February 8, 2007 Mr. Alexander Marion Nuclear Energy Institute
1776 I Street, NW, Suite 400
Washington, DC 20006-3708
SUBJECT:
PROPOSED LICENSE RENEWAL INTERIM STAFF GUIDANCE LR-ISG-2006-02: STAFF GUIDANCE ON ACCEPTANCE REVIEW FOR
ENVIRONMENTAL REPORTS FOR LICENSE RENEWAL APPLICATIONS
Dear Mr. Marion:
The purpose of this letter is to provide you with an opportunity to comment on the proposed License Renewal Interim Staff Guidance (LR-ISG) 2006-02 (Enclosure) on the acceptance
review criteria for environmental reports submitted with applications for reactor license renewal.
This LR-ISG summarizes the Title 10 of the Code of Federal Regulations Part 51 (10 CFR Part 51) requirements for environmental reports submitted with license renewal
applications in a checklist format that will be used by the U.S. Nuclear Regulatory Commission (NRC) staff to verify the completeness of these reports.
This proposed LR-ISG does not convey a change in the NRC's regulations or how they are being interpreted. It is being provided to assist future applicants in preparing environmental
reports that are submitted with license renewal applications. As such, we are interested in
receiving comments on the proposed LR-ISG. The staff plans to incorporate this guidance into
a future update of NUREG-1555, Standard Review Plans for Environmental Reviews forNuclear Power Plants, Supplement 1: Operating License Renewal
. Because this LR-ISG provides documentation of the existing acceptance review practice in accordance with existing regulations, the staff did not perform a backfit evaluation.
A. Marion A notice relating to this proposed LR-ISG will be published in the Federal Register. The staff is requesting your comments on the proposed LR-ISG as indicated in the Federal Register Notice. If you have any questions regarding this matter, please contact Ms. Jennifer Davis, by
telephone at 301-415-3835 or by e-mail at jxd10@nrc.gov
.An identical letter was sent to Mr. David Lochbaum of the Union of Concerned Scientists for comment. Sincerely, /RA/Pao-Tsin Kuo, Acting Director Division of License Renewal
Office of Nuclear Reactor Regulation Project No. 690
Enclosure:
As stated cc w/encl: See next page A. Marion A notice relating to this proposed LR-ISG will be published in the Federal Register. The staff is requesting your comments on the proposed LR-ISG as indicated in the Federal Register Notice. If you have any questions regarding this matter, please contact Ms. Jennifer Davis, by
telephone at 301-415-3835 or by e-mail at jxd10@nrc.gov
.An identical letter was sent to Mr. David Lochbaum of the Union of Concerned Scientists for comment. Sincerely, /RA/Pao-Tsin Kuo, Acting Director Division of License Renewal
Office of Nuclear Reactor Regulation Project No. 690
Enclosure:
As stated cc w/encl: See next pageAdams Accession Nos. Package:
ML063190421 Letter: ML063190440 FRN: ML063190464 Checklist:
ML063190452OFFICELA:DLRPM:DLRPM:DLRPM:DLRNAME SFigueroaJDavisRSchaafLTran DATE11/17/0611/08/0611/13/0612/12/06 OFFICEOGCBC:DLRBC:DLRD:DLR NAMEJMortina NLO w/edits BPham for RFranovichRAuluckPTKuo DATE 12/21/0612/27/0601/03/0702/08/07 OFFICIAL RECORD COPY February 8, 2007 Mr. David Lochbaum Union of Concerned Scientists
1707 H Street, NW, Suite 600
Washington, DC 20006-3919
SUBJECT:
PROPOSED LICENSE RENEWAL INTERIM STAFF GUIDANCE LR-ISG-2006-02: STAFF GUIDANCE ON ACCEPTANCE REVIEW FOR
ENVIRONMENTAL REPORTS FOR LICENSE RENEWAL APPLICATIONS
Dear Mr. Lochbaum:
The purpose of this letter is to provide you with an opportunity to comment on the proposed License Renewal Interim Staff Guidance (LR-ISG) 2006-02 (Enclosure) on the acceptance
review criteria for environmental reports submitted with applications for reactor license renewal.
This LR-ISG summarizes the Title 10 of the Code of Federal Regulations Part 51 (10 CFR Part 51) requirements for environmental reports submitted with license renewal
applications in a checklist format that will be used by the U.S. Nuclear Regulatory Commission (NRC) staff to verify the completeness of these reports.
This proposed LR-ISG does not convey a change in the NRC's regulations or how they are being interpreted. It is being provided to assist future applicants in preparing environmental
reports that are submitted with license renewal applications. As such, we are interested in
receiving comments on the proposed LR-ISG. The staff plans to incorporate this guidance into
a future update of NUREG-1555, Standard Review Plans for Environmental Reviews forNuclear Power Plants, Supplement 1: Operating License Renewal
. Because this LR-ISG provides documentation of the existing acceptance review practice in accordance with existing regulations, the staff did not perform a backfit evaluation.
