MONTHYEARML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24257A0582024-09-26026 September 2024 Summary of August 1, 2024, Hybrid Public Meeting on the Potential Palisades Nuclear Plant Restart ML24212A0592024-08-0606 August 2024 May 15, 2024, Summary of Meeting with Holtec Decommissioning International,Llc Regarding LAR to Approve Biasi Critical Heat Flux Correlation for Use with Main Steam Line Break Analysis to Support Potential Reauthorization of Power Operation ML24166A2912024-06-25025 June 2024 April 29, 2024, Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a Quality Assurance Program Manual to Support Potential Reauthorization of Power Operations at Palisades Nuclear Plant ML24141A0632024-05-23023 May 2024 Summary of April 17, 2024, Hybrid Public Outreach Meeting ML24089A2472024-04-0808 April 2024 March 18, 2024, Summary of Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Proposed Emergency Plan for Resumption of Power Operations at the Palisades Nuclear Plant ML24051A0942024-02-27027 February 2024 Summary of February 6, 2024, Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Technical Specifications Administrative Controls and Quality Assurance Program ML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21012A0382021-01-14014 January 2021 December 8, 2020, Summary of Public Teleconference with Entergy Nuclear Operations Inc. Regarding Pre-submittal of a License Transfer Application to Holtec International for Palisades Nuclear Plant ML20309A2372020-11-0606 November 2020 Summary of Public Teleconference with Entergy Nuclear Operations, Inc. to Discuss Future Request for One-Time Exemption from Certain Requirements of 10 CFR 50, Appendix E, Section Iv.F. at Palisades Nuclear Plant (EPID L-2020-LRM-0091 ML20304A1442020-11-0202 November 2020 Summary of September 21, 2020, Public Teleconference with Entergy Nuclear Operations Inc. Regarding a Proposed Alternative for Repair of Reactor Vessel Head Penetrations for Palisades Nuclear Plant ML20280A6952020-10-13013 October 2020 Letter - Palisades Nuclear Plant- Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant EPID L-2020-LRO-0051 ML20280A6962020-10-13013 October 2020 20200912 NRC Mid Outage Q and a for Phone Call for Palisades 1R27 (Revised) ML20280A6972020-10-13013 October 2020 20200910 NRC Mid Outage Q and a for Phone Call for Palisades 1R27-Entergy Responses ML20231A2202020-08-17017 August 2020 Summary of Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML19296D0632019-11-0101 November 2019 August 2019 Palisades NEIMA 108 Public Meeting Summary ML19136A2552019-05-16016 May 2019 Summary of the Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML18351A2382018-12-18018 December 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant ML18340A0072018-12-0606 December 2018 Summary of Call with Entergy Nuclear Operations, Inc. - Verbal Authorization of Request for Alternative for the Repair of Reactor Vessel Closure Head Penetrations ML18268A2802018-09-26026 September 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18008A2302018-01-10010 January 2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant ML17335A0262017-12-0505 December 2017 Summary of November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Confomances ML17338B0502017-12-0505 December 2017 Summary of November 28, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding a Potential Request Associated with an Alternative to the Reexamination Frequency for a Relevant Condition ML17227A2742017-08-14014 August 2017 Summary of the July 26, 2017, Public Meeting Regarding Palisades Nuclear Plant ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17164A3112017-06-27027 June 2017 Summary of 06/12/2017, Pre-Submittal Meeting with Entergy Nuclear Operations, Inc. to Discuss Palisades Nuclear Plant Post Shutdown Emergency Plan and Administrative Technical Specification License Amendment Request ML17160A1812017-06-14014 June 2017 Summary of Conference Call with Palisades Nuclear Plant Regarding the Spring 2017 Steam Generator Inspections ML17080A1492017-03-23023 March 2017 Summary of March 20, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Cyber Security Plan Implementation Schedule ML16344A0862016-12-20020 December 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding National Fire Protection Association Standard 805 ML16277A6772016-10-11011 October 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Proposed Closure Plant for Generic Safety Issue 191, Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance ML16182A5142016-06-30030 June 2016 Summary of the June 23, 2016, Public Meeting Regarding Palisades Nuclear Plant ML16127A1722016-05-0505 May 2016 6/23/16 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Palisades Nuclear Plant Performance for the 2015 Calendar Year ML16035A4252016-03-0101 March 2016 Summary of January 25, 2016, Pre-Application Teleconference Meeting with Entergy Nuclear Operations to Discuss a Forthcoming License Amendment Request Regarding Steam Generator Cold Leg Alternate Repair Criteria at Palisades Nuclear Plant ( ML15294A2972015-10-27027 October 2015 Steam Generator Tube Inspection Discussion During Palisades 2015 (RF24) Outage (Preliminary Information) ML15294A2922015-10-27027 October 2015 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2015 Steam Generator Inspections ML15272A0652015-09-30030 September 2015 Summary of Telephone Conference on September 28, 2015, Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15261A0392015-09-21021 September 2015 September 17, 2015, Summary of Telephone Conference Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15119A0442015-05-0606 May 2015 Summary of April 14, 2015, Meeting with Entergy Nuclear Operations, Inc. on Plans for Volumetric Examinations of Primary Coolant System Alloy 600 Welds ML15118A0352015-04-27027 April 2015 Meeting Summary with Public to Discuss the 2014 Annual Assessment Results for Palisades Nuclear Plant 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2010
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
On May 11, 2010, the Nuclear Regulatory Commission (NRC) held a public meeting at the Holiday Inn Express Conference Room in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representativ es to discuss the NRC's assessment of the safety performance of Palisades Nuclear Plant for the period from January 1, 2009, through December 31, 2009. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML101040711 and ML101300433, respectively.
