2013 Perry Nuclear Power Plant Initial License Examination Administrative ES-201-1
ML13178A363
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 03/14/2013
From:
NRC/RGN-III
To:
FirstEnergy Nuclear Operating Co
Bielby, M.
Shared Package
ML11354A269 List:
References
Download: ML13178A363 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Perry Nuclear Power Plant Date of Examination: Weeks of 2/25 and 3/4/2013 Developed by: Written - Facility NRC // Operating - Facility NRC Target Chief Date* Task Description (Reference) Examiners Initials

-180 1. Examination administration date confirmed (C.1.a; C.2.a and b) meb

-120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) meb

-120 3. Facility contact briefed on security and other requirements (C.2.c) meb

-120 4. Corporate notification letter sent (C.2.d) meb

[-90] [5. Reference material due (C.1.e; C.3.c; Attachment 3)] NA

{-75} 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, meb ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d)

{-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility meb licensee (C.2.h; C.3.e)}

{-45} 8. Proposed examinations (including written, walk-through JPMs, and meb scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d)

-30 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; meb ES-202)

-14 10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; meb ES-202)

-14 11. Examination approved by NRC supervisor for facility licensee review meb (C.2.h; C.3.f)

-14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) meb

-7 13. Written examinations and operating tests approved by NRC supervisor meb (C.2.i; C.3.h)

-7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm meb qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES-202, C.2.e; ES-204)

-7 15. Proctoring/written exam administration guidelines reviewed meb with facility licensee (C.3.k)

-7 16. Approved scenarios, job performance measures, and questions meb distributed to NRC examiners (C.3.i)

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.