Condition A o Restore the DNBR to within limit within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

During the turbine load reduction, Pressurizer level may exceed 56%. If so, LCO 3.4.9, Pressurizer, Condition A o Be in MODE 3 with reactor trip breakers open within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and be in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Examiner Note: When the crew has commenced the boration and the CRS has address Technical Specifications, or at lead evaluators discretion, proceed to Event 5, ESD Inside Containment.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 19 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Examiner Note: The following steps are from 40AO-9ZZ11, CEA Malfunctions, Appendix E, Initial Actions ATC 1. Enter Appendix entry time and date

2. Direct an operator to go to the CEDM Control Room and perform the following:

Report all abnormal indications on the CEDM Control Cabinets ATC Perform 40AL-9SF01, Local Alarm Panel J-SFN-C01D Responses for existing alarms Report all abnormal indications on the MG set control panels Driver Cue: If sent to the CEDMCS room to investigate the CEA drop, wait 1 minute and report that the breaker for CEA 66 is tripped-free and a CWP alarm is in on the local alarm panel.

3. IF the affected control rod is a twelve fingered CEA (REFER TO Appendix A, CEA Information), THEN perform the following:

Monitor the CPC DNBR and LPD margins to trip by using ANY ATC of the following:

Pt IDs 0107 & 0172 Group Display (Dropped/Slipped CEA)

Inform the CRS if a trip value is being approached

4. Inform ALL of the following of the CEA malfunction and obtain assistance as needed:

ATC I&C Maintenance Reactor Engineering SM Procedure Note: The starting point for the subsequent maneuvering plan will be the end point of the COLR driven power reduction (for example, the subsequent downpower plan would start at 80% for a CEA misalignment occurring at full power).

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 20 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior

5. Request from Reactor Engineering situation-specific maneuvering plan(s) to perform a subsequent power reduction required in the event the CEA cannot be restored. The plan(s) will encompass ALL of the following:

The subsequent power reduction will commence no later than 2 ATC hours from the initial CEA misalignment.

IF the subsequent power reduction begins above 50%, THEN power reduction rate will be a minimum of 15% per hour to 50%

power.

WHEN power level is less than 50%, THEN power reduction rate will be a minimum of 10% per hour to 20% power.

6. IF reactor power is greater than 35%, AND a downpower will be performed, THEN initiate pressurizer boron equalization:

ATC Override and energize all pressurizer backup heaters Lower the setpoint on RCN-PIC-100, Pressurizer Pressure Controller, to 2220 psia

7. IF the affected control rod is a Reg Group CEA, THEN perform ATC section 8.4 (PDIL Alarm Circuit) of 40ST-9ZZ23, CEA Position Data Log within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 21 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Examiner Note: The following steps are from 40OP-9CH01, CVCS Normal Operations, Section 6.33, Makeup - Borate Mode

1. Prerequisite - The CVCS is operating per Section 6.1, Establishing ATC Charging and Letdown System Operations
2. Initial Action -

IF an active BAC release permit is in effect for the HUT, THEN ATC notify the Effluent Technician to update the permit Ensure a Reactivity Brief has been conducted Ensure Chemistry has been notified of the intended boration

3. IF the reactor is critical, THEN perform the following:

Determine the gallons of boric acid to be added using ANY of the following:

STA Reactivity Worksheet ATC Reactor Engineering Game Plan Power Change Worksheet Boron OAP Core Data Book Record the required gallons of boric acid

4. IF the reactor is NOT critical, THEN perform the following:

Determine the difference between the desired boron concentration and the actual boron concentration Determine the gallons of boric acid required to obtain the ATC desired boron concentration, using the difference in boron concentration and ONE of the following:

Boron OAP STA Reactivity Worksheet Record the required gallons of boric acid.