The NRC began the meeting with an overview of the NRC's Mission, the Reactor Oversight Process (ROP), national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC's assessment of Palisades performance in 2009, which was documented in the March 3, 2010, End-Of-Cycle assessment letter (ML100610274).
The licensee then provided a response to the NRC's assessment. The licensee presentation can be found in the ADAMS as ML101330508. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Several members of the public asked questions that covered the emergency plan, ground water monitoring, spent fuel, reactor head and steam generator replacements, and license renewal. A list of principal meeting attendees can be found in the attached enclosure.
/RA/
John B. Giessner, Chief Branch 4 Division of Reactor Projects
Docket No. 50-255;72-007 License No. DPR-20
Enclosure:
As Stated
cc w/encl: Distribution via ListServ
PUBLIC MEETING PRINCIPAL ATTENDEES May 11, 2010
Nuclear Regulatory Commission
S. West, Director, Division of Reactor Projects, RIII J. Giessner, Branch Chief, Division of Reactor Projects, RIII J. Ellegood, Senior Resident Inspector, Palisades T. Taylor, Resident Inspector, Palisades E. Duncan, Chief, Plant Support Branch, Division of Reactor Safety, RIII
C. Lipa, Chief, Materials Control, ISFSI, and Decommissioning Branch, Division of Nuclear Materials Safety, RIII J. Cassidy, Senior Health Physicist, Division of Reactor Safety, RIII F. Tran, Reactor Engineer, Division of Reactor Projects, RIII M. Chawla, Project Manager, Office of Nuclear Reactor Regulation V. Mitlyng, Senior Public Affairs Officer, RIII C. Hernandez, Resident Office Assistant, Palisades
Entergy Nuclear Operations, Inc.
C. Schwarz, Site Vice President T. Kirwin, Plant Manager A. Blind, Entergy D. Hamilton, Entergy M. Savage, Entergy K. Madden, Entergy
Other Attendees
T. Davis, Public
D. Rozanski, Public J. Bredeweg, Don't Waste Michigan C. Lowe, IGE - Don't Waste Michigan F. Jason, Don't Waste Michigan M. Merla B. Burr, City of South Haven
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2010
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
On May 11, 2010, the Nuclear Regulatory Commission (NRC) held a public meeting at the Holiday Inn Express Conference Room in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representativ es to discuss the NRC's assessment of the safety performance of Palisades Nuclear Plant for the period from January 1, 2009, through December 31, 2009. The meeting notice and NRC presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML101040711 and ML101300433, respectively.
The NRC began the meeting with an overview of the NRC's Mission, the Reactor Oversight Process (ROP), national ROP results, and the Action Matrix in general. This was followed by a
discussion of the NRC's assessment of Palisades performance in 2009, which was documented in the March 3, 2010, End-Of-Cycle assessment letter (ML100610274).
The licensee then provided a response to the NRC's assessment. The licensee presentation can be found in the ADAMS as ML101330508. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Several members of the public asked questions that covered the emergency plan, ground water monitoring, spent fuel, reactor head and steam generator replacements, and license renewal. A list of principal meeting attendees can be found in the attached enclosure.
/RA/ John B. Giessner, Chief Branch 4 Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20
Enclosure:
As Stated
cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2009\EOC Letters\EOC Meeting Summaries\Palisades EOC 09 Public Meeting Summary.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME FTran:dpt JGiessner DATE 05/19/2010 05/21/2010 OFFICIAL RECORD COPY Letter to Entergy Nuclear Operations, Inc. from J. Giessner dated May 21, 2010.
SUBJECT:
SUMMARY
OF THE MAY 11, 2010, PUBLIC MEETING TO DISCUSS THE 2009 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT
DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-1 RidsNrrPMPalisades Resource
RidsNrrDirsIpab Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource