MONTHYEARIR 05000341/20224012022-03-21021 March 2022 Security Baseline Inspection Report 05000341/2022401 IR 05000341/20214022021-12-0909 December 2021 Security Baseline Inspection Report 05000341/2021402 IR 05000341/20215012021-10-21021 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2021501 IR 05000341/20164062016-07-14014 July 2016 Cyber Security Problem and Identification Inspection Report 05000341/2016406 - Cover Letter Only IR 05000341/20155012016-02-0303 February 2016 NRC Emergency Preparedness Annual Inspection Report No. 05000341/2015501 IR 05000034/20104052010-02-17017 February 2010 Cover Letter for IR Fermi 2 Nuclear Power Station - NRC ISFSI Security Inspection Report 0500034/2010405(DNMS) ML0909103282009-04-0101 April 2009 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000341-09-004 IR 05000016/20080092008-09-24024 September 2008 IR 05000016-08-009, on 08/27/2008 & 08/28/2008, Enrico Fermi Unit 1, Routine Decommissioning Inspection Included Reviews of Facility Management and Control, and Radiological Safety IR 05000341/20075012008-02-14014 February 2008 IR 05000341-07-501, and IR 05000341-07-403, on 12/31/2007, for Fermi, Emergency Preparedness Annual and Security Annual Inspection Report IR 05000341/20060122006-09-12012 September 2006 IR 05000341-06-012 Cover Letter IR 05000341/20020022002-03-0404 March 2002 IR 05000341/2002-002(DRP), Detroit Edison Company, Fermi 2 Nuclear Power Station, on 12/30/2001- 02/15/2002. No Violations Issued IR 05000341/20010172002-01-16016 January 2002 IR 05000341/2001-017(DRP), Detroit Edison Company, Fermi 2 Nuclear Power Station, Inspection on 11/17-12/29/2001 Re Maintenance Risk Assessments and Emergent Work Evaluation. Two Noncited Violations 2022-03-21
[Table view] Category:Letter
MONTHYEARIR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23243A9432023-12-0606 December 2023 Closeout Letter to DTE Regarding 2017, 2020 and 2023 Updated DFPs for Fermi 2 ISFSI IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) 2024-09-09
[Table view] |
Inspection Report - - 2010405 ( Security) |
---|
|
|
Text
ary 17, 2010
SUBJECT:
FERMI 2 NUCLEAR POWER STATION - NRC ISFSI SECURITY INSPECTION REPORT 05000341/2010405(DNMS)
Dear Mr. Davis:
On January 27, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection of the Independent Spent Fuel Storage Installation (ISFSI) at the Fermi 2 Nuclear Power Station (NPS), Newport, Michigan. The purpose of the inspection was to evaluate whether the protection of the ISFSI was in compliance with the Fermi 2 Physical Security Plan (PSP) and the NRC Order EA-09-072, "Issuance of Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for Fermi Power Plant Independent Spent Fuel Storage Installation," dated April 7, 2009. In addition, the inspectors verified the location of your instrument calibrators, and determined whether their use and storage was conducted safely and in accordance with 10 CFR Part 20 requirements. At the conclusion of the on-site inspection on January 27, 2010, the inspector discussed the inspection findings with members of your security and radiation protection staff.
Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related discussion contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
Enclosure Contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled.
Official Use Only Security-Related Information Official Use Only Security-Related Information We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/ Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch
Docket No. 050-00341, 072-00071 License No. NPF-43, General License (ISFSI)
Enclosure:
IR 05000341/2010405 (DNMS) (Non Public)
cc w/encl: M. Finley, Security Manager, Fermi 2 NPS J. Slaback, Licensing Engineer, Fermi 2 NPS T. Strong, State Liaison Officer, State of Michigan
cc w/o encl: Distribution via ListServ