5. IF at any time, letdown is diverted to the HUT, THEN notify RP to ATC evaluated the impact on current radiation levels near the HUT PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 22 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior

6. WHEN diverting CVCS letdown, THEN perform the following:

IF ANY of the following conditions exist:

The SM/CRS directs CHN-E03, Gas Stripper, operation Chemistry directs CHN-E03, Gas Stripper, operation THEN direct CVCS letdown to ONE of the following:

ATC CHN-E03, Gas Stripper The EDT IF CVCS letdown will NOT be diverted to CHN-E03, Gas Stripper, OR CVCS letdown will NOT be diverted to the EDT, THEN bypass CHN-E03, Gas Stripper per 40OP-9CH04, Gas Stripper

7. IF automatic makeup to the VCT was disabled in step 6.6.2, AND directed by the SM/CRS, THEN perform the following:

Place CHN-HS-210, Makeup Mode Selector, to AUTO ATC Place CHN-HS-527, Makeup to CHRG PMPS (VCT BYP) VLV UV-527, in OPEN/AUTO Place CHN-FIC-210Y, Boric Acid Make-up to VCT Flow Control, to AUTO per Appendix H - Operation of the Digital Makeup Controllers and Totalizers Procedure Notes:

CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, will operate with flow rates as low as 2 gpm.

Digital makeup will operate satisfactorily at flow rates less than 2 gpm.

The threshold for actuation of 3A04B, CVCS MAKEUP FLOW, is 3 gpm.

The alarm will not activate until flow is greater than or equal to 3 gpm.

The function of 3A04B, CVCS MAKEUP FLOW, is to alert the Control Room Operator that flow exists through CHN-FQIS-210X, Reactor Make-up Water Totalized Flow Control, and/or CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, and is an indication that reactivity management may be in jeopardy.

CHN-FIC-210Y, Boric Acid Make-up to VCT Flow Control, is tuned to provide optimal system response for flows in the 5 gpm to 40 gpm range.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 23 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior Procedure Cautions:

Failure to maintain flow greater than or equal to 3 gpm will prevent 3A04B, CVCS MAKEUP FLOW, from alerting the Control Room Operator that reactivity management is in jeopardy.

Operation of CHN-FIC-210Y, Boric Acid Make-up to VCT Flow Control, in AUTO with an initial controller setpoint of greater than 40 gpm will cause controller instability.

8. Perform the following:

IF the boric acid makeup flow rate is less than 40 gpm, THEN set CHN-FIC-210Y, Boric Acid Make-up to VCT Flow Control, ATC to the boric acid makeup flow rate IF the boric acid makeup flow rate is greater than or equal to 40 gpm, THEN set CHN-FIC-210Y, Boric Acid Make-up Flow Control, to no more than 40 gpm Procedure Note:

A 299 second timer exists. If flow is not achieved within 299 seconds, CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, will receive a Timer Alarm.

9. Set CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, ATC to the required gallons of boric acid as determined in step 6.33.3 or step 6.33.4
10. IF the reactor is critical, THEN ensure CEDMCS is in the mode of ATC operation per SM/CRS direction
11. IF borating directly to the VCT, THEN place CHN-HS-512, Makeup ATC Inlet to VCT VLV UV-512, in OPEN PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 4 Page 24 of 31 Event

Description:

CEA 66 Drop Time Position Applicants Actions or Behavior

12. Perform the following:

Place CHN-HS-210, Makeup Mode Selector, in BORATE Check one BAMP is running IF borating directly to the suction of the Charging Pumps, THEN ensure CHN-UV-527, Makeup to CHRG PMPS (VCT BYP), is open ATC IF END is displayed in the lower left corner, THEN press the END pushbutton on CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control Press the RESET pushbutton on CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, Totalizer/Counter module Press the START pushbutton on CHN-FQIS-210Y, Boric Acid Make-up Totalized Flow Control, Totalizer/Counter module

13. Check CHN-FIC-210X, Reactor Make-up Water to VCT Flow ATC Control, indicates no reactor makeup water flow
14. Check the following occurs on CHN-FIC-210Y, Boric Acid Make-up to VCT Flow Control, Process Flow bar graph:

ATC Flow rises toward the auto setpoint Flow overshoots the auto setpoint Flow stabilizes at the auto setpoint

15. IF the required boric acid makeup flow is greater than or equal to 40 gpm, THEN perform the following:

Ensure CHN-FIC-210Y, Boric Acid Make-up to VCT Flow ATC Control, is selected to AUTO SETPOINT Press the up arrow to raise the setpoint to the required makeup flow valve

16. Monitor ANY of the following for indication of a reactivity change:

Axial Shape Index CEA motion ATC RCS temperature Reactor power Turbine first state pressure PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 25 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Driver: When directed, INITIATE Key 5, ESD Inside Containment Indications Available:

Rising power level Rising Containment pressure and temperature Rising Containment sump levels Examiner Note: The following steps are from 40EP-9EO01, Standard Post Trip Actions CRS 1. Open the placekeeper and enter the EOP entry time.

2. Determine if Reactivity Control acceptance criteria is met:

BOP Check that reactor power is dropping.

BOP Check that start-up rate is negative.

BOP Check that ALL full strength CEAs are inserted.

BOP Check that the Main Turbine is tripped.

3. Determine if Maintenance of Vital Auxiliaries acceptance criteria is met:

ATC Check that the Main Generator output breakers are open.

Check that station loads have transferred to offsite electrical power such that BOTH of the following conditions are met:

ATC All vital and non-vital AC buses are powered All vital and non-vital DC buses are powered Examiner Note: Although the non-vital AC buses are deenergized, there is no contingency action for this in SPTAs.

4. Determine if RCS Inventory Control acceptance criteria is met:

Check that pressurizer level meets BOTH of the following:

10 - 65%

Trending as expected to 33 - 53%

ATC (CA) Restore and maintain pressurizer level to 33 - 53% by ANY of the following:

Operation of PLCS Manual operation of Charging Pumps and Letdown Control Valves ATC Check that the RCS is 24°F or more subcooled.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 26 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Check that BOTH of the following are in service to all RCPs:

Seal injection ATC Nuclear Cooling Water (CA) Isolate controlled bleedoff from ANY RCP(s) as appropriate. REFER TO 40AO-9ZZ04, Reactor Coolant Pump Emergencies, Appendix E, Control Board B04 Label.

Examiner Note: Due to the loss of non-vital power, controlled bleedoff will be isolated using the containment isolation valves, HV-505/506/507. Due to the loss of IA to containment (due to the CSAS), IAA-UV2, Instrument Air to Containment Isolation Valve, will have to be overridden and opened to maintain HV-507 closed as it fails open on a loss of IA.

5. Determine if RCS Pressure Control acceptance criteria is met:

Check BOTH of the following:

Pressurizer pressure is 1837 - 2285 psia Pressurizer pressure is trending as expected to 2225 - 2275 psia (CA) Restore and maintain pressurizer pressure to the normal control band by ANY of the following:

Operation of PPCS ATC Manual operation of pressurizer heaters and spray valves (CA) If pressurizer pressure drops to the SIAS setpoint, THEN ensure that SIAS is actuated (CA) IF pressurizer pressure remains below the SIAS setpoint, THEN stop one RCP in each loop (CA) IF pressurizer pressure drops below the RCP NPSH limits, THEN stop all RCPs. REFER TO Appendix 2, Figures

6. Determine if Core Heat Removal acceptance criteria is met:

Check ALL of the following:

At least one RCP is operating ATC Loop T is less than 10°F RCS is 24°F or more subcooled

7. Determine if RCS Heat Removal acceptance criteria is met:

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 27 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Check that at least one SG meets BOTH of the following conditions:

Level is 35% WR or more BOP Feedwater is restoring or maintaining level 45 - 60% NR (CA) Restore and maintain level in at least one SG 45 - 60%

