HNP-15-064, Submits 90-day Inservice Inspection Summary Report

From kanterella
Revision as of 09:23, 31 October 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Submits 90-day Inservice Inspection Summary Report
ML15217A561
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 08/05/2015
From: Brewer H
Duke Energy Progress
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
HNP-15-064
Download: ML15217A561 (6)


Text

HNP-15-064 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/RENEWED LICENSE NO. NPF-63 Enclosure 90-day Inservice Inspection Summary Report (5 pages including cover)

Summary The Shearon Harris Nuclear Power Plant Unit 1 Third Ten Year Inservice Inspection (ISI) Plan complies with 10CFR50.55a(g), which implements, by reference, the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, 2001 Edition with 2003 Addenda.

This summary report is being submitted pursuant to the reporting requirements of ASME Section XI as amended by ASME Code Case N-532-4, Repair/Replacement Activity Documentation Requirements and Inservice Summary Report Preparation and Submission Section XI, Division 1.

Contained within this summary report are the form OAR-1 (Owners Activity Report) and Tables 1 and 2 of Code Case N-532-4 for Harris Nuclear Plant during cycle 19 and Refueling Outage 19 (RFO-19). RFO-19 is the first of two outages of the third period in the third inspection interval and includes the Repair/Replacement activities from February 12, 2014 to May 15, 2015.

1