ML13178A363
ML13178A363 | |
Person / Time | |
---|---|
Site: | Perry |
Issue date: | 03/14/2013 |
From: | NRC/RGN-III |
To: | FirstEnergy Nuclear Operating Co |
Bielby, M. | |
Shared Package | |
ML11354A269 | List: |
References | |
Download: ML13178A363 (1) | |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Perry Nuclear Power Plant Date of Examination: Weeks of 2/25 and 3/4/2013 Developed by: Written - Facility NRC // Operating - Facility NRC Target Chief Date* Task Description (Reference) Examiners Initials
-180 1. Examination administration date confirmed (C.1.a; C.2.a and b) meb
-120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) meb
-120 3. Facility contact briefed on security and other requirements (C.2.c) meb
-120 4. Corporate notification letter sent (C.2.d) meb
[-90] [5. Reference material due (C.1.e; C.3.c; Attachment 3)] NA
{-75} 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, meb ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d)
{-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility meb licensee (C.2.h; C.3.e)}
{-45} 8. Proposed examinations (including written, walk-through JPMs, and meb scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d)
-30 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; meb ES-202)
-14 10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; meb ES-202)
-14 11. Examination approved by NRC supervisor for facility licensee review meb (C.2.h; C.3.f)
-14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) meb
-7 13. Written examinations and operating tests approved by NRC supervisor meb (C.2.i; C.3.h)
-7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm meb qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES-202, C.2.e; ES-204)
-7 15. Proctoring/written exam administration guidelines reviewed meb with facility licensee (C.3.k)
-7 16. Approved scenarios, job performance measures, and questions meb distributed to NRC examiners (C.3.i)
- Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.