ML13298A091

From kanterella
Revision as of 12:08, 4 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Change of Schedule Letter for Environmental and Safety Review of Seabrook License Renewal Application
ML13298A091
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 12/16/2013
From: John Lubinski
Division of License Renewal
To: Walsh K
NextEra Energy Seabrook
References
TAC ME3959, TAC ME4028
Download: ML13298A091 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 16, 2013 Mr. Kevin Walsh Site Vice President NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 0387 4

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL AND SAFEY REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NOS. ME3959 AND ME4028)

Dear Mr. Walsh:

By letter dated May 25, 2010, Next Era Energy Seabrook, LLC (NextEra), submitted an application to renew the operating license for Seabrook Station, Unit 1 (Seabrook), for an additional 20 years. In support of the application and in accordance with Title 10 of the Code of Federal Regulations (1 0 CFR) Part 51 and 10 CFR Part 54, Next Era also submitted an environmental report for Seabrook. This letter is to inform you of a change in the environmental and safety review schedule for the Seabrook license renewal review.

Regarding the environmental review, in August 2013, the U.S. Nuclear Regulatory Commission (NRC) staff, NextEra, Friends of the Coast and the New England Coalition reached a settlement agreement regarding resolution of Contention 4D associated with the supplemental environmental impact statement (SEIS). As a result of this agreement NRC staff requires additional time to complete its analysis for inclusion in the final SEIS.

The safety review schedule is being revised because the NRC staff is including a second Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting to discuss the NRC staff's review of the Seabrook revised plant-specific Alkali-Silica Reaction Monitoring Program which NextEra supplemented by letter dated September 13, 2013.

Enclosed is the NRC staff's revised environmental and safety review schedule for the Seabrook license renewal application. The schedule has been updated to reflect a change in the date of issuance for the final SEIS and the addition of an ACRS subcommittee meeting.

K. Walsh If you have any questions on this revised schedule, please contact the NRC's environmental project manager, Ms. Lois James, at 301-415-3306 or by e-mail at lois.james@nrc.gov or the safety project manager, at 301-415-1427 or by e-mail at Richard.Piasse@nrc.gov.

Sincerely, ki, Director Divis1on of Lie nse Renewal Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Revised Seabrook Station Review Schedule cc w/encl: Listserv

K. Walsh If you have any questions on this revised schedule, please contact the NRC's environmental project manager, Ms. Lois James, at 301-415-3306 or by e-mail at lois.james@nrc.gov or the safety project manager, at 301-415-1427 or by e-mail at Richard.Piasse@nrc.gov.

Sincerely, IRA/

John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Revised Seabrook Station Review Schedule cc w/encl: Listserv DISTRIBUTION: See following pages A DAMS Accession No.: ML13298A091 c

  • oncurrence bv e-mail OFFICE LA:DLR* PM:RPB2:DLR OGC PM:RPB1 :DLR BC:RPB1 :DLR NAME IKing LJames BHarris RPiasse YDiaz-Sanabria DATE 11/25/2013 11/04/2013 11/05/2013 11/21/2013 11/21/2013 OFFICE BC:RPB2:DLR D:DLR NAME BWittick JLubinski DATE 12/11/2013 12/16/2013 OFFICIAL RECORD COPY

Letter to Kevin Walsh from John Lubinski dated December 16, 2013

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL AND SAFEY REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAG NOS. ME3959 AND ME4028)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDraApla Resource Listserv Lois.James@nrc.gov Richard. Plasse@nrc.gov Brian.Wittick@nrc.gov Yoira. Diaz-Sanabria@nrc.gov John. Lamb@nrc.gov David.Mclntyre@nrc.gov Eugene. Dacus@nrc.gov Brian. Harris@nrc.gov Glenn. Dental@nrc.gov Paul. Cataldo@nrc.gov Chris. Newport@nrc.gov Jasmine. Gilliam@nrc.gov Nancy.McNamara@nrc.gov Doug. Tiff@nrc.gov Neii.Sheehan@nrc.gov Diane.Screnci@nrc.gov

SEABROOK STATION LICENSE RENEWAL APPLICATION UPDATED REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 6/01/10 6/01/10 Publish Federal Register notice (FRN) - LRA availability 6/14/10 6/16/10 Publish FRN - acceptance/rejection and opportunity for hearing 7/23/10 7/21/10 Publish FRN - intent to conduct environmental seeping 7/23/10 7/10/10 Public Meeting - License Renewal Overview and Environmental Seeping 8/19/10 8/19/10 Meeting Deadline for filing hearing requests and petitions for intervention 9/20/10 10/20/10 Environmental seeping period ends 9/21/10 9/21/10 Audit - environmental 10/04/10 10/05/10 Issue draft supplemental environmental impact statement (SEIS) 8/2011 8/01/11 Publish FRN - draft SEIS available for comments 8/2011 8/12/11 Public Meeting -draft SEIS meeting 9/2011 9/15/11 End of draft SEIS comment period 11/2011 10/26/11 Issue safety evaluation report (SER) with open items 6/2012 6/08/12 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Meeting 7/2012 7/10/12 Issue draft supplement to the Seabrook Station (Seabrook) draft SEIS 4/2013 4/2013 Publish FRN -draft supplement to the Seabrook draft SEIS available for comments. 4/2013 4/2013 Proposed Second ACRS Subcommittee Meeting TBD Issue Final SER TBD IACRS Full Committee Meeting TBD End of comment period on the draft supplement to the Seabrook draft SEIS 6/2013 6/2013 Issue final SEIS 7/2014 Decision - Director, Office of Nuclear Reactor Regulation TBD Commission decision TBD ENCLOSURE