MONTHYEARML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station ML24229A0472024-08-27027 August 2024 Letter and Safety Evaluation Report for Revision 31 to PGE-8010 Trojan Quality Assurance Program L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage ML24115A2542024-05-13013 May 2024 Request for Additional Information for Trojan Docket No. 72-0017, PGE-8010, Trojan ISFSI Quality Assurance Program, Revision 31 ML24099A1522024-05-0303 May 2024 Trojan Independent Spent Fuel Storage Installation Part 73 Exemption IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24274A1482024-09-30030 September 2024 NRR E-mail Capture - Davis-Besse - RAI Re Relief Request L-23-214 ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station ML24204A0012024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information Vistraops Fleet Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Reports ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24115A2542024-05-13013 May 2024 Request for Additional Information for Trojan Docket No. 72-0017, PGE-8010, Trojan ISFSI Quality Assurance Program, Revision 31 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information ML23033A0322023-02-0101 February 2023 NRR E-mail Capture - Request for Additional Information for Davis-Besse's 2022 Steam Generator Inspection Report (L-2022-LRO-0115) ML22357A0302022-12-23023 December 2022 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000346/2023010 ML22266A1102022-09-23023 September 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding July 21, 2022, Request for Withholding Information from Public Disclosure ML22214A7042022-08-0202 August 2022 Reissue - Davis-Besse Nuclear Power Station, Unit 1 Notification of Nrc Fire Protection Team Inspection Request for Information: Inspection Report 05000346/2022011 ML22187A0992022-07-0606 July 2022 Notification of NRC Supplemental Inspection (95001) and Request for Information ML22164A8572022-06-13013 June 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan ML22118A6862022-04-28028 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML22112A1092022-04-22022 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building ML22055A0872022-02-23023 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Relief Request RP-3 IR 05000346/20210912021-12-17017 December 2021 NRC Inspection Report (05000346/2021091) Preliminary Greater than Green Finding ML21321A3792021-11-16016 November 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML21301A0992021-10-28028 October 2021 Draft Request for Additional Information: Proposed Alternate for Examination of Steam Generator Welds - Energy Harbor Nuclear Corp., Davis-Besse Nuclear Power Station, Unit No. 1 ML21203A3252021-07-28028 July 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000346/2021011 ML21155A1952021-06-0404 June 2021 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Davis Besse Nuclear Power Station ML21041A5452021-02-10010 February 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Steam Generator Tube Inspection Reports ML21007A3732021-01-0707 January 2021 NRR E-mail Capture - (External_Sender) (External) Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, ML21004A1442020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff ML20300A5592020-10-27027 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML20154K7642020-06-0202 June 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425 ML20133J9792020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML20021A3162020-01-21021 January 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request to Revise Containment Leakage Rate Testing ML19192A2222019-07-18018 July 2019 Request for Additional Information Regarding Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML19179A1382019-06-28028 June 2019 NRR E-mail Capture - Davis-Besse - Request for Additional Information Regarding the Decommissioning Quality Assurance Program ML19164A1532019-06-13013 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Post-Shutdown Emergency Plan ML19162A3922019-06-11011 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications ML19143A0732019-05-29029 May 2019 FENOC Fleet - Beaver Valley, Units 1 and 2; Davis-Besse, Unit 1, Perry, Unit 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action; Application for Order Consenting to License Transfer and Conforming Amendments ML19035A6112019-02-0404 February 2019 Enclosurai (Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) ML18305B0192018-11-0101 November 2018 18 Davis-Besse Nuclear Power Station - Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information(Rdb) ML18201A4122018-07-19019 July 2018 NRR E-mail Capture - Davis-Besse - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 ML18190A4902018-07-0909 July 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team), Inspection Report 05000346/2018011 (DRP-DXB) ML18113A3392018-04-23023 April 2018 Enclosurai (Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) ML18113A3412018-04-23023 April 2018 Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) ML18102B0852018-04-12012 April 2018 NRR E-mail Capture - Follow-up Request for Additional Information (RAI) FENOC FLEET-- Exemption Request for a Physical Barrier Requirement for Beaver ML18094A4872018-04-0303 April 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation) ML18043A0102018-02-0909 February 2018 NRR E-mail Capture - FENOC--MG0010-MG0011, MG-0012, MG0013-- Request for Additional Information (RAI) - Exemption Request Security Barrier in Physical Plans ML17355A3722017-12-21021 December 2017 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 ML17303B1582017-11-0707 November 2017 FENOC-Beaver Valley Power Station, Units 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, Perry Nuclear Power Plant Unit 1 - Generic Letter 2016-01, Request for Supplemental Information ML17257A1402017-09-14014 September 2017 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt NFPA 805 ML17135A3612017-05-12012 May 2017 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000346/2017010 (Jvb) 2024-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532
-4352 May 28, 2015 Mr. Raymond Lieb Site Vice President FirstEnergy Nuclear Operating Co.
Davis-Besse Nuclear Power Station 5501 N. State Rte. 2, Mail Stop A
-DB-3080 Oak Harbor, OH 43449
-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION
- INFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION
Dear Mr. Lieb:
This letter is to request information to support the Emergency Action Level and Emergency Plan change inspection that will be conducted during the third quarter of 2015.
This ins pection will be performed as an in-office review
, and in accordance with the U.S. Nuclear Regulatory C ommission (NRC) baseline inspection procedure IP 71114.04.
In the past, this inspection was conducted at the end of the calendar year
, and all requests were made informally to your staff. However, in order to increase efficiency and timeliness of the review; and, promote consistency of document requests across the sites, this request is being sent to all operating reactor licensees in Region III.
The list of requested documents needed for this inspection from each site is enclosed. We are requesting that these documents are for the time period specified in the list, as applicable.
The point of contact for this request is Ms. Michelle Garza, Region III Emergency Preparedness Inspector , and can be reached at (630) 829-9719. We will keep in close communications with the Emergency Preparedness staff at your site regarding this request , and the inspection when performed.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/
Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-346;72-017 License No. NPF
-3
Enclosure:
Emergency Action Level and Emergency Plan Changes Inspection Document Request cc w/encl: Distribution via LISTSERV
EMERGENCY ACTION L EVEL AND EMERGENCY PLAN CHANGES INSPECTION DOCUMENT REQUEST We request that all information listed below be received no later than July 17, 2015. The information is preferred electronically on a CD
-ROM. Send the information requested to the NRC Region III office:
U.S. NRC Region III Attn: Michelle Garza, DRS 2443 Warrenville Road
, Suite 210 Lisle, I L 60532-4352 Documents Requested:
- 1. Current revision of the Emergency Plan
- 2. Current Emergency Action Level (EAL) scheme 3. Most recent NRC
-approved Emergency Plan and E AL 4. On Shift Staffing Analysis baseline
- 5. Most recent Evacuation Time Estimate
- 6. Governing site document for Title 10 , Code of Federal Regulation (CFR) Part 50.54(q) evaluation process
- 7. Title 10 CFR 50.54(q) evaluator training program and qualification records
- 8. Title 10 CFR 50.54(q) evaluations that were completed between Oct ober 31, 2014 and June 30, 2015 9. For each change evaluation, the previous documents and proposed documents, and the associated 50.54(q) screen and evaluation (if performed)
- 10. Corrective Action Program entries related to E AL and Emergency Plan changes dated between October 31, 2014 and June 30, 2015.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/
Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-346;72-017 License No. NPF-3
Enclosure:
Emergency Action Level and Emergency Plan Changes Inspection Document Request cc w/encl: Distribution via LISTSERV DISTRIBUTION w/encl
- Kimyata MorganButler RidsNrrDorlLpl3
-2 Resource RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15149A376 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MGarza:cl SOrth DATE 05/13/15 05/28/15 OFFICIAL RECORD COPY