NR Check that Tcold is 560 - 570°F (CA) IF Tcold is less than 560°F, then perform the following:

Ensure feed flow is not excessive Ensure SG Blowdown is isolated BOP Restore Tcold to 560 - 570°F using SBCS or ADVs IF MSIS has actuated and the cooldown terminates, THEN stabilize Tcold using ADVs IF AFAS has actuated, AND at least one SG level is 10% WR or more, THEN override and throttle Auxiliary Feedwater to maintain Tcold 560 - 570°F Check that SG pressure is 1140 - 1200 psia (CA) IF SG pressure drops to the MSIS setpoint, THEN ensure MSIS has actuated (CA) IF SG pressure is less than 1140 psia, THEN perform the BOP following:

Ensure the SBCS valves are closed Ensure the ADVs are closed (CA) IF SG pressure is greater than 1200 psia, THEN restore and maintain SG pressure to less than 1200 psia using SBCS or ADVs Critical Task # 1: When the Main Steam Isolation setpoints are exceeded, ensure Main Steam Isolation has actuated prior to automatic AFAS actuation.

SAT / UNSAT PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 28 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Critical Task # 2: Following a plant overcooling event, stabilize RCS Temperature and operate Safety Injection to prevent lifting the primary safeties.

SAT / UNSAT

8. Determine if Containment Isolation acceptance criteria is met:

Check that containment pressure is less than 2.5 psig ATC (CA) IF containment pressure is 3 psig or more, THEN ensure CIAS has been initiated Check BOTH of the following conditions:

No valid containment area radiation monitor alarms or unexplained ATC rise in activity No valid steam plant activity monitor alarms or unexplained rise in activity

9. Determine if Containment Temperature and Pressure Control acceptance criteria are met:

Check that containment temperature is less than 117°F (CA) IF containment temperature is 117°F or more, AND a SIAS has NOT actuated, THEN ensure that ALL of the available systems are in operation:

ATC Containment Normal ACUs CEDM ACUs Reactor Cavity Fans PZR Cooling Fans Check that containment pressure is less than 2.5 psig (CA) If containment pressure is 3 psig or more, THEN ensure that CIAS has been initiated (CA) IF containment pressure is 8.5 psig or more, THEN perform the following:

ATC Ensure CSAS is actuated Ensure at least one Containment Spray header flow is greater than 4350 gpm Stop all of the operating RCPs Ensure RCP controlled bleedoff flow is isolated PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 29 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Examiner Note: The CRS should diagnose an ESD inside containment with the CSAS setpoint exceeded and no Containment Spray flow available due to the sheared shaft on the Train B CS Pump and the seized shut CS flow control valve on Train A and transition to the Functional Recovery procedure to align Train B LPSI for containment spray.

The following steps are from 40EP-9EO09, Functional Recovery.

Critical Task # 3: Align LPSI for CS to restore the CTPC safety function within 30 minutes of entering 40EP-9EO09, Functional Recovery.

Functional Recovery Entry Time (Start Time): _________

LPSI aligned for Containment Spray (Stop Time): _________

SAT / UNSAT CRS 1. Ensure the event is being classified.

CRS 2. Enter the EOP entry time.

3. IF pressurizer pressure remains below the SIAS setpoint, THEN perform the following:

Ensure ONE RCP is stopped in each loop.

IF RCS subcooling is less than 24°F, THEN ensure all RCPs are stopped.

4. IF any RCPs are operating, THEN perform Appendix 16, RCP Trip Criteria and check RCP operating limits satisfied.
5. Perform the following:

Ensure that the Steam Generator Sample Valves are open.

BOP Direct Chemistry to perform 74DP-9ZZ05, Abnormal Occurrence Checklist.

ATC 6. Place the Hydrogen Analyzers in service.