D. Lochbaum A notice relating to this proposed LR-ISG will be published in the Federal Register. The staff is requesting your comments on the proposed LR-ISG as indicated in the Federal Register Notice. If you have any questions regarding this matter, please contact Ms. Jennifer Davis, by
telephone at 301-415-3835 or by e-mail at jxd10@nrc.gov
.An identical letter was sent to Mr. Alexander Marion of the Nuclear Energy Institute for comment. Sincerely, /RA/Pao-Tsin Kuo, Acting Director Division of License Renewal
Office of Nuclear Reactor Regulation Project No. 690
Enclosure:
As stated cc w/encl: See next page Letter to A. Marion and (identical sent to D. Lochbaum) from P.T. Kuo, dated February 8, 2007
SUBJECT:
PROPOSED LICENSE RENEWAL INTERIM STAFF GUIDANCE LR-ISG-2006-02: STAFF GUIDANCE ON ACCEPTANCE REVIEW FOR
ENVIRONMENTAL REPORTS ASSOCIATED WITH LICENSE RENEWAL
APPLICATIONS DISTRIBUTION
- HARD COPY:
DLR RF R. Schaaf L. Tran E-MAIL: PUBLIC RidsNrrOd RidsNrrAdro
RidsNrrAdra
RidsNrrAdes
RidsNrrDlr
RidsNrrDra
RidsNrrDnrl
RidsNrrDlrRebb
RidsNrrDlrReba
DLR Staff PROPOSED LICENSE RENEWAL INTERIM STAFF GUIDANCE LR-ISG-2006-02:
STAFF GUIDANCE ON ACCEPTANCE REVIEW FOR ENVIRONMENTAL REPORTS ASSOCIATED WITH LICENSE RENEWAL APPLICATIONS Introduction Each applicant for renewal of a license to operate a nuclear power plant is required to submit with its application a separate environmental report (ER) in accordance with Title 10 of the Code of Federal Regulations (10 CFR 54.23). As stated in 10 CFR 54.23, the ER must comply with the requirements of Subpart A of 10 CFR Part 51. The requirements governing the contents of
an ER submitted at the operating license renewal stage are specified in 10 CFR 51.45 and 10
CFR 51.53(c). This License Renewal Interim Staff Guidance (LR-ISG) is being proposed to
document the staff's practice in performing an acceptance review of ERs submitted as part of a
Background and Discussion The NRC staff routinely reviews ERs against the requirements of 10 CFR 51.45 and 10 CFR 51.53(c) as part of the acceptance review of reactor license renewal applications. Staff
review guidance governing reactor license renew al environmental reviews and the preparation of environmental impact statements is provided in NUREG-1555, Standard Review Plans forEnvironmental Reviews for Nuclear Power Plants, Supplement 1: Operating License Renewal. In conducting its acceptance review, the staff also relies on the guidance provided to applicants in Regulatory Guide 4.2, Supplement 1, Preparation of Supplemental Environmental Reports for Applications to Renew Nuclear Power Plant Operating Licenses. The regulatory guide provides methods acceptable to the staff for implementing the provisions of 10 CFR 51.45 and
10 CFR 51.53(c). While conformance with the suggested format of the regulatory guide is not
required, use of the guide is expected to ensure the completeness of the information provided, assist the NRC staff and others in locating information, and result in more efficient and timely
NRC staff review.
Proposed Action The acceptance review checklist for ERs submitted with license renewal applications, available via ADAMS at Accession No. ML063190452, will be incorporated into the next revision of
NUREG-1555, Supplement 1. The acceptance checklist is intended to be a tool to ensure
efficiency and consistency in the staff's acceptance reviews and ensure that all necessary
components of license renewal stage ERs are submitted in accordance with governing regulations. As noted in the checklist instructions, the absence of any of the information
recommended in Regulatory Guide 4.2, Supplement 1, would not require that supplemental
information be provided prior to acceptance of an application; however, applicants should
expect that the absence of such information may result in more intensive environmental audit
activities and/or issuance of early requests for additional information to support the staff's
review. The docketing and subsequent finding of a timely and sufficient application (including
the ER) does not preclude NRC reviewers from requesting additional information as a review
proceeds, nor does it predict the NRC's final determination regarding the approval or denial of a
license renewal application. This proposed LR-ISG is not intended to substitute or re-interpret
requirements outlined in 10 CFR 51.45 and 10 CFR 51.53(c). The checklist is expected to
serve as a knowledge management tool for NRC sta ff members by specifying review criteria in a simplified, user-friendly format.
Enclosure NUCLEAR ENERGY INSTITUTE Project No. 690
cc:
Ms. Christine S. Salembier, Commissioner State Liaison Officer
Department of Public Service
112 State St., Drawer 20
Montipelier, VT 05620-2601Mr. James Ross Nuclear Energy Institute
1776 I St., NW, Suite 400
Washington, DC 20006-3708 Mr. Frederick W. Polaski Manager License Renewal
Exelon Corporation
200 Exelon Way
Kennett Square, PA 19348 Mark Ackerman Project Manager, License Renewal
FirstEnergy Nuclear Operating Company
P.O. Box 4
Route 168 (Mail Stop BV-SGRP)
Shippingport, PA 15077 Mr. Paul Gunter, Director Reactor Watchdog Project
Nuclear Information & Resource Service
6930 Carroll Avenue, Suite 340
Takoma Park, MD 20912 Mr. Hugh Jackson Public Citizen's Critical Mass Energy
& Environment Program
215 Pennsylvania Ave., SE
Washington, DC 20003Mary Olson Nuclear Information & Resource Service
Southeast Office
P.O. Box 7586
Asheville, NC 28802 Talmage B. Clements Manager - License Renewal Progress Energy
P.O. Box 1551
Raleigh, NC 27602 Mr. Garry G. Young Manager, License Renewal Services
1448 SR 333, N-GSB-45
Russellville, AR 72802 Mr. William Crough, Manager Licensing and Regulatory Affairs
Browns Ferry Nuclear Plant
Tennessee Valley Authority
P.O. Box 2000
Decatur, AL 35609 Robert A. Vincent Licensing Lead - License Renewal Project
Palisades Nuclear Plant
27780 Blue Star Memorial Highway
Covert, MI 49043