7. Identify the success path(s) to be used to satisfy each safety function.

REFER to BOTH of the following:

CRS Section 4.0, Safety Function Tracking Section 6.0, Resource Assessment Trees PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 30 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior Examiner Note: The CRS should jeopardize CTPC-2, Containment Temperature and Pressure Control, and align Train B LPSI for Train B Containment Spray

8. Perform Section 5.0, Safety Function Status Check for those success CRS paths in use.
9. Perform ALL of the following in the order listed:

Success path instructions for those safety functions that are in jeopardy CRS Success path instructions for those safety functions that are challenged Success path instructions for all other non-shaded paths in use Examiner Note: The following steps are from CTPC-2, Containment Temperature and Pressure Control CRS 1. Open the placekeeper

2. IF containment pressure is 8.5 psig or more, THEN check that CSAS is ATC actuated Examiner Note (from FR procedure): There is no indication of CS flow when using a LPSI pump for CS.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

Appendix D Operator Action Form ES-D-2 Operating Test : NRC Scenario # 2 Event # 5, 6, 7, 8, 9 Page 31 of 31 Event

Description:

ESD inside Containment, NAN-S01 and NAN-S02 supply breakers trip on the reactor trip, SIAS/CIAS/MSIS fail to auto actuate, Train A CS flow control valve seized closed, Train B CS Pump shaft shear Time Position Applicants Actions or Behavior

3. IF CSAS actuated, THEN check at least one CS header is delivering 4350 gpm or more 3.1 (CA) IF it is desired to use LPSI Pump A to supply CS A train, AND LPSI Pump A is NOT needed to support any RC, IC, or HR success path, THEN perform the following:
a. Ensure that LPSI Pump A is running
b. Ensure that SIA-HV-306, LPSI Shutdown Cooling Heat Exchanger A Bypass Valve, is closed
c. Ensure that SIA-HV-687, LPSI-Containment Spray From Shutdown Heat Exchanger A Cross-Tie Valve, is open
d. Ensure that SIA-UV-672, Containment Spray A Discharge to Spray Header 1 Valve, is open
e. Ensure SIA-HV-685, LPSI-Containment Spray To Shutdown Heat Exchanger A Cross-Tie Valve, is open ATC
f. Check that the LPSI Pump is running at less than 60 amps 3.2 (CA) IF it is desired to use LPSI Pump B to supply CS B train, AND LPSI Pump B is NOT needed to support any RC, IC, or HR success path, THEN perform the following:
a. Ensure that LPSI Pump B is running
b. Ensure that SIB-HV-307, LPSI Shutdown Cooling Heat Exchanger B Bypass Valve, is closed
c. Ensure that SIB-HV-695, LPSI-Containment Spray From Shutdown Heat Exchanger B Cross-Tie Valve, is open
d. Ensure that SIB-UV-671, Containment Spray B Discharge to Spray Header 2 Valve, is open
e. Ensure SIB-HV-694, LPSI-Containment Spray To Shutdown Heat Exchanger B Cross-Tie Valve, is open
f. Check that the LPSI Pump is running at less than 60 amps Scenario Termination: When the crew has aligned Train B LPSI to supply Train B Containment Spray, or at lead evaluators discretion, the scenario may be terminated.

PVNGS 2016 NRC Exam Scenario # 2 Rev 3

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R1 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R2 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R3 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R4 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R5 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 0 1 1 1 R6 I/C 2,4,7 2,3 5 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R7 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 4 1 1 1 0 NOR 0 1 1 1 R8 I/C 2,4,7 2,3 5 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 4 1 1 1 0 NOR 1 1 2 1 1 1 I/C 3,4,5 3 5 4 4 2 R9 ,8 MAJ 6,9 5,9 4 2 2 1 TS 0 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I1 I/C 2,4,7 2,3,4 6 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 3,4 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I2 I/C 2,4,7 2,3,4 6 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 3,4 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I3 I/C 2,4,7 2,3,4 6 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 3,4 2 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 0 1 1 0 NOR 1 1 1 1 1 I4 I/C 2,4,7 2,3,4 6 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 3,4 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I5 I/C 2,4,7 2,3,4 6 4 4 2 MAJ 6,9 5,9 4 2 2 1 TS 3,4 2 0 2 2 RX 4 1 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 2,3 7 4 4 2 U1 ,7,8 MAJ 6,9 5,9 4 2 2 1 TS 2,5 2 0 2 2 RX 4 1 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 2,3 7 4 4 2 U2 ,7,8 MAJ 6,9 5,9 4 2 2 1 TS 2,5 2 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 4 1 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 2,3 7 4 4 2 U3 ,7,8 MAJ 6,9 5,9 4 2 2 1 TS 2,5 2 0 2 2 RX 4 1 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 2,3 7 4 4 2 U4 ,7,8 MAJ 6,9 5,9 4 2 2 1 TS 2,5 2 0 2 2 RX 4 1 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 2,3 7 4 4 2 U5 ,7,8 MAJ 6,9 5,9 4 2 2 1 TS 2,5 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 5 4 4 2 U6 ,7,8 MAJ 6,9 2 2 2 1 TS 2,5 2 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 - Spare 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 0 1 1 0 NOR 1 1 1 1 1 U7 I/C 2,3,4 3 4 4 2 MAJ 5,9 2 2 2 1 TS 3,4 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 I/C 3,4,5 5 4 4 2 U8 ,7,8 MAJ 6,9 2 2 2 1 TS 2,5 2 0 2 2 RX 0 1 1 0 NOR 1 1 1 1 1 U9 I/C 2,3,4 3 4 4 2 MAJ 5,9 2 2 2 1 TS 3,4 2 0 2 2 RX NOR I/C MAJ TS Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Transient and Event Checklist Form ES-301-5 Facility: PVNGS Date of Exam: 10/28/16 Operating Test No.: 2016 A E Scenarios P V 1 2 3 - Spare 4 T M P E O I L N CREW POSITION CREW POSITION CREW POSITION CREW POSITION T N I T S A B S A B S A B S A B I C A R T O R T O R T O R T O M A T L O C P O C P O C P O C P U N Y M(*)

T P E R I U RX 0 NOR 0 6

CRS I/C 1, 2, 3, 4, (spare) 6, 7 MAJ 5 1 TS 1, 4 2 RX 0 NOR 0 6

ATC I/C 1, 2, 3, 4, (spare) 6, 7 MAJ 5 1 TS 0 RX 0 NOR 0 BOP I/C 1, 2, 4 (spare) 4, 7 MAJ 5 1 TS 0 RX NOR I/C MAJ TS Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.
4. For licensees that use the ATC operator primarily for monitoring plant parameters, the chief examiner may place SRO-I applicants in either the ATC or BOP position to best evaluate the SRO-I in manipulating plant controls.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO 1 RO 2 RO 3 RO 4 SRO-I SRO-I SRO-I SRO-I SRO-U SRO-U SRO-U SRO-U Competencies SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 3,4, 3,4, 3,4, 3,4, 3,4, 3,4, 3,4, 3,4, Events and Conditions 5,8 5,6, 5,8 5,6, 5,8 5,6, 5,8 5,6, 8,9 8,9 8,9 8,9 Comply With and 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, Use Procedures (1) 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 9 9 9 9 9 9 9 9 Operate Control 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, 1,3, Boards (2) 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 4,5, 9 9 9 9 9 9 9 9 Communicate All All All All All All All All and Interact Demonstrate Supervisory Ability (3)

Comply With and Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO 5 RO 6 RO 7 RO 8 SRO-I SRO-I SRO-I SRO-I SRO-U SRO-U SRO-U SRO-U Competencies SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 3,4,5, 3,4, 2,4, 2,3, 3,4, 3,4, 2,4, 2,3, Events and Conditions 8 5,6, 7 4,5, 5,8 5,6, 7 4,5, 8,9 6,7 8,9 6,7 Comply With and 1,3,4, 1,3, 2,4, 2,3, 1,3, 1,3, 2,4, 2,3, Use Procedures (1) 5,9 4,5, 7 4 4,5, 4,5, 7 4 9 9 9 Operate Control 1,3,4, 1,3, 2,4, 2,3, 1,3, 1,3, 2,4, 2,3, Boards (2) 5,9 4,5, 7 4,5, 4,5, 4,5, 7 4,5, 9 7 9 9 7 Communicate All All All All All All All All and Interact Demonstrate Supervisory Ability (3)

Comply With and Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO 9 RO RO RO SRO-I SRO-I 1 SRO-I 2 SRO-I 3 SRO-U SRO-U SRO-U SRO-U Competencies SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 3,4,5, 3,4, 2,4, 5,8 2,4, 5,8 2,4, 5,8 Events and Conditions 8 5,6, 7 7 7 8,9 Comply With and 1,3,4, 1,3, 2,4, 2,3, 2,4, 2,3, 2,4, 2,3, Use Procedures (1) 5,9 4,5, 7 4,9 7 4,9 7 4,9 9

Operate Control 1,3,4, 1,3, 2,4, 2,4, 2,4, Boards (2) 5,9 4,5, 7 7 7 9

Communicate All All All All All All All All and Interact Demonstrate All All All Supervisory Ability (3)

Comply With and 3,4 3,4 3,4 Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO RO RO RO SRO-I 4 SRO-I 5 SRO-I SRO-I SRO-U SRO-U SRO-U 1 SRO-U 2 Competencies SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 2,4,7 5,8 2,4, 5,8 6,9 2,3, 6,9 2,3, Events and Conditions 7 4,5, 4,5, 6,7 6,7 Comply With and 2,4,7 2,3, 2,4, 2,3, 2,3, 2,3, 2,3, 2,3, Use Procedures (1) 4,9 7 4,9 4,5, 4 4,5, 4 7,8, 7,8, 9 9 Operate Control 2,4,7 2,4, 2,3, 2,3, Boards (2) 7 4,5, 4,5, 7 7 Communicate All All All All All All All All and Interact Demonstrate All All All All Supervisory Ability (3)

Comply With and 3,4 3,4 2,5 2,5 Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO RO RO RO SRO-I SRO-I SRO-I SRO-I SRO-U 3 SRO-U 4 SRO-U 5 SRO-U 6 Competencies SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 6,9 2,3, 6,9 2,3, 6,9 2,3, 6,9 Events and Conditions 4,5, 4,5, 4,5, 6,7 6,7 6,7 Comply With and 2,3,4, 2,3, 2,3, 2,3, 2,3, 2,3, 2,3, Use Procedures (1) 5,7,8, 4 4,5, 4 4,5, 4 4,5, 9 7,8, 7,8, 7,8, 9 9 9 Operate Control 2,3, 2,3, 2,3, Boards (2) 4,5, 4,5, 4,5, 7 7 7 Communicate All All All All All All All and Interact Demonstrate All All All All Supervisory Ability (3)

Comply With and 2,5 2,5 2,5 2,5 Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.

ES-301 Competencies Checklist Form ES-301-6 Facility: PVNGS Date of Examination: 10/31/2016 Operating Test No.: 2016 APPLICANTS RO RO RO SRO-I SRO-I SRO-I SRO-U 7 SRO-U 8 SRO-U 9 Competencies SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/Diagnose 5,8 6,9 5,8 Events and Conditions Comply With and 2,3, 2,3, 2,3, Use Procedures (1) 4,9 4,5, 4,9 7,8, 9

Operate Control Boards (2)

Communicate All All All and Interact Demonstrate All All All Supervisory Ability (3)

Comply With and 3,4 2,5 3,4 Use Tech. Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicants license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant. (This includes all rating factors for each competency.) (Competency Rating factors as described on forms ES-303-1 and ES-303